Labour Statement

State: Odisha District: Kandhamal Block: Raikia Gram Panchayat: Beredakia
Work Code: OD/359/3431/275320/417543/00067390 (IMP OF KALYAN MANDAP AT BEREDAKIA, BEREDAKIA GP)
Project Category: Building
Financial Year: 2021-22 Execution Level: ps
Executing Agency: Panchayat Samiti, Raikia Bill Status: Final Bill
Proposal Date: 22-05-2021 Date of Commencement: 11-12-2025
Date of Completion: 16-12-2025 Scheme Name: SFC Devolution of Fund
Scheme Component Name: 5TH SFC DEVOLUTION GRANT TO PANCHAYAT SAMITI Project Sub-Category: Kalyan Mandap
Project Type: Upgradation or Improvement Name of Executant: MR SUBHENDU KUMAR PRADHAN
Administrative Approval Details
Approval No.: OD/359/3431/275320/417543/00067390/AS
Technical Sanction Details
Technical Sanction No.: OD/359/3431/275320/417543/00067390/TS
Fund Sanction No.: 1093
Fund Sanction Amount (in Rs.): 201919
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Highly-Skilled
Rs. 462 Rs. 562 Rs. 612
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 0.283168 Cubic Meter 0.516 0.146114688 - - - -
2 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 0.283168 Cubic Meter 4.6 1.3025728 0.68 0.19255424 - -
4 Roofing (AR1132) : Supplying, feeting & fixing of G.C.I. Sheet (0.30mm thick) in roof drilling hole in wind ties - Supplying, fitting & fixing of G.C.I. Sheet (0.30mm thick) in roof drilling hole in wind ties including fixing of ridges valleys wind ties etc. including cost of fitting, Labour and material etc. complete as per direction of Engineer-in-Charge 49.424396 Square Meter 0.21505376344086 10.628902365591 - - 0.16129032258065 7.9716767741935
Total Qty 12.077589853591 0.19255424 7.9716767741935
Rate Per Man Day 462 562 612
Total Amount 5579.8465123592 108.21548288 4878.6661858065
Total Labour Amount (in Rs.): 10566.728181046