Labour Statement

State: Odisha District: Jajpur Block: Bari Gram Panchayat: Bainsiria
Work Code: OD/356/3395/118278/402007/00070524 (Repairing of CC road from Binapani Pathagara to Rama Raja Temple via Ramachandra Panda house)
Project Category: Road
Financial Year: 2023-24 Execution Level: ps
Executing Agency: Panchayat Samiti, Bari Bill Status: Final Bill
Proposal Date: - Date of Commencement: 20-12-2025
Date of Completion: 31-12-2025 Scheme Name: SFC Devolution of Fund
Scheme Component Name: 5TH SFC DEVOLUTION GRANT TO PANCHAYAT SAMITI Project Sub-Category: CC Road
Project Type: New Work Name of Executant: Chirad Prasad Rout
Administrative Approval Details
Approval No.: OD/356/3395/118278/402007/00070524/AS
Technical Sanction Details
Technical Sanction No.: OD/356/3395/118278/402007/00070524/TS
Fund Sanction No.: 4520
Fund Sanction Amount (in Rs.): 200000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Skilled Un-Skilled Semi-Skilled
Rs. 562 Rs. 462 Rs. 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 13.55808384 Cubic Meter 3.9 52.876526976 - - 0.18 2.4404550912
2 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 16.62220476 Square Meter - - 0.05 0.831110238 0.05 0.831110238
3 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 13.55808384 Cubic Meter 4.6 62.367185664 - - 0.68 9.2194970112
Total Qty 12.4910623404 115.24371264 0.831110238
Rate Per Man Day 562 462 512
Total Amount 7019.9770353048 53242.59523968 425.528441856
Total Labour Amount (in Rs.): 60688.100716841