Material Statement

State: Odisha District: Kandhamal Block: Tikabali Gram Panchayat: Katimaha
Work Code: OD/359/3432/119005/415924/00047508 (IMPROVEMENT OF ROAD WITH CC/GR-II METALLING AT MUNINGIA,(DASAPADA))
Project Category: Road
Financial Year: 2024-25 Execution Level: ps
Executing Agency: Panchayat Samiti, Tikabali Bill Status: Final Bill
Proposal Date: - Date of Commencement: 04-09-2025
Date of Completion: 16-09-2025 Scheme Name: 5th SFC Grant in Aid
Scheme Component Name: Maintenance and improvement of Road infrastructure Project Sub-Category: CC Road
Project Type: Upgradation or Improvement Name of Executant: BHAJARAM BEHERA
Administrative Approval Details
Approval No.: OD/359/3432/119005/415924/00047508/AS
Technical Sanction Details
Technical Sanction No.: OD/359/3432/119005/415924/00047508/TS
Fund Sanction No.:
Fund Sanction Amount (in Rs.): 251852
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM340 BRM028 BRM056 BRM104 BRM092 BRM029 BRM045
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 17.895 Cum 3.23 57.80085 0.45 8.05275 0.9 16.1055 - - - - - - - -
2 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 34.95 Sqm - - - - - - 0.00267 0.0933165 0.126 4.4037 - - - -
3 Earth Work (AR0102aa) :.Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 3.075 Cum - - - - - - - - - - - - - -
4 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 14.76 Cum - - - - - - - - - - 1 14.76 - -
5 Concrete (AR0303a) :.Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal - Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 17.835 Cum 2.29 40.84215 0.48 8.5608 - - - - - - - - 0.96 17.1216
Total Qty 98.643 16.61355 16.1055 0.0933165 4.4037 14.76 17.1216
Rate Per Unit 557.587 1030.79 2442.53 58573.086 229.106 346.01 1063.37
Total Amount 55002.054441 17125.0812045 39338.166915 5465.835379719 1008.9140922 5107.1076 18206.595792
Total Material Amount (in Rs.): 141253.75542442