Material Statement

State: Odisha District: Nayagarh Block: Gania Gram Panchayat: Chhamundia
Work Code: OD/367/3525/120629/405325/00053465 (IMP. CC ROAD FROM CHHAMUNDIA KEUTA SAHI TO MADHUPUR SAHI)
Project Category: Road
Financial Year: 2024-25 Execution Level: ps
Executing Agency: Panchayat Samiti, Gania Bill Status: Final Bill
Proposal Date: - Date of Commencement: 18-09-2025
Date of Completion: 26-11-2025 Scheme Name: 5th SFC Grant in Aid
Scheme Component Name: All Weather Connectivity Project Sub-Category: CC Road
Project Type: New Work Name of Executant: SMT PUSPANJALI MURMU
Administrative Approval Details
Approval No.: OD/367/3525/120629/405325/00053465/AS
Technical Sanction Details
Technical Sanction No.: OD/367/3525/120629/405325/00053465/TS
Fund Sanction No.: 31142
Fund Sanction Amount (in Rs.): 180000
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM340 BRM028 BRM045 BRM056 BRM104 BRM092
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) :.Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 1.5075 Cum - - - - - - - - - - - - - -
2 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 11.47375 Cum 1 11.47375 - - - - - - - - - - - -
3 Concrete (AR0303a) :.Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal - Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 13.735 Cum - - 2.29 31.45315 0.48 6.5928 0.96 13.1856 - - - - - -
4 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 12.20122 Cum - - 3.23 39.4099406 0.45 5.490549 - - 0.9 10.981098 - - - -
5 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 20.1 Sqm - - - - - - - - - - 0.00267 0.053667 0.126 2.5326
Total Qty 11.47375 70.8630906 12.083349 13.1856 10.981098 0.053667 2.5326
Rate Per Unit 332.58 599.517 339.01 1259.78 1893.97 58573.086 229.106
Total Amount 3815.939775 42483.62748724 4096.37614449 16610.955168 20797.87017906 3143.441806362 580.2338556
Total Material Amount (in Rs.): 91528.444415752