Material Statement

State: Odisha District: Jagatsinghpur Block: Tirtol Gram Panchayat: Gopalpur
Work Code: OD/355/3393/118215/397636/00056486 (CONSTRUCTION OF CC ROAD FROM RAMA CHANDRA PRADHAN HOUSE TO POLUA GADA, VILL- ARANA.)
Project Category: Road
Financial Year: 2024-25 Execution Level: ps
Executing Agency: Panchayat Samiti, Tirtol Bill Status: Final Bill
Proposal Date: - Date of Commencement: 14-10-2025
Date of Completion: 10-11-2025 Scheme Name: 5th SFC Grant in Aid
Scheme Component Name: Maintenance and improvement of Road infrastructure Project Sub-Category: CC Road
Project Type: New Work Name of Executant: KISHORE CHANDRA SAHOO
Administrative Approval Details
Approval No.: OD/355/3393/118215/397636/00056486/AS
Technical Sanction Details
Technical Sanction No.: OD/355/3393/118215/397636/00056486/TS
Fund Sanction No.: 1130
Fund Sanction Amount (in Rs.): 186532
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM340 BRM028 BRM044 BRM104 BRM092 BRM056
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 7.2 Cum 2.29 16.488 0.48 3.456 0.96 6.912 - - - - - -
2 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 38 Sqm - - - - - - 0.00267 0.10146 0.126 4.788 - -
3 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 14.7825 Cum 3.23 47.747475 0.45 6.652125 - - - - - - 0.9 13.30425
Total Qty 64.235475 10.108125 6.912 0.10146 4.788 13.30425
Rate Per Unit 619.272 412.82 2501.16 58620.646 276.666 2902.53
Total Amount 39779.2310742 4172.8361625 17288.01792 5947.65074316 1324.676808 38615.9847525
Total Material Amount (in Rs.): 107128.39746036