| State: Odisha |
District: Bargarh |
Block: Bargarh |
Gram Panchayat: Gudesira |
Work Code: OD/347/3312/116380/380624/00014298 (Imp of CC road at Harijanpada, Nua Gudesira)
Project Category: Road
| Financial Year: 2024-25 |
Execution Level: ps |
| Executing Agency: Panchayat Samiti, Bargarh |
Proposal Date: - |
| Date of Commencement: 04-04-2025 |
Date of Completion: 07-06-2025 |
| Scheme Name: SFC Devolution of Fund |
Scheme Component Name: 5TH SFC DEVOLUTION GRANT TO PANCHAYAT SAMITI |
| Project Sub-Category: CC Road |
Project Type: Upgradation or Improvement |
| Name of Executant: SUSHMITA TIRKEY |
|
Administrative Approval Details
Approval No.: OD/347/3312/116380/380624/00014298/AS
Technical Sanction Details
Technical Sanction No.: OD/347/3312/116380/380624/00014298/TS
Fund Sanction No.: 15384
Fund Sanction Amount (in Rs.): 300000
ACTIVITY STATEMENT
| Sl.No. |
Activity taken |
Unit |
Quantity |
Unit Price (in Rs.) |
Total (in Rs.) |
| 1 |
Earth Work (AR0122Bi) : Earthwork in ordinary soil within 5 Km. mechanical carriages and spreading in filling area/road berm within initial lead and lift - Earthwork in ordinary soil within 5 Km. mechanical carriages and spreading in filling area/road berm within initial lead and lift including dressing and leveling the bed, etc. as per direction of Engineer-in-Charge.
|
Cum |
6.4538 |
306.77910892 |
1979.8910131479 |
| 2 |
Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge.
|
Cum |
21.96 |
502.502472 |
11034.95428512 |
| 3 |
Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge.
|
Cum |
22.8018 |
5196.00278008 |
118478.21619083 |
| 4 |
Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge.
|
Cum |
21.96 |
6770.08271796 |
148671.0164864 |
| 5 |
R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc
|
Sqm |
56.12 |
215.38264180804 |
12087.273858267 |
| 6 |
Earth Work (AR0122Bi) : Earthwork in ordinary soil within 5 Km. mechanical carriages and spreading in filling area/road berm within initial lead and lift - Earthwork in ordinary soil within 5 Km. mechanical carriages and spreading in filling area/road berm within initial lead and lift including dressing and leveling the bed, etc. as per direction of Engineer-in-Charge.
|
Cum |
0 |
306.77910892 |
0 |
Total Amount (in Rs.): 292251.35183376
LABOUR STATEMENT
| Sl.No. |
Activity Name |
Quantity (A) |
Unit |
Un-Skilled
|
Skilled
|
Semi-Skilled
|
| 452 |
552 |
502 |
| Qty/Unit (B) |
Total Qty (A*B) |
Qty/Unit (B) |
Total Qty (A*B) |
Qty/Unit (B) |
Total Qty (A*B) |
| 1 |
Earth Work (AR0122Bi) : Earthwork in ordinary soil within 5 Km. mechanical carriages and spreading in filling area/road berm within initial lead and lift - Earthwork in ordinary soil within 5 Km. mechanical carriages and spreading in filling area/road berm within initial lead and lift including dressing and leveling the bed, etc. as per direction of Engineer-in-Charge.
|
6.4538 |
Cubic Meter |
0.32 |
2.065216 |
- |
- |
- |
- |
| 2 |
Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge.
|
21.96 |
Cubic Meter |
0.1236 |
2.714256 |
- |
- |
- |
- |
| 3 |
Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge.
|
22.8018 |
Cubic Meter |
3.9 |
88.92702 |
- |
- |
0.18 |
4.104324 |
| 4 |
Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge.
|
21.96 |
Cubic Meter |
4.6 |
101.016 |
- |
- |
0.68 |
14.9328 |
| 5 |
R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc
|
56.12 |
Square Meter |
- |
- |
0.05 |
2.806 |
0.05 |
2.806 |
| 6 |
Earth Work (AR0122Bi) : Earthwork in ordinary soil within 5 Km. mechanical carriages and spreading in filling area/road berm within initial lead and lift - Earthwork in ordinary soil within 5 Km. mechanical carriages and spreading in filling area/road berm within initial lead and lift including dressing and leveling the bed, etc. as per direction of Engineer-in-Charge.
|
0 |
Cubic Meter |
0.32 |
0 |
- |
- |
- |
- |
| Total Qty |
194.722492 |
21.843124 |
2.806 |
| Rate Per Man Day |
452 |
552 |
502 |
| Total Amount |
88014.566384 |
12057.404448 |
1408.612 |
Total Labour Amount (in Rs.): 101480.582832
MATERIAL STATEMENT
| Sl.No. |
Activity Name |
Quantity (A) |
Unit |
BRMM402 |
BRMM401 |
BRM029 |
BRM340 |
BRM028 |
BRM044 |
BRM056 |
BRM104 |
BRM092 |
| Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
| 1 |
Earth Work (AR0122Bi) :.Earthwork in ordinary soil within 5 Km. mechanical carriages and spreading in filling area/road berm within initial lead and lift - Earthwork in ordinary soil within 5 Km. mechanical carriages and spreading in filling area/road berm within initial lead and lift including dressing and leveling the bed, etc. as per direction of Engineer-in-Charge. |
6.4538 |
Cum |
-0.6666 |
-4.30210308 |
1 |
6.4538 |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
| 2 |
Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. |
21.96 |
Cum |
- |
- |
- |
- |
1 |
21.96 |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
| 3 |
Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. |
22.8018 |
Cum |
- |
- |
- |
- |
- |
- |
2.29 |
52.216122 |
0.48 |
10.944864 |
0.96 |
21.889728 |
- |
- |
- |
- |
- |
- |
| 4 |
Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. |
21.96 |
Cum |
- |
- |
- |
- |
- |
- |
3.23 |
70.9308 |
0.45 |
9.882 |
- |
- |
0.9 |
19.764 |
- |
- |
- |
- |
| 5 |
R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc |
56.12 |
Sqm |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
0.00267 |
0.1498404 |
0.126 |
7.07112 |
| 6 |
Earth Work (AR0122Bi) :.Earthwork in ordinary soil within 5 Km. mechanical carriages and spreading in filling area/road berm within initial lead and lift - Earthwork in ordinary soil within 5 Km. mechanical carriages and spreading in filling area/road berm within initial lead and lift including dressing and leveling the bed, etc. as per direction of Engineer-in-Charge. |
0 |
Cum |
-0.6666 |
0 |
1 |
0 |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
| Total Qty |
-4.30210308 |
6.4538 |
21.96 |
123.146922 |
20.826864 |
21.889728 |
19.764 |
0.1498404 |
7.07112 |
| Rate Per Unit |
175.38 |
276.01 |
401.41 |
560.422 |
409.04 |
1354.39 |
1802.83 |
58620.646 |
276.666 |
| Total Amount |
-754.5028381704 |
1781.313338 |
8814.9636 |
69014.244321084 |
8519.02045056 |
29647.22870592 |
35631.13212 |
8783.7410448984 |
1956.33848592 |
Total Material Amount (in Rs.): 163393.47922821
ROYALTY STATEMENT
| Sl.No. |
Activity Name |
Quantity (A) |
Unit |
BRM029 |
BRM340 |
BRM028 |
BRM044 |
BRM056 |
BRM104 |
BRM092 |
| Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
| 1 |
Earth Work (AR0122Bi) :.Earthwork in ordinary soil within 5 Km. mechanical carriages and spreading in filling area/road berm within initial lead and lift - Earthwork in ordinary soil within 5 Km. mechanical carriages and spreading in filling area/road berm within initial lead and lift including dressing and leveling the bed, etc. as per direction of Engineer-in-Charge. |
6.4538 |
Cum |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
| 2 |
Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. |
21.96 |
Cum |
1 |
21.96 |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
| 3 |
Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. |
22.8018 |
Cum |
- |
- |
2.29 |
52.216122 |
0.48 |
10.944864 |
0.96 |
21.889728 |
- |
- |
- |
- |
- |
- |
| 4 |
Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. |
21.96 |
Cum |
- |
- |
3.23 |
70.9308 |
0.45 |
9.882 |
- |
- |
0.9 |
19.764 |
- |
- |
- |
- |
| 5 |
R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc |
56.12 |
Sqm |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
0.00267 |
0.1498404 |
0.000614 |
0.03445768 |
| 6 |
Earth Work (AR0122Bi) :.Earthwork in ordinary soil within 5 Km. mechanical carriages and spreading in filling area/road berm within initial lead and lift - Earthwork in ordinary soil within 5 Km. mechanical carriages and spreading in filling area/road berm within initial lead and lift including dressing and leveling the bed, etc. as per direction of Engineer-in-Charge. |
0 |
Cum |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
| Total Qty |
21.96 |
123.146922 |
20.826864 |
21.889728 |
19.764 |
0.1498404 |
0.03445768 |
| Rate Per Unit |
40.25 |
0 |
40.25 |
149.5 |
149.5 |
0 |
0 |
| Total Amount |
883.89 |
0 |
838.281276 |
3272.514336 |
2954.718 |
0 |
0 |
Total Royalty Amount (in Rs.): 7949.403612
ADDITION COMPONENT
| S/N |
Item Name |
Amount (in Rs.) |
| 1 |
Provision for Contingency @
1%
|
Rs. 2922.5135183376 |
| 2 |
Display Citizen Board @
Rs. 4826
|
Rs. 4826 |
Total Addition Component Amount (in Rs.): 7748.5135183376
DEDUCTION COMPONENT
| Sl.No. |
Item Name |
Amount (in Rs.) |
| No data to display. |
Total Deduction Component Amount (in Rs.): 0
Total Net Amount (in Rs.): 299999.8653521