| State: Odisha |
District: Deogarh |
Block: Tileibani |
Gram Panchayat: Suguda |
Work Code: OD/351/3348/117233/382783/00014371 (Repair & Maintanance of Apurba High school, Suguda)
Project Category: Building
| Financial Year: 2022-23 |
Execution Level: ps |
| Executing Agency: Panchayat Samiti, Tileibani |
Proposal Date: - |
| Date of Commencement: 22-09-2025 |
Date of Completion: 21-11-2025 |
| Scheme Name: Asset Management School and Mass Education Department |
Scheme Component Name: Self/Personal Deposit |
| Project Sub-Category: Others |
Project Type: Repair and Maintenance |
| Name of Executant: RASHMIRANJAN BEHERA |
|
Administrative Approval Details
Approval No.: OD/351/3348/117233/382783/00014371/AS
Technical Sanction Details
Technical Sanction No.: OD/351/3348/117233/382783/00014371/TS
Fund Sanction No.: 2546
Fund Sanction Amount (in Rs.): 91500
ACTIVITY STATEMENT
| Sl.No. |
Activity taken |
Unit |
Quantity |
Unit Price (in Rs.) |
Total (in Rs.) |
| 1 |
Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge.
|
Cum |
3.9645 |
6138.16213048 |
24334.743766288 |
| 2 |
Concrete (AR0307a) : Cement concrete (1:2:4)with 12mm size hard granite(Hand broken)chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(hand broken) chips including hoisting and laying in position compacting to proper thickness and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge.
|
Cum |
2.973375 |
7324.95286176 |
21779.831715336 |
| 3 |
Plastering (AR1014) : 16mm thick cement Plaster in CM (1:6) over brick work in inside. - 16mm thick cement Plaster in CM (1:6) over brick work in inside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc comp.and as per direction of Engineer-in-charge.
|
Sqm |
16.25 |
262.422746616 |
4264.36963251 |
| 4 |
Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge
|
Cum |
4.5 |
240.77592 |
1083.49164 |
| 5 |
Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge.
|
Cum |
0.9 |
433.101332 |
389.7911988 |
| 6 |
Masonry Brick Work (AR0603b) : Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in foundation and plinth - Brickwork with Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in foundation and plinth having crushing strength not less than 75.00 Kg/cm2 with dimensional tolerance ±8 percent immersing the bricks in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge.
|
Cum |
1.8 |
5312.688260264 |
9562.8388684752 |
| 7 |
Masonry Brick Work (AR0603bi) : Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in superstructure - Brickwork with Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in superstructure having crushing strength not less than 75.00 Kg/cm2 with dimensional tolerance ±8 percent immersing the bricks in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge.
|
Cum |
3.90625 |
5346.018260264 |
20882.883829156 |
| 8 |
Plastering (AR1004) : 12mm thick cement plster (1:6) over Brick work in inside - 12mm thick cement plster (1:6) over Brick work in inside including racking out joints finishing smooth with proper plumb and line curing for proper period with cost conveyance, royality, taxes of all materials, labour and T & P required for the work etc. comp.and as per direction of Engineer-in-charge.
|
Sqm |
16.25 |
185.1168248096 |
3008.148403156 |
| 9 |
Painting (AR0901d) : Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces (Inner surface) - Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces including cost conveyance, taxes of all materials, labor and T&P required for the work complete as per direction of the Engineer-in-charge.
|
Sqm |
32.5 |
71.83753306751 |
2334.7198246941 |
| 10 |
Painting (AR0918Ai) : Finishing wall one coat with weather coat - Finishing wall one coat with weather coat including all costs of labour, Paint, Primer and Brushes required for the work etc. complete and as per direction of Engineer-in-charge.
|
Sqm |
32.5 |
57.09560199 |
1855.607064675 |
Total Amount (in Rs.): 89496.42594309
LABOUR STATEMENT
| Sl.No. |
Activity Name |
Quantity (A) |
Unit |
Skilled
|
Un-Skilled
|
Highly-Skilled
|
| 562 |
462 |
612 |
| Qty/Unit (B) |
Total Qty (A*B) |
Qty/Unit (B) |
Total Qty (A*B) |
Qty/Unit (B) |
Total Qty (A*B) |
| 1 |
Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge.
|
3.9645 |
Cubic Meter |
3.9 |
15.46155 |
0.18 |
0.71361 |
- |
- |
| 2 |
Concrete (AR0307a) : Cement concrete (1:2:4)with 12mm size hard granite(Hand broken)chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(hand broken) chips including hoisting and laying in position compacting to proper thickness and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge.
|
2.973375 |
Cubic Meter |
4.6 |
13.677525 |
0.68 |
2.021895 |
- |
- |
| 3 |
Plastering (AR1014) : 16mm thick cement Plaster in CM (1:6) over brick work in inside. - 16mm thick cement Plaster in CM (1:6) over brick work in inside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc comp.and as per direction of Engineer-in-charge.
|
16.25 |
Square Meter |
0.24 |
3.9 |
0.16 |
2.6 |
- |
- |
| 4 |
Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge
|
4.5 |
Cubic Meter |
0.516 |
2.322 |
- |
- |
- |
- |
| 5 |
Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge.
|
0.9 |
Cubic Meter |
0.1236 |
0.11124 |
- |
- |
- |
- |
| 6 |
Masonry Brick Work (AR0603b) : Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in foundation and plinth - Brickwork with Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in foundation and plinth having crushing strength not less than 75.00 Kg/cm2 with dimensional tolerance ±8 percent immersing the bricks in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge.
|
1.8 |
Cubic Meter |
2.96 |
5.328 |
1.05 |
1.89 |
0.35 |
0.63 |
| 7 |
Masonry Brick Work (AR0603bi) : Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in superstructure - Brickwork with Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in superstructure having crushing strength not less than 75.00 Kg/cm2 with dimensional tolerance ±8 percent immersing the bricks in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge.
|
3.90625 |
Cubic Meter |
2.96 |
11.5625 |
1.05 |
4.1015625 |
0.35 |
1.3671875 |
| 8 |
Plastering (AR1004) : 12mm thick cement plster (1:6) over Brick work in inside - 12mm thick cement plster (1:6) over Brick work in inside including racking out joints finishing smooth with proper plumb and line curing for proper period with cost conveyance, royality, taxes of all materials, labour and T & P required for the work etc. comp.and as per direction of Engineer-in-charge.
|
16.25 |
Square Meter |
0.12 |
1.95 |
0.14 |
2.275 |
- |
- |
| 9 |
Painting (AR0901d) : Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces (Inner surface) - Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces including cost conveyance, taxes of all materials, labor and T&P required for the work complete as per direction of the Engineer-in-charge.
|
32.5 |
Square Meter |
0.053763440860215 |
1.747311827957 |
- |
- |
0.053763440860215 |
1.747311827957 |
| 10 |
Painting (AR0918Ai) : Finishing wall one coat with weather coat - Finishing wall one coat with weather coat including all costs of labour, Paint, Primer and Brushes required for the work etc. complete and as per direction of Engineer-in-charge.
|
32.5 |
Square Meter |
0.043 |
1.3975 |
- |
- |
0.036 |
1.17 |
| Total Qty |
13.6020675 |
57.457626827957 |
4.914499327957 |
| Rate Per Man Day |
562 |
462 |
612 |
| Total Amount |
7644.361935 |
26545.423594516 |
3007.6735887097 |
Total Labour Amount (in Rs.): 37197.459118226
MATERIAL STATEMENT
| Sl.No. |
Activity Name |
Quantity (A) |
Unit |
BRM340 |
BRM028 |
BRM044 |
BRM057 |
BRM029 |
BRM005 |
BRMMR0025 |
BRM253 |
BRM255 |
| Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
| 1 |
Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. |
3.9645 |
Cum |
2.29 |
9.078705 |
0.48 |
1.90296 |
0.96 |
3.80592 |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
| 2 |
Concrete (AR0307a) :.Cement concrete (1:2:4)with 12mm size hard granite(Hand broken)chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(hand broken) chips including hoisting and laying in position compacting to proper thickness and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. |
2.973375 |
Cum |
3.23 |
9.60400125 |
0.45 |
1.33801875 |
- |
- |
0.9 |
2.6760375 |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
| 3 |
Plastering (AR1014) :.16mm thick cement Plaster in CM (1:6) over brick work in inside. - 16mm thick cement Plaster in CM (1:6) over brick work in inside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc comp.and as per direction of Engineer-in-charge. |
16.25 |
Sqm |
0.043 |
0.69875 |
0.018 |
0.2925 |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
| 4 |
Earth Work (AR0102aa) :.Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge |
4.5 |
Cum |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
| 5 |
Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. |
0.9 |
Cum |
- |
- |
- |
- |
- |
- |
- |
- |
1 |
0.9 |
- |
- |
- |
- |
- |
- |
- |
- |
| 6 |
Masonry Brick Work (AR0603b) :.Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in foundation and plinth - Brickwork with Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in foundation and plinth having crushing strength not less than 75.00 Kg/cm2 with dimensional tolerance ±8 percent immersing the bricks in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge. |
1.8 |
Cum |
0.672 |
1.2096 |
0.28 |
0.504 |
- |
- |
- |
- |
- |
- |
350 |
630 |
- |
- |
- |
- |
- |
- |
| 7 |
Masonry Brick Work (AR0603bi) :.Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in superstructure - Brickwork with Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in superstructure having crushing strength not less than 75.00 Kg/cm2 with dimensional tolerance ±8 percent immersing the bricks in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge. |
3.90625 |
Cum |
0.672 |
2.625 |
0.28 |
1.09375 |
- |
- |
- |
- |
- |
- |
350 |
1367.1875 |
1 |
3.90625 |
- |
- |
- |
- |
| 8 |
Plastering (AR1004) :.12mm thick cement plster (1:6) over Brick work in inside - 12mm thick cement plster (1:6) over Brick work in inside including racking out joints finishing smooth with proper plumb and line curing for proper period with cost conveyance, royality, taxes of all materials, labour and T & P required for the work etc. comp.and as per direction of Engineer-in-charge. |
16.25 |
Sqm |
0.0358 |
0.58175 |
0.015 |
0.24375 |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
| 9 |
Painting(AR0901d) :.Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces (Inner surface) - Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces including cost conveyance, taxes of all materials, labor and T&P required for the work complete as per direction of the Engineer-in-charge. |
32.5 |
Sqm |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
0.084 |
2.73 |
- |
- |
| 10 |
Painting(AR0918Ai) :.Finishing wall one coat with weather coat - Finishing wall one coat with weather coat including all costs of labour, Paint, Primer and Brushes required for the work etc. complete and as per direction of Engineer-in-charge. |
32.5 |
Sqm |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
0.075 |
2.4375 |
| Total Qty |
23.79780625 |
5.37497875 |
3.80592 |
2.6760375 |
0.9 |
1997.1875 |
3.90625 |
2.73 |
2.4375 |
| Rate Per Unit |
548.122 |
1063.41 |
1726.96 |
1816.9 |
331.46 |
6.1539 |
33 |
159.33732 |
195.09732 |
| Total Amount |
13044.101157363 |
5715.8061525375 |
6572.6716032 |
4862.09253375 |
298.314 |
12290.49215625 |
128.90625 |
434.9908836 |
475.5497175 |
Total Material Amount (in Rs.): 43822.9244542
ROYALTY STATEMENT
| Sl.No. |
Activity Name |
Quantity (A) |
Unit |
BRM340 |
BRM028 |
BRM044 |
BRM057 |
BRM029 |
BRM005 |
BRM253 |
BRM255 |
| Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
| 1 |
Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. |
3.9645 |
Cum |
2.29 |
9.078705 |
0.48 |
1.90296 |
0.96 |
3.80592 |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
| 2 |
Concrete (AR0307a) :.Cement concrete (1:2:4)with 12mm size hard granite(Hand broken)chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(hand broken) chips including hoisting and laying in position compacting to proper thickness and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. |
2.973375 |
Cum |
3.23 |
9.60400125 |
0.45 |
1.33801875 |
- |
- |
0.9 |
2.6760375 |
- |
- |
- |
- |
- |
- |
- |
- |
| 3 |
Plastering (AR1014) :.16mm thick cement Plaster in CM (1:6) over brick work in inside. - 16mm thick cement Plaster in CM (1:6) over brick work in inside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc comp.and as per direction of Engineer-in-charge. |
16.25 |
Sqm |
0.043 |
0.69875 |
0.018 |
0.2925 |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
| 4 |
Earth Work (AR0102aa) :.Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge |
4.5 |
Cum |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
| 5 |
Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. |
0.9 |
Cum |
- |
- |
- |
- |
- |
- |
- |
- |
1 |
0.9 |
- |
- |
- |
- |
- |
- |
| 6 |
Masonry Brick Work (AR0603b) :.Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in foundation and plinth - Brickwork with Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in foundation and plinth having crushing strength not less than 75.00 Kg/cm2 with dimensional tolerance ±8 percent immersing the bricks in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge. |
1.8 |
Cum |
0.672 |
1.2096 |
0.28 |
0.504 |
- |
- |
- |
- |
- |
- |
350 |
630 |
- |
- |
- |
- |
| 7 |
Masonry Brick Work (AR0603bi) :.Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in superstructure - Brickwork with Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in superstructure having crushing strength not less than 75.00 Kg/cm2 with dimensional tolerance ±8 percent immersing the bricks in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge. |
3.90625 |
Cum |
0.672 |
2.625 |
0.28 |
1.09375 |
- |
- |
- |
- |
- |
- |
350 |
1367.1875 |
- |
- |
- |
- |
| 8 |
Plastering (AR1004) :.12mm thick cement plster (1:6) over Brick work in inside - 12mm thick cement plster (1:6) over Brick work in inside including racking out joints finishing smooth with proper plumb and line curing for proper period with cost conveyance, royality, taxes of all materials, labour and T & P required for the work etc. comp.and as per direction of Engineer-in-charge. |
16.25 |
Sqm |
0.0358 |
0.58175 |
0.015 |
0.24375 |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
| 9 |
Painting(AR0901d) :.Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces (Inner surface) - Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces including cost conveyance, taxes of all materials, labor and T&P required for the work complete as per direction of the Engineer-in-charge. |
32.5 |
Sqm |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
0.084 |
2.73 |
- |
- |
| 10 |
Painting(AR0918Ai) :.Finishing wall one coat with weather coat - Finishing wall one coat with weather coat including all costs of labour, Paint, Primer and Brushes required for the work etc. complete and as per direction of Engineer-in-charge. |
32.5 |
Sqm |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
0.075 |
2.4375 |
| Total Qty |
23.79780625 |
5.37497875 |
3.80592 |
2.6760375 |
0.9 |
1997.1875 |
2.73 |
2.4375 |
| Rate Per Unit |
0 |
560.25 |
156.5 |
156.5 |
40.25 |
0.04025 |
0 |
0 |
| Total Amount |
0 |
3011.3318446875 |
595.62648 |
418.79986875 |
36.225 |
80.386796875 |
0 |
0 |
Total Royalty Amount (in Rs.): 4142.3699903125
ADDITION COMPONENT
| S/N |
Item Name |
Amount (in Rs.) |
| 1 |
Provision for Contingency @
Rs. 1000
|
Rs. 1000 |
| 2 |
Display Citizen Board @
Rs. 1000
|
Rs. 1000 |
Total Addition Component Amount (in Rs.): 2000
DEDUCTION COMPONENT
| Sl.No. |
Item Name |
Amount (in Rs.) |
| No data to display. |
Total Deduction Component Amount (in Rs.): 0
Total Net Amount (in Rs.): 91496.42594309