State: Odisha District: Ganjam Block: Polosara Gram Panchayat: Madhupalli
Work Code: OD/354/3380/117915/411583/00017498 (Repair & Maintenance of AWC Building at Hirapalli under Madhupalli GP)
Project Category: Building
Financial Year: 2023-24 Execution Level: ps
Executing Agency: Panchayat Samiti, Polosara Proposal Date: 20-07-2024
Date of Commencement: 13-05-2025 Date of Completion: 28-05-2025
Scheme Name: Asset Management Women and Child Development Department Scheme Component Name: Self/Personal Deposit
Project Sub-Category: AWC Project Type: Repair and Maintenance
Name of Executant: Sradhanta Prasad Sahu
Administrative Approval Details
Approval No.: OD/354/3380/117915/411583/00017498/AS
Technical Sanction Details
Technical Sanction No.: OD/354/3380/117915/411583/00017498/TS
Fund Sanction No.: 45000
Fund Sanction Amount (in Rs.): 45000
ACTIVITY STATEMENT
Sl.No. Activity taken Unit Quantity Unit Price (in Rs.) Total (in Rs.)
1 Concrete (AR0317) : 2.5 cm thick grading concrete (1:2:2) on roof slab with 6mm size hard granite chips - 2.5 cm thick grading concrete (1:2:2) on roof slab with 6mm size hard granite chips including hoisting and laying in position compacting and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. (new work) Sqm 39.69 351.297275446 13942.988862452
2 Painting (AR0901d) : Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces (Inner surface) - Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces including cost conveyance, taxes of all materials, labor and T&P required for the work complete as per direction of the Engineer-in-charge. Sqm 39.69 71.83248932951 2851.0315014883
3 Other Building Items. (AR1902) : cement based wall putty (water based) - Finishing surface of walls with cement based wall putty (water based) of approved make and finished smooth and even surface to receive painting including cost of scaffolding staging charges with cost of all materials taxes,labour,T&P,etc.complete. and as per the direction of Engineer in Charge. Sqm 170.6875 79.21834 13521.58040875
4 Painting (AR0918ca) : Finishing wall two coats with weather coat with one coat oilbound Primer - Finishing wall surface two coats with weather coat with one coat oilbound Primer including all costs of labour, Paint, Primer, Brushes and putty required for the work etc. complete and as per direction of Engineer-in-charge.(Outside) Sqm 83.875 156.85349521701 13156.086911327
Total Amount (in Rs.): 43471.687684017
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Highly-Skilled Skilled
462 612 562
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Concrete (AR0317) : 2.5 cm thick grading concrete (1:2:2) on roof slab with 6mm size hard granite chips - 2.5 cm thick grading concrete (1:2:2) on roof slab with 6mm size hard granite chips including hoisting and laying in position compacting and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. (new work) 39.69 Square Meter 0.36 14.2884 - - 0.1 3.969
2 Painting (AR0901d) : Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces (Inner surface) - Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces including cost conveyance, taxes of all materials, labor and T&P required for the work complete as per direction of the Engineer-in-charge. 39.69 Square Meter 0.053763440860215 2.1338709677419 - - 0.053763440860215 2.1338709677419
3 Other Building Items. (AR1902) : cement based wall putty (water based) - Finishing surface of walls with cement based wall putty (water based) of approved make and finished smooth and even surface to receive painting including cost of scaffolding staging charges with cost of all materials taxes,labour,T&P,etc.complete. and as per the direction of Engineer in Charge. 170.6875 Square Meter 0.057 9.7291875 0.05 8.534375 - -
4 Painting (AR0918ca) : Finishing wall two coats with weather coat with one coat oilbound Primer - Finishing wall surface two coats with weather coat with one coat oilbound Primer including all costs of labour, Paint, Primer, Brushes and putty required for the work etc. complete and as per direction of Engineer-in-charge.(Outside) 83.875 Square Meter 0.11776344086022 9.8774086021505 - - 0.10776344086022 9.0386586021505
Total Qty 36.028867069892 15.141529569892 8.534375
Rate Per Man Day 462 612 562
Total Amount 16645.33658629 9266.6160967742 4796.31875
Total Labour Amount (in Rs.): 30708.271433065
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM340 BRM028 BRM064 BRM253 BRMMR0038 BRM255 BRM252
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Concrete (AR0317) :.2.5 cm thick grading concrete (1:2:2) on roof slab with 6mm size hard granite chips - 2.5 cm thick grading concrete (1:2:2) on roof slab with 6mm size hard granite chips including hoisting and laying in position compacting and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. (new work) 39.69 Sqm 0.1208 4.794552 0.0169 0.670761 0.0169 0.670761 - - - - - - - -
2 Painting(AR0901d) :.Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces (Inner surface) - Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces including cost conveyance, taxes of all materials, labor and T&P required for the work complete as per direction of the Engineer-in-charge. 39.69 Sqm - - - - - - 0.084 3.33396 - - - - - -
3 Other Building Items. (AR1902) :.cement based wall putty (water based) - Finishing surface of walls with cement based wall putty (water based) of approved make and finished smooth and even surface to receive painting including cost of scaffolding staging charges with cost of all materials taxes,labour,T&P,etc.complete. and as per the direction of Engineer in Charge. 170.6875 Sqm - - - - - - - - 0.8 136.55 - - - -
4 Painting(AR0918ca) :.Finishing wall two coats with weather coat with one coat oilbound Primer - Finishing wall surface two coats with weather coat with one coat oilbound Primer including all costs of labour, Paint, Primer, Brushes and putty required for the work etc. complete and as per direction of Engineer-in-charge.(Outside) 83.875 Sqm - - - - - - - - - - 0.125 10.484375 0.084 7.0455
Total Qty 4.794552 0.670761 0.670761 3.33396 136.55 10.484375 7.0455
Rate Per Unit 593.232 407.34 1155.02 159.27787 30 195.03787 125.74787
Total Amount 2844.281672064 273.22778574 774.74237022 531.0260474652 4096.5 2044.8501682813 885.956618085
Total Material Amount (in Rs.): 11450.584661855
ROYALTY STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM340 BRM028 BRM064 BRM253 BRM255 BRM252
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Concrete (AR0317) :.2.5 cm thick grading concrete (1:2:2) on roof slab with 6mm size hard granite chips - 2.5 cm thick grading concrete (1:2:2) on roof slab with 6mm size hard granite chips including hoisting and laying in position compacting and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. (new work) 39.69 Sqm 0.1208 4.794552 0.0169 0.670761 0.0169 0.670761 - - - - - -
2 Painting(AR0901d) :.Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces (Inner surface) - Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces including cost conveyance, taxes of all materials, labor and T&P required for the work complete as per direction of the Engineer-in-charge. 39.69 Sqm - - - - - - 0.084 3.33396 - - - -
3 Other Building Items. (AR1902) :.cement based wall putty (water based) - Finishing surface of walls with cement based wall putty (water based) of approved make and finished smooth and even surface to receive painting including cost of scaffolding staging charges with cost of all materials taxes,labour,T&P,etc.complete. and as per the direction of Engineer in Charge. 170.6875 Sqm - - - - - - - - - - - -
4 Painting(AR0918ca) :.Finishing wall two coats with weather coat with one coat oilbound Primer - Finishing wall surface two coats with weather coat with one coat oilbound Primer including all costs of labour, Paint, Primer, Brushes and putty required for the work etc. complete and as per direction of Engineer-in-charge.(Outside) 83.875 Sqm - - - - - - - - 0.125 10.484375 0.084 7.0455
Total Qty 4.794552 0.670761 0.670761 3.33396 10.484375 7.0455
Rate Per Unit 0 40.25 149.5 0 0 0
Total Amount 0 26.99813025 100.2787695 0 0 0
Total Royalty Amount (in Rs.): 127.27689975
ADDITION COMPONENT
S/N Item Name Amount (in Rs.)
1 Provision for Contingency @ 1% Rs. 434.71687684017
2 Display Citizen Board @ Rs. 1093 Rs. 1093
Total Addition Component Amount (in Rs.): 1527.7168768402
DEDUCTION COMPONENT
Sl.No. Item Name Amount (in Rs.)
No data to display.
Total Deduction Component Amount (in Rs.): 0
Total Net Amount (in Rs.): 44999.404560857