State: Odisha District: Sundargarh Block: Gurundia Gram Panchayat: Kundheidiha
Work Code: OD/373/3577/121585/385038/00026880 (Imp. of Road ( CC/ Gr-II Meatlling ) with culvert at Majhisahi Pada House to Bandhadhipa)
Project Category: Road
Financial Year: 2024-25 Execution Level: ps
Executing Agency: Panchayat Samiti, Gurundia Proposal Date: -
Date of Commencement: 30-12-2025 Date of Completion: 22-01-2026
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: Maintenance and improvement of Road infrastructure
Project Sub-Category: CC Road Project Type: Upgradation or Improvement
Name of Executant: Sumanti Kullu
Administrative Approval Details
Approval No.: OD/373/3577/121585/385038/00026880/AS
Technical Sanction Details
Technical Sanction No.: OD/373/3577/121585/385038/00026880/TS
Fund Sanction No.: 1130
Fund Sanction Amount (in Rs.): 330000
ACTIVITY STATEMENT
Sl.No. Activity taken Unit Quantity Unit Price (in Rs.) Total (in Rs.)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge Cum 36.792 240.77592 8858.62764864
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. Cum 5.841 993.641232 5803.858436112
3 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. Cum 32.17075 6135.31499502 197377.68487604
4 R.C.C. Work (AR0404Ag) : Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge (RCC Roof slab, landing, balcony, sun shade) Cum 5.022 12910.675756722 64837.413650258
5 R.C.C. Work (AR0409) : Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position - Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position including cost of binding wire 18 to 20 gauge with cost of steel rod and as per drawing, design, and direction of Engineer-in-charge. Qntl 4.99631 8515.2896283 42545.026722772
6 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. Cum 0.777 7578.71667274 5888.662854719
Total Amount (in Rs.): 325311.27418854
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled Highly-Skilled
462 562 512 612
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 36.792 Cubic Meter 0.516 18.984672 - - - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 5.841 Cubic Meter 0.1236 0.7219476 - - - - - -
3 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 32.17075 Cubic Meter 3.9 125.465925 - - 0.18 5.790735 - -
4 R.C.C. Work (AR0404Ag) : Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge (RCC Roof slab, landing, balcony, sun shade) 5.022 Cubic Meter 1.3333 6.6958326 3.11255 15.6312261 3.15525 15.8456655 - -
5 R.C.C. Work (AR0409) : Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position - Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position including cost of binding wire 18 to 20 gauge with cost of steel rod and as per drawing, design, and direction of Engineer-in-charge. 4.99631 Quintal 0.8 3.997048 0.044 0.21983764 - - 0.3 1.498893
6 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 0.777 Cubic Meter 4.6 3.5742 - - 0.68 0.52836 - -
Total Qty 159.4396252 22.1647605 15.85106374 1.498893
Rate Per Man Day 462 562 512 612
Total Amount 73661.1068424 12456.595401 8115.74463488 917.322516
Total Labour Amount (in Rs.): 95150.76939428
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM340 BRM028 BRM044 BRM060 BRM052 BRM084 BRM104 BRM162 BRM341 BRM056
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) :.Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 36.792 Cum - - - - - - - - - - - - - - - - - - - - - -
2 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 5.841 Cum 1 5.841 - - - - - - - - - - - - - - - - - - - -
3 Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 32.17075 Cum - - 2.29 73.6710175 0.48 15.44196 0.96 30.88392 - - - - - - - - - - - - - -
4 R.C.C. Work (AR0404Ag) :.Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge (RCC Roof slab, landing, balcony, sun shade) 5.022 Cum - - 3.4733 17.4429126 0.45 2.2599 - - 0.36 1.80792 0.54 2.71188 6.2216 31.2448752 0.0502172 0.2521907784 - - - - - -
5 R.C.C. Work (AR0409) :.Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position - Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position including cost of binding wire 18 to 20 gauge with cost of steel rod and as per drawing, design, and direction of Engineer-in-charge. 4.99631 Qntl - - - - - - - - - - - - - - - - 0.8 3.997048 1.05 5.2461255 - -
6 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 0.777 Cum - - 3.23 2.50971 0.45 0.34965 - - - - - - - - - - - - - - 0.9 0.6993
Total Qty 5.841 93.6236401 18.05151 30.88392 1.80792 2.71188 31.2448752 0.2521907784 3.997048 5.2461255 0.6993
Rate Per Unit 673.45 573.132 678.39 2041.16 2435.91 2428.2 250.166 58573.086 90.1 6297.612 2442.53
Total Amount 3933.62145 53658.704097793 12245.9638689 63039.0221472 4403.9304072 6584.987016 7816.4054492832 14771.59215163 360.1340248 33038.062902306 1708.061229
Total Material Amount (in Rs.): 201560.48474411
ROYALTY STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM340 BRM028 BRM044 BRM060 BRM052 BRM084 BRM104 BRM341 BRM056
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) :.Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 36.792 Cum - - - - - - - - - - - - - - - - - - - -
2 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 5.841 Cum 1 5.841 - - - - - - - - - - - - - - - - - -
3 Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 32.17075 Cum - - 2.29 73.6710175 0.48 15.44196 0.96 30.88392 - - - - - - - - - - - -
4 R.C.C. Work (AR0404Ag) :.Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge (RCC Roof slab, landing, balcony, sun shade) 5.022 Cum - - 3.4733 17.4429126 0.45 2.2599 - - 0.36 1.80792 0.54 2.71188 0.076659 0.384981498 0.0502172 0.2521907784 - - - -
5 R.C.C. Work (AR0409) :.Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position - Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position including cost of binding wire 18 to 20 gauge with cost of steel rod and as per drawing, design, and direction of Engineer-in-charge. 4.99631 Qntl - - - - - - - - - - - - - - - - 1.05 5.2461255 - -
6 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 0.777 Cum - - 3.23 2.50971 0.45 0.34965 - - - - - - - - - - - - 0.9 0.6993
Total Qty 5.841 93.6236401 18.05151 30.88392 1.80792 2.71188 0.384981498 0.2521907784 5.2461255 0.6993
Rate Per Unit 253.25 0 253.25 243.5 243.5 243.5 0 0 0 243.5
Total Amount 1479.23325 0 4571.5449075 7520.23452 440.22852 660.34278 0 0 0 170.27955
Total Royalty Amount (in Rs.): 14841.8635275
ADDITION COMPONENT
S/N Item Name Amount (in Rs.)
1 Provision for Contingency @ Rs. 1688 Rs. 1688
2 Display Citizen Board @ Rs. 3000 Rs. 3000
Total Addition Component Amount (in Rs.): 4688
DEDUCTION COMPONENT
Sl.No. Item Name Amount (in Rs.)
No data to display.
Total Deduction Component Amount (in Rs.): 0
Total Net Amount (in Rs.): 329999.27418854