| State: Odisha |
District: Khordha |
Block: Khordha |
Gram Panchayat: Barasahi |
Work Code: OD/362/3464/275250/407308/00032314 (Const Of Metal Morrum Road From Prafful Samantaray House To Nityananda Sundaray House,Kumbhilo)
Project Category: Road
| Financial Year: 2023-24 |
Execution Level: ps |
| Executing Agency: Panchayat Samiti, Khordha |
Proposal Date: - |
| Date of Commencement: 15-09-2025 |
Date of Completion: - |
| Scheme Name: 5th SFC Grant in Aid |
Scheme Component Name: All Weather Connectivity |
| Project Sub-Category: Mettalling Road |
Project Type: New Work |
| Name of Executant: SUBHASMITA SAHOO |
|
Administrative Approval Details
Approval No.: OD/362/3464/275250/407308/00032314/AS
Technical Sanction Details
Technical Sanction No.: OD/362/3464/275250/407308/00032314/TS
Fund Sanction No.: 15598
Fund Sanction Amount (in Rs.): 300000
ACTIVITY STATEMENT
| Sl.No. |
Activity taken |
Unit |
Quantity |
Unit Price (in Rs.) |
Total (in Rs.) |
| 1 |
Earth Work (AR0110) : Fine dressing of earth work in ordinary or hard soil in road formation - Fine dressing of earth work in ordinary or hard soil in road formaton according to the direction of the department including cutting or filling earth upto 0.15m depth of surface.
|
Sqm |
989.41695 |
4.6662 |
4616.81737209 |
| 2 |
Road Work (AR1308) : moorum and sand admixture laying in sub-base in layers not exceeding 100mm watering and compacting to the required density in O.M.C with PRR - Supplying & spreading moorum and sand admixture in a ratio (70:30) laying in sub-base in layers not exceeding 100mm watering and compacting to the required density in O.M.C with PRR including cost, conveyance, royalty, taxes cost of all labour & material, hire charges of T & P materials required for work as per specification and complete as per direction of Engineer-in-Charge.
|
Cum |
100.52464 |
1414.1884233516 |
142160.78214959 |
| 3 |
Road Work (AR1313) : Supplying & spreading with sand 6mm thick for road binding in road surface - Supplying & spreading with sand 6mm thick for road binding in road surface including cost, conveyance, royalty, taxes cost of all labour & material, hire charges of T & P materials required for work as per specification and direction of Engineer-in-Charge.
|
Sqm |
659.6113 |
6.9683158064516 |
4596.3798479041 |
| 4 |
Road Work (AR1341d) : Providing, laying, spreading and compacting Grading-II stone aggregates of specific sizes using stone screened dust to water bound macadam - Providing, laying, spreading and compacting Grading-II stone aggregates of specific sizes using stone screened dust to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with 3 wheeled steel roller 8-10 tonnes in stages to proper grade and camber, applying and brooming requisite type of screening/binding materials to fill up the interstices of coarse aggregate, watering and compacting to the required density as per Clause 404 of MoRT&H Specifications for Road & Bridge works(Last Revision).
|
Cum |
66.3462624 |
1794.7279921361 |
119073.49430289 |
| 5 |
Earth Work (AR0122Bii) : Earthwork in hard soil or gravelly soil within 5 Km. mechanical carriages and spreading in filling area/road berm within initial lead and lift - Earthwork in hard soil or gravelly soil within 5 Km.mechanical carriages and spreading in filling area/road berm within initial lead and lift including dressing and leveling the bed, etc. as per direction of Engineer-in-Charge.
|
Cum |
30.157392 |
361.33930892 |
10897.05118411 |
| 6 |
Road Work (AR1306) : Labour for admixture of sand and moorum - Labour for admixture of sand and moorum including labour cost, for work as per specification and direction of Engineer-in-Charge.
|
Cum |
100.52464 |
116.655 |
11726.7018792 |
Total Amount (in Rs.): 293071.22673578
LABOUR STATEMENT
| Sl.No. |
Activity Name |
Quantity (A) |
Unit |
Un-Skilled
|
Skilled
|
Semi-Skilled
|
| 462 |
562 |
512 |
| Qty/Unit (B) |
Total Qty (A*B) |
Qty/Unit (B) |
Total Qty (A*B) |
Qty/Unit (B) |
Total Qty (A*B) |
| 1 |
Earth Work (AR0110) : Fine dressing of earth work in ordinary or hard soil in road formation - Fine dressing of earth work in ordinary or hard soil in road formaton according to the direction of the department including cutting or filling earth upto 0.15m depth of surface.
|
989.41695 |
Square Meter |
0.01 |
9.8941695 |
- |
- |
- |
- |
| 2 |
Road Work (AR1308) : moorum and sand admixture laying in sub-base in layers not exceeding 100mm watering and compacting to the required density in O.M.C with PRR - Supplying & spreading moorum and sand admixture in a ratio (70:30) laying in sub-base in layers not exceeding 100mm watering and compacting to the required density in O.M.C with PRR including cost, conveyance, royalty, taxes cost of all labour & material, hire charges of T & P materials required for work as per specification and complete as per direction of Engineer-in-Charge.
|
100.52464 |
Cubic Meter |
1.1333922261484 |
113.93384551237 |
- |
- |
- |
- |
| 3 |
Road Work (AR1313) : Supplying & spreading with sand 6mm thick for road binding in road surface - Supplying & spreading with sand 6mm thick for road binding in road surface including cost, conveyance, royalty, taxes cost of all labour & material, hire charges of T & P materials required for work as per specification and direction of Engineer-in-Charge.
|
659.6113 |
Square Meter |
0.0032258064516129 |
2.1277783870968 |
- |
- |
- |
- |
| 4 |
Road Work (AR1341d) : Providing, laying, spreading and compacting Grading-II stone aggregates of specific sizes using stone screened dust to water bound macadam - Providing, laying, spreading and compacting Grading-II stone aggregates of specific sizes using stone screened dust to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with 3 wheeled steel roller 8-10 tonnes in stages to proper grade and camber, applying and brooming requisite type of screening/binding materials to fill up the interstices of coarse aggregate, watering and compacting to the required density as per Clause 404 of MoRT&H Specifications for Road & Bridge works(Last Revision).
|
66.3462624 |
Cubic Meter |
0.69444444444444 |
46.073793333333 |
0.028 |
1.8576953472 |
0.0055555555555556 |
0.36859034666667 |
| 5 |
Earth Work (AR0122Bii) : Earthwork in hard soil or gravelly soil within 5 Km. mechanical carriages and spreading in filling area/road berm within initial lead and lift - Earthwork in hard soil or gravelly soil within 5 Km.mechanical carriages and spreading in filling area/road berm within initial lead and lift including dressing and leveling the bed, etc. as per direction of Engineer-in-Charge.
|
30.157392 |
Cubic Meter |
0.43 |
12.96767856 |
- |
- |
- |
- |
| 6 |
Road Work (AR1306) : Labour for admixture of sand and moorum - Labour for admixture of sand and moorum including labour cost, for work as per specification and direction of Engineer-in-Charge.
|
100.52464 |
Cubic Meter |
0.25 |
25.13116 |
- |
- |
- |
- |
| Total Qty |
210.1284252928 |
0.36859034666667 |
1.8576953472 |
| Rate Per Man Day |
462 |
562 |
512 |
| Total Amount |
97079.332485272 |
207.14777482667 |
951.1400177664 |
Total Labour Amount (in Rs.): 98237.620277866
MATERIAL STATEMENT
| Sl.No. |
Activity Name |
Quantity (A) |
Unit |
BRM025 |
BRM029 |
BRMMR0037 |
BRM076 |
BRM026 |
BRMM402 |
BRMM401 |
| Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
| 1 |
Earth Work (AR0110) :.Fine dressing of earth work in ordinary or hard soil in road formation - Fine dressing of earth work in ordinary or hard soil in road formaton according to the direction of the department including cutting or filling earth upto 0.15m depth of surface. |
989.41695 |
Sqm |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
| 2 |
Road Work (AR1308) :.moorum and sand admixture laying in sub-base in layers not exceeding 100mm watering and compacting to the required density in O.M.C with PRR - Supplying & spreading moorum and sand admixture in a ratio (70:30) laying in sub-base in layers not exceeding 100mm watering and compacting to the required density in O.M.C with PRR including cost, conveyance, royalty, taxes cost of all labour & material, hire charges of T & P materials required for work as per specification and complete as per direction of Engineer-in-Charge. |
100.52464 |
Cum |
0.89578798586572 |
90.048764795477 |
0.384 |
38.60146176 |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
| 3 |
Road Work (AR1313) :.Supplying & spreading with sand 6mm thick for road binding in road surface - Supplying & spreading with sand 6mm thick for road binding in road surface including cost, conveyance, royalty, taxes cost of all labour & material, hire charges of T & P materials required for work as per specification and direction of Engineer-in-Charge. |
659.6113 |
Sqm |
- |
- |
0.006 |
3.9576678 |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
| 4 |
Road Work (AR1341d) :.Providing, laying, spreading and compacting Grading-II stone aggregates of specific sizes using stone screened dust to water bound macadam - Providing, laying, spreading and compacting Grading-II stone aggregates of specific sizes using stone screened dust to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with 3 wheeled steel roller 8-10 tonnes in stages to proper grade and camber, applying and brooming requisite type of screening/binding materials to fill up the interstices of coarse aggregate, watering and compacting to the required density as per Clause 404 of MoRT&H Specifications for Road & Bridge works(Last Revision). |
66.3462624 |
Cum |
- |
- |
- |
- |
0.4 |
26.53850496 |
1.21 |
80.278977504 |
0.34669444444444 |
23.001880583733 |
- |
- |
- |
- |
| 5 |
Earth Work (AR0122Bii) :.Earthwork in hard soil or gravelly soil within 5 Km. mechanical carriages and spreading in filling area/road berm within initial lead and lift - Earthwork in hard soil or gravelly soil within 5 Km.mechanical carriages and spreading in filling area/road berm within initial lead and lift including dressing and leveling the bed, etc. as per direction of Engineer-in-Charge. |
30.157392 |
Cum |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
-0.6666 |
-20.1029175072 |
1 |
30.157392 |
| 6 |
Road Work (AR1306) :.Labour for admixture of sand and moorum - Labour for admixture of sand and moorum including labour cost, for work as per specification and direction of Engineer-in-Charge. |
100.52464 |
Cum |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
| Total Qty |
90.048764795477 |
42.55912956 |
26.53850496 |
80.278977504 |
23.001880583733 |
-20.1029175072 |
30.157392 |
| Rate Per Unit |
532.56 |
853 |
10 |
867.3 |
672.74 |
175.38 |
276.01 |
| Total Amount |
47956.370179479 |
36302.93751468 |
265.3850496 |
69625.957189219 |
15474.285143901 |
-3525.6496724127 |
8323.74176592 |
Total Material Amount (in Rs.): 174423.02717039
ROYALTY STATEMENT
| Sl.No. |
Activity Name |
Quantity (A) |
Unit |
BRM025 |
BRM029 |
BRM026 |
| Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
| 1 |
Earth Work (AR0110) :.Fine dressing of earth work in ordinary or hard soil in road formation - Fine dressing of earth work in ordinary or hard soil in road formaton according to the direction of the department including cutting or filling earth upto 0.15m depth of surface. |
989.41695 |
Sqm |
- |
- |
- |
- |
- |
- |
| 2 |
Road Work (AR1308) :.moorum and sand admixture laying in sub-base in layers not exceeding 100mm watering and compacting to the required density in O.M.C with PRR - Supplying & spreading moorum and sand admixture in a ratio (70:30) laying in sub-base in layers not exceeding 100mm watering and compacting to the required density in O.M.C with PRR including cost, conveyance, royalty, taxes cost of all labour & material, hire charges of T & P materials required for work as per specification and complete as per direction of Engineer-in-Charge. |
100.52464 |
Cum |
0.89578798586572 |
90.048764795477 |
0.384 |
38.60146176 |
- |
- |
| 3 |
Road Work (AR1313) :.Supplying & spreading with sand 6mm thick for road binding in road surface - Supplying & spreading with sand 6mm thick for road binding in road surface including cost, conveyance, royalty, taxes cost of all labour & material, hire charges of T & P materials required for work as per specification and direction of Engineer-in-Charge. |
659.6113 |
Sqm |
- |
- |
0.006 |
3.9576678 |
- |
- |
| 4 |
Road Work (AR1341d) :.Providing, laying, spreading and compacting Grading-II stone aggregates of specific sizes using stone screened dust to water bound macadam - Providing, laying, spreading and compacting Grading-II stone aggregates of specific sizes using stone screened dust to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with 3 wheeled steel roller 8-10 tonnes in stages to proper grade and camber, applying and brooming requisite type of screening/binding materials to fill up the interstices of coarse aggregate, watering and compacting to the required density as per Clause 404 of MoRT&H Specifications for Road & Bridge works(Last Revision). |
66.3462624 |
Cum |
- |
- |
- |
- |
0.34669444444444 |
23.001880583733 |
| 5 |
Earth Work (AR0122Bii) :.Earthwork in hard soil or gravelly soil within 5 Km. mechanical carriages and spreading in filling area/road berm within initial lead and lift - Earthwork in hard soil or gravelly soil within 5 Km.mechanical carriages and spreading in filling area/road berm within initial lead and lift including dressing and leveling the bed, etc. as per direction of Engineer-in-Charge. |
30.157392 |
Cum |
- |
- |
- |
- |
- |
- |
| 6 |
Road Work (AR1306) :.Labour for admixture of sand and moorum - Labour for admixture of sand and moorum including labour cost, for work as per specification and direction of Engineer-in-Charge. |
100.52464 |
Cum |
- |
- |
- |
- |
- |
- |
| Total Qty |
90.048764795477 |
42.55912956 |
23.001880583733 |
| Rate Per Unit |
48.5 |
48.5 |
214.75 |
| Total Amount |
4367.3650925806 |
2064.11778366 |
4939.6538553567 |
Total Royalty Amount (in Rs.): 11371.136731597
ADDITION COMPONENT
| S/N |
Item Name |
Amount (in Rs.) |
| 1 |
Provision for Contingency @
1%
|
Rs. 2930.7122673578 |
| 2 |
Display Citizen Board @
Rs. 2000
|
Rs. 2000 |
| 3 |
Any Other Lumpsum @
Rs. 1998
|
Rs. 1998 |
Total Addition Component Amount (in Rs.): 6928.7122673578
DEDUCTION COMPONENT
| Sl.No. |
Item Name |
Amount (in Rs.) |
| No data to display. |
Total Deduction Component Amount (in Rs.): 0
Total Net Amount (in Rs.): 299999.93900314