State: Odisha District: Malkangiri Block: Chitrakonda Gram Panchayat: Jodamba
Work Code: OD/364/3483/119986/430799/00037312 (Repair & Maintenance of Primary school Building, Matikhal)
Project Category: Building
Financial Year: 2024-25 Execution Level: ps
Executing Agency: Panchayat Samiti, Chitrakonda Proposal Date: 07-12-2024
Date of Commencement: 04-09-2025 Date of Completion: 17-10-2025
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: Maintenance of Primary School Building
Project Sub-Category: Secondary School Project Type: Repair and Maintenance
Name of Executant: KAMALESH NAYAK
Administrative Approval Details
Approval No.: OD/364/3483/119986/430799/00037312/AS
Technical Sanction Details
Technical Sanction No.: OD/364/3483/119986/430799/00037312/TS
Fund Sanction No.: 28923
Fund Sanction Amount (in Rs.): 200000
ACTIVITY STATEMENT
Sl.No. Activity taken Unit Quantity Unit Price (in Rs.) Total (in Rs.)
1 Dismantling (AR1612) : Dismantling and removing 2.5 cm. thick artificial stone flooring - Dismantling and removing 2.5 cm. thick artificial stone flooring including stacking the useful materials for reuse and removing the debris within 50m lead and as per direction of Engineer-in-Charge. Sqm 59.34 100.34838709677 5954.6732903223
2 Dismantling (AR1613) : Removing old lime or cement plaster - Removing old lime or cement plaster from walls including raking out joints 12 mm deep and removing the debris within 50m lead and as per direction of Engineer-in-Charge. Sqm 254.925 50.174193548387 12790.656290323
3 Other Building Items. (AR1901B) : Vitrified Tile 600mmx600mm Plain Ivory - Supplying, fitting & fixing Vitrified Tile 600mmx600mm Plain Ivory in floors of size 600mm x 600 mm of approved make conforming IS:13755 laid on 20 mm thick cement mortar(1:4)and filling joints with white cement of approved quality including cost of all materials, taxes, labour, T&P , etc. required for the work all complete as per direction of Engineer-in-charge(for new work only) Sqm 59.34 1049.3692513074 62269.571372581
4 Dismantling (AR1620) : Dismantling and removing 2.5 cm thick grading concrete from roof - Dismantling and removing 2.5 cm thick grading concrete from roof slab cleaning the surface lowering and removing the debris within 50m lead and as per direction of Engineer-in-Charge. Sqm 99.16 112.89193548387 11194.364322581
5 Concrete (AR0317) : 2.5 cm thick grading concrete (1:2:2) on roof slab with 6mm size hard granite chips - 2.5 cm thick grading concrete (1:2:2) on roof slab with 6mm size hard granite chips including hoisting and laying in position compacting and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. (new work) Sqm 99.16 384.1520794148 38092.520194772
6 Plastering (AR1004) : 12mm thick cement plster (1:6) over Brick work in inside - 12mm thick cement plster (1:6) over Brick work in inside including racking out joints finishing smooth with proper plumb and line curing for proper period with cost conveyance, royality, taxes of all materials, labour and T & P required for the work etc. comp.and as per direction of Engineer-in-charge. Sqm 129.6 187.2964932048 24273.625519342
7 Painting (AR0901a) : Priming one coat in inner surface with primer of approved quality over woodwork - Priming one coat in inner surface with primer of approved quality over woodwork including cost conveyance, taxes of all materials, labor and T&P required for the work complete as per direction of the Engineer-in-charge. Sqm 150.87 70.12597102871 10579.905249101
8 Painting (AR0918c) : Finishing wall with two coat water proofing cement paint including one coat cement wash on the outer surface of approved shade on new work (Outside) - Finishing wall with two coat water proofing cement paint including one coat cement wash on the outer surface of approved shade on new work to give an even shade including all costs of labour, Paint, Brushes, and putty required for the work, etc. complete and as per direction of Engineer-in-charge. (Outside) Sqm 153.48 58.714936386624 9011.5684366191
9 Painting (AR0918Ai) : Third Floor - Finishing wall one coat with weather coat including all costs of labour, Paint, Primer and Brushes required for the work etc. complete and as per direction of Engineer-in-charge. Sqm 300.19 63.8018426625 19152.675148856
Total Amount (in Rs.): 193319.5598245
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Highly-Skilled Skilled
462 612 562
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Dismantling (AR1612) : Dismantling and removing 2.5 cm. thick artificial stone flooring - Dismantling and removing 2.5 cm. thick artificial stone flooring including stacking the useful materials for reuse and removing the debris within 50m lead and as per direction of Engineer-in-Charge. 59.34 Square Meter 0.21505376344086 12.761290322581 - - - -
2 Dismantling (AR1613) : Removing old lime or cement plaster - Removing old lime or cement plaster from walls including raking out joints 12 mm deep and removing the debris within 50m lead and as per direction of Engineer-in-Charge. 254.925 Square Meter 0.10752688172043 27.411290322581 - - - -
3 Other Building Items. (AR1901B) : Vitrified Tile 600mmx600mm Plain Ivory - Supplying, fitting & fixing Vitrified Tile 600mmx600mm Plain Ivory in floors of size 600mm x 600 mm of approved make conforming IS:13755 laid on 20 mm thick cement mortar(1:4)and filling joints with white cement of approved quality including cost of all materials, taxes, labour, T&P , etc. required for the work all complete as per direction of Engineer-in-charge(for new work only) 59.34 Square Meter 0.216 12.81744 - - 0.216 12.81744
4 Dismantling (AR1620) : Dismantling and removing 2.5 cm thick grading concrete from roof - Dismantling and removing 2.5 cm thick grading concrete from roof slab cleaning the surface lowering and removing the debris within 50m lead and as per direction of Engineer-in-Charge. 99.16 Square Meter 0.24193548387097 23.990322580645 - - - -
5 Concrete (AR0317) : 2.5 cm thick grading concrete (1:2:2) on roof slab with 6mm size hard granite chips - 2.5 cm thick grading concrete (1:2:2) on roof slab with 6mm size hard granite chips including hoisting and laying in position compacting and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. (new work) 99.16 Square Meter 0.36 35.6976 - - 0.1 9.916
6 Plastering (AR1004) : 12mm thick cement plster (1:6) over Brick work in inside - 12mm thick cement plster (1:6) over Brick work in inside including racking out joints finishing smooth with proper plumb and line curing for proper period with cost conveyance, royality, taxes of all materials, labour and T & P required for the work etc. comp.and as per direction of Engineer-in-charge. 129.6 Square Meter 0.12 15.552 0.14 18.144 - -
7 Painting (AR0901a) : Priming one coat in inner surface with primer of approved quality over woodwork - Priming one coat in inner surface with primer of approved quality over woodwork including cost conveyance, taxes of all materials, labor and T&P required for the work complete as per direction of the Engineer-in-charge. 150.87 Square Meter 0.053763440860215 8.1112903225806 - - 0.053763440860215 8.1112903225806
8 Painting (AR0918c) : Finishing wall with two coat water proofing cement paint including one coat cement wash on the outer surface of approved shade on new work (Outside) - Finishing wall with two coat water proofing cement paint including one coat cement wash on the outer surface of approved shade on new work to give an even shade including all costs of labour, Paint, Brushes, and putty required for the work, etc. complete and as per direction of Engineer-in-charge. (Outside) 153.48 Square Meter 0.042752688172043 6.5616825806452 0.0080645161290323 1.2377419354839 0.022 3.37656
9 Painting (AR0918Ai) : Third Floor - Finishing wall one coat with weather coat including all costs of labour, Paint, Primer and Brushes required for the work etc. complete and as per direction of Engineer-in-charge. 300.19 Square Meter 0.049777875 14.94282029625 - - 0.0416745 12.510268155
Total Qty 157.84573642528 46.731558477581 19.381741935484
Rate Per Man Day 462 612 562
Total Amount 72924.73022848 28599.713788279 10892.538967742
Total Labour Amount (in Rs.): 112416.9829845
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM174 BRM340 BRM028 BRM131 BRM064 BRM138 BRM143 BRM255
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Dismantling (AR1612) :.Dismantling and removing 2.5 cm. thick artificial stone flooring - Dismantling and removing 2.5 cm. thick artificial stone flooring including stacking the useful materials for reuse and removing the debris within 50m lead and as per direction of Engineer-in-Charge. 59.34 Sqm - - - - - - - - - - - - - - - -
2 Dismantling (AR1613) :.Removing old lime or cement plaster - Removing old lime or cement plaster from walls including raking out joints 12 mm deep and removing the debris within 50m lead and as per direction of Engineer-in-Charge. 254.925 Sqm - - - - - - - - - - - - - - - -
3 Other Building Items. (AR1901B) :.Vitrified Tile 600mmx600mm Plain Ivory - Supplying, fitting & fixing Vitrified Tile 600mmx600mm Plain Ivory in floors of size 600mm x 600 mm of approved make conforming IS:13755 laid on 20 mm thick cement mortar(1:4)and filling joints with white cement of approved quality including cost of all materials, taxes, labour, T&P , etc. required for the work all complete as per direction of Engineer-in-charge(for new work only) 59.34 Sqm 0.0076 0.450984 0.1074 6.373116 0.021 1.24614 1 59.34 - - - - - - - -
4 Dismantling (AR1620) :.Dismantling and removing 2.5 cm thick grading concrete from roof - Dismantling and removing 2.5 cm thick grading concrete from roof slab cleaning the surface lowering and removing the debris within 50m lead and as per direction of Engineer-in-Charge. 99.16 Sqm - - - - - - - - - - - - - - - -
5 Concrete (AR0317) :.2.5 cm thick grading concrete (1:2:2) on roof slab with 6mm size hard granite chips - 2.5 cm thick grading concrete (1:2:2) on roof slab with 6mm size hard granite chips including hoisting and laying in position compacting and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. (new work) 99.16 Sqm - - 0.1208 11.978528 0.0169 1.675804 - - 0.0169 1.675804 - - - - - -
6 Plastering (AR1004) :.12mm thick cement plster (1:6) over Brick work in inside - 12mm thick cement plster (1:6) over Brick work in inside including racking out joints finishing smooth with proper plumb and line curing for proper period with cost conveyance, royality, taxes of all materials, labour and T & P required for the work etc. comp.and as per direction of Engineer-in-charge. 129.6 Sqm - - 0.0358 4.63968 0.015 1.944 - - - - - - - - - -
7 Painting(AR0901a) :.Priming one coat in inner surface with primer of approved quality over woodwork - Priming one coat in inner surface with primer of approved quality over woodwork including cost conveyance, taxes of all materials, labor and T&P required for the work complete as per direction of the Engineer-in-charge. 150.87 Sqm - - - - - - - - - - 0.075 11.31525 - - - -
8 Painting(AR0918c) :.Finishing wall with two coat water proofing cement paint including one coat cement wash on the outer surface of approved shade on new work (Outside) - Finishing wall with two coat water proofing cement paint including one coat cement wash on the outer surface of approved shade on new work to give an even shade including all costs of labour, Paint, Brushes, and putty required for the work, etc. complete and as per direction of Engineer-in-charge. (Outside) 153.48 Sqm - - 0.010763440860215 1.6519729032258 - - - - - - - - 0.25 38.37 - -
9 Painting(AR0918Ai) :.Third Floor - Finishing wall one coat with weather coat including all costs of labour, Paint, Primer and Brushes required for the work etc. complete and as per direction of Engineer-in-charge. 300.19 Sqm - - - - - - - - - - - - - - 0.075 22.51425
Total Qty 0.450984 24.643296903226 4.865944 59.34 1.675804 11.31525 38.37 22.51425
Rate Per Unit 2095.472 614.662 1398.79 675.4086121 1321.51 155.86292 48.61292 195.57292
Total Amount 945.024344448 15147.298161131 6806.43380776 40078.747042014 2214.59174404 1763.62790553 1865.2777404 4403.17761411
Total Material Amount (in Rs.): 73224.178359433
ROYALTY STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM174 BRM340 BRM028 BRM131 BRM064 BRM138 BRM143 BRM255
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Dismantling (AR1612) :.Dismantling and removing 2.5 cm. thick artificial stone flooring - Dismantling and removing 2.5 cm. thick artificial stone flooring including stacking the useful materials for reuse and removing the debris within 50m lead and as per direction of Engineer-in-Charge. 59.34 Sqm - - - - - - - - - - - - - - - -
2 Dismantling (AR1613) :.Removing old lime or cement plaster - Removing old lime or cement plaster from walls including raking out joints 12 mm deep and removing the debris within 50m lead and as per direction of Engineer-in-Charge. 254.925 Sqm - - - - - - - - - - - - - - - -
3 Other Building Items. (AR1901B) :.Vitrified Tile 600mmx600mm Plain Ivory - Supplying, fitting & fixing Vitrified Tile 600mmx600mm Plain Ivory in floors of size 600mm x 600 mm of approved make conforming IS:13755 laid on 20 mm thick cement mortar(1:4)and filling joints with white cement of approved quality including cost of all materials, taxes, labour, T&P , etc. required for the work all complete as per direction of Engineer-in-charge(for new work only) 59.34 Sqm 0.0076 0.450984 0.1074 6.373116 0.021 1.24614 1 59.34 - - - - - - - -
4 Dismantling (AR1620) :.Dismantling and removing 2.5 cm thick grading concrete from roof - Dismantling and removing 2.5 cm thick grading concrete from roof slab cleaning the surface lowering and removing the debris within 50m lead and as per direction of Engineer-in-Charge. 99.16 Sqm - - - - - - - - - - - - - - - -
5 Concrete (AR0317) :.2.5 cm thick grading concrete (1:2:2) on roof slab with 6mm size hard granite chips - 2.5 cm thick grading concrete (1:2:2) on roof slab with 6mm size hard granite chips including hoisting and laying in position compacting and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. (new work) 99.16 Sqm - - 0.1208 11.978528 0.0169 1.675804 - - 0.0169 1.675804 - - - - - -
6 Plastering (AR1004) :.12mm thick cement plster (1:6) over Brick work in inside - 12mm thick cement plster (1:6) over Brick work in inside including racking out joints finishing smooth with proper plumb and line curing for proper period with cost conveyance, royality, taxes of all materials, labour and T & P required for the work etc. comp.and as per direction of Engineer-in-charge. 129.6 Sqm - - 0.0358 4.63968 0.015 1.944 - - - - - - - - - -
7 Painting(AR0901a) :.Priming one coat in inner surface with primer of approved quality over woodwork - Priming one coat in inner surface with primer of approved quality over woodwork including cost conveyance, taxes of all materials, labor and T&P required for the work complete as per direction of the Engineer-in-charge. 150.87 Sqm - - - - - - - - - - 0.075 11.31525 - - - -
8 Painting(AR0918c) :.Finishing wall with two coat water proofing cement paint including one coat cement wash on the outer surface of approved shade on new work (Outside) - Finishing wall with two coat water proofing cement paint including one coat cement wash on the outer surface of approved shade on new work to give an even shade including all costs of labour, Paint, Brushes, and putty required for the work, etc. complete and as per direction of Engineer-in-charge. (Outside) 153.48 Sqm - - 0.010763440860215 1.6519729032258 - - - - - - - - 0.25 38.37 - -
9 Painting(AR0918Ai) :.Third Floor - Finishing wall one coat with weather coat including all costs of labour, Paint, Primer and Brushes required for the work etc. complete and as per direction of Engineer-in-charge. 300.19 Sqm - - - - - - - - - - - - - - 0.075 22.51425
Total Qty 0.450984 24.643296903226 4.865944 59.34 1.675804 11.31525 38.37 22.51425
Rate Per Unit 0 0 197.25 0 658.5 0 0 0
Total Amount 0 0 959.807454 0 1103.516934 0 0 0
Total Royalty Amount (in Rs.): 2063.324388
ADDITION COMPONENT
S/N Item Name Amount (in Rs.)
1 Provision for Contingency @ 1% Rs. 1933.195598245
2 Display Citizen Board @ Rs. 4747 Rs. 4747
Total Addition Component Amount (in Rs.): 6680.195598245
DEDUCTION COMPONENT
Sl.No. Item Name Amount (in Rs.)
No data to display.
Total Deduction Component Amount (in Rs.): 0
Total Net Amount (in Rs.): 199999.75542274