State: Odisha District: Bargarh Block: Sohella Gram Panchayat: Tungibandhali
Work Code: OD/347/3321/116580/380299/00040430 (IMPROVEMENT OF ROAD FROM TUNGIBANDHALI TO MATHURAPALI )
Project Category: Road
Financial Year: 2025-26 Execution Level: ps
Executing Agency: Panchayat Samiti, Sohella Proposal Date: -
Date of Commencement: 03-12-2025 Date of Completion: -
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: Maintenance and improvement of Road infrastructure
Project Sub-Category: Mettalling Road Project Type: Upgradation or Improvement
Name of Executant: JAYRAM BAG
Administrative Approval Details
Approval No.: OD/347/3321/116580/380299/00040430/AS
Technical Sanction Details
Technical Sanction No.: OD/347/3321/116580/380299/00040430/TS
Fund Sanction No.: 29133
Fund Sanction Amount (in Rs.): 1000000
ACTIVITY STATEMENT
Sl.No. Activity taken Unit Quantity Unit Price (in Rs.) Total (in Rs.)
1 Road Work (AR1305) : Filler materials laterite moorum and consolidation with H.R.R. - Supplying & spreading metal to proper camber and consolidation with filler materials laterite moorum and consolidation with H.R.R. including watering and turf edging including cost, conveyance, royalty, and taxes, etc. required for work as per specification and direction of Engineer-in-Charge. Cum 233.472 2241.1257811307 523240.11837215
2 Road Work (AR1307) : Supplying & spreading moorum and consolidation with HRR - Supplying & spreading moorum and consolidation with HRR including cost, conveyance, royalty, taxes cost of all labour & material, hire charges of T & P materials required for work as per specification and complete as per direction of Engineer-in-Charge. Cum 420.48 1113.0481286784 468014.47714669
Total Amount (in Rs.): 991254.59551884
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled
462
Qty/Unit (B) Total Qty (A*B)
1 Road Work (AR1305) : Filler materials laterite moorum and consolidation with H.R.R. - Supplying & spreading metal to proper camber and consolidation with filler materials laterite moorum and consolidation with H.R.R. including watering and turf edging including cost, conveyance, royalty, and taxes, etc. required for work as per specification and direction of Engineer-in-Charge. 233.472 Cubic Meter 1.7667844522968 412.49469964664
2 Road Work (AR1307) : Supplying & spreading moorum and consolidation with HRR - Supplying & spreading moorum and consolidation with HRR including cost, conveyance, royalty, taxes cost of all labour & material, hire charges of T & P materials required for work as per specification and complete as per direction of Engineer-in-Charge. 420.48 Cubic Meter 1.0600706713781 445.73851590106
Total Qty 858.2332155477
Rate Per Man Day 462
Total Amount 396503.74558304
Total Labour Amount (in Rs.): 396503.74558304
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM041 BRM025
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Road Work (AR1305) :.Filler materials laterite moorum and consolidation with H.R.R. - Supplying & spreading metal to proper camber and consolidation with filler materials laterite moorum and consolidation with H.R.R. including watering and turf edging including cost, conveyance, royalty, and taxes, etc. required for work as per specification and direction of Engineer-in-Charge. 233.472 Cum 1 233.472 0.3 70.0416
2 Road Work (AR1307) :.Supplying & spreading moorum and consolidation with HRR - Supplying & spreading moorum and consolidation with HRR including cost, conveyance, royalty, taxes cost of all labour & material, hire charges of T & P materials required for work as per specification and complete as per direction of Engineer-in-Charge. 420.48 Cum - - 1.28 538.2144
Total Qty 233.472 608.256
Rate Per Unit 1009.68 338.09
Total Amount 235732.00896 205645.27104
Total Material Amount (in Rs.): 441377.28
ROYALTY STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM041 BRM025
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Road Work (AR1305) :.Filler materials laterite moorum and consolidation with H.R.R. - Supplying & spreading metal to proper camber and consolidation with filler materials laterite moorum and consolidation with H.R.R. including watering and turf edging including cost, conveyance, royalty, and taxes, etc. required for work as per specification and direction of Engineer-in-Charge. 233.472 Cum 1 233.472 0.3 70.0416
2 Road Work (AR1307) :.Supplying & spreading moorum and consolidation with HRR - Supplying & spreading moorum and consolidation with HRR including cost, conveyance, royalty, taxes cost of all labour & material, hire charges of T & P materials required for work as per specification and complete as per direction of Engineer-in-Charge. 420.48 Cum - - 1.28 538.2144
Total Qty 233.472 608.256
Rate Per Unit 249.5 140.25
Total Amount 58251.264 85307.904
Total Royalty Amount (in Rs.): 143559.168
ADDITION COMPONENT
S/N Item Name Amount (in Rs.)
1 Provision for Contingency @ Rs. 3744 Rs. 3744
2 Display Citizen Board @ Rs. 5000 Rs. 5000
Total Addition Component Amount (in Rs.): 8744
DEDUCTION COMPONENT
Sl.No. Item Name Amount (in Rs.)
No data to display.
Total Deduction Component Amount (in Rs.): 0
Total Net Amount (in Rs.): 999998.59551884