State: Odisha District: Koraput Block: Kotpad Gram Panchayat: Chandili
Work Code: OD/363/3472/119815/428124/00043057 (repair and maintenance of AWC birahandi)
Project Category: Building
Financial Year: 2023-24 Execution Level: ps
Executing Agency: Panchayat Samiti, Kotpad Proposal Date: -
Date of Commencement: 29-07-2025 Date of Completion: -
Scheme Name: Asset Management Women and Child Development Department Scheme Component Name: Self/Personal Deposit
Project Sub-Category: AWC Project Type: Repair and Maintenance
Name of Executant: Rajesh Kumar Dhir
Administrative Approval Details
Approval No.: OD/363/3472/119815/428124/00043057/AS
Technical Sanction Details
Technical Sanction No.: OD/363/3472/119815/428124/00043057/TS
Fund Sanction No.:
Fund Sanction Amount (in Rs.): 45000
ACTIVITY STATEMENT
Sl.No. Activity taken Unit Quantity Unit Price (in Rs.) Total (in Rs.)
1 Plastering (AR1033) : White washing two coats with stone lime in any surface - White washing two coats with stone lime in any surface including all costs of labour, coaltar and brushes required for the work etc. complete and as per direction of Engineer-in-charge. Sqm 228.69 35.240277075269 8059.0989643433
2 Painting (AR0922) : Finishing wall two coats with distemper of approved shades on new work (Inside) - Finishing wall two coats with distemper of approved shades on new work to give an even shade including all costs of labor, Paint and Brushes required for the work, etc. complete and as per direction of the Engineer-in-charge.(Inside) Sqm 228.69 78.8252783 18026.552894427
3 Painting (AR0903i) : Painting two coats of enamel paint in outer surface paint (outer surface) - Painting two coats of enamel paint in outer surface paint including all costs of labour, Paint and brushes required for the work etc. complete and as per direction of Engineer-in-charge.(Outside) Sqm 17.28 164.21250721452 2837.5921246669
Total Amount (in Rs.): 28923.243983437
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Highly-Skilled
462 562 612
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Plastering (AR1033) : White washing two coats with stone lime in any surface - White washing two coats with stone lime in any surface including all costs of labour, coaltar and brushes required for the work etc. complete and as per direction of Engineer-in-charge. 228.69 Square Meter 0.0080645161290323 1.8442741935484 0.010752688172043 2.4590322580645 - -
2 Painting (AR0922) : Finishing wall two coats with distemper of approved shades on new work (Inside) - Finishing wall two coats with distemper of approved shades on new work to give an even shade including all costs of labor, Paint and Brushes required for the work, etc. complete and as per direction of the Engineer-in-charge.(Inside) 228.69 Square Meter 0.062 14.17878 - - 0.052 11.89188
3 Painting (AR0903i) : Painting two coats of enamel paint in outer surface paint (outer surface) - Painting two coats of enamel paint in outer surface paint including all costs of labour, Paint and brushes required for the work etc. complete and as per direction of Engineer-in-charge.(Outside) 17.28 Square Meter 0.11827956989247 2.0438709677419 - - 0.13440860215054 2.3225806451613
Total Qty 18.06692516129 2.4590322580645 14.214460645161
Rate Per Man Day 462 562 612
Total Amount 8346.9194245161 1381.9761290323 8699.2499148387
Total Labour Amount (in Rs.): 18428.145468387
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM031 BRM142 BRM141
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Plastering (AR1033) :.White washing two coats with stone lime in any surface - White washing two coats with stone lime in any surface including all costs of labour, coaltar and brushes required for the work etc. complete and as per direction of Engineer-in-charge. 228.69 Sqm 1.149247311828 262.82136774194 - - - -
2 Painting(AR0922) :.Finishing wall two coats with distemper of approved shades on new work (Inside) - Finishing wall two coats with distemper of approved shades on new work to give an even shade including all costs of labor, Paint and Brushes required for the work, etc. complete and as per direction of the Engineer-in-charge.(Inside) 228.69 Sqm - - 0.25 57.1725 - -
3 Painting(AR0903i) :.Painting two coats of enamel paint in outer surface paint (outer surface) - Painting two coats of enamel paint in outer surface paint including all costs of labour, Paint and brushes required for the work etc. complete and as per direction of Engineer-in-charge.(Outside) 17.28 Sqm - - - - 0.125 2.16
Total Qty 262.82136774194 57.1725 2.16
Rate Per Unit 21.86 70.30732 205.46732
Total Amount 5745.2750988387 4019.6452527 443.8094112
Total Material Amount (in Rs.): 10208.729762739
ROYALTY STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM142 BRM141
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Plastering (AR1033) :.White washing two coats with stone lime in any surface - White washing two coats with stone lime in any surface including all costs of labour, coaltar and brushes required for the work etc. complete and as per direction of Engineer-in-charge. 228.69 Sqm - - - -
2 Painting(AR0922) :.Finishing wall two coats with distemper of approved shades on new work (Inside) - Finishing wall two coats with distemper of approved shades on new work to give an even shade including all costs of labor, Paint and Brushes required for the work, etc. complete and as per direction of the Engineer-in-charge.(Inside) 228.69 Sqm 0.25 57.1725 - -
3 Painting(AR0903i) :.Painting two coats of enamel paint in outer surface paint (outer surface) - Painting two coats of enamel paint in outer surface paint including all costs of labour, Paint and brushes required for the work etc. complete and as per direction of Engineer-in-charge.(Outside) 17.28 Sqm - - 0.125 2.16
Total Qty 57.1725 2.16
Rate Per Unit 0 0
Total Amount 0 0
Total Royalty Amount (in Rs.): 0
ADDITION COMPONENT
S/N Item Name Amount (in Rs.)
1 Provision for Contingency @ Rs. 576.75 Rs. 576.75
2 Display Citizen Board @ Rs. 2000 Rs. 2000
3 Any Other Lumpsum @ Rs. 13500 Rs. 13500
Total Addition Component Amount (in Rs.): 16076.75
DEDUCTION COMPONENT
Sl.No. Item Name Amount (in Rs.)
No data to display.
Total Deduction Component Amount (in Rs.): 0
Total Net Amount (in Rs.): 44999.993983437