State: Odisha District: Balangir Block: Saintala Gram Panchayat: Kumbhari
Work Code: OD/345/3295/115999/421122/00052769 (IMP OF ROAD FROM KUMBHARI TO DHUMAMARA)
Project Category: Road
Financial Year: 2024-25 Execution Level: ps
Executing Agency: Panchayat Samiti, Saintala Proposal Date: -
Date of Commencement: 16-09-2025 Date of Completion: 23-10-2025
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: All Weather Connectivity
Project Sub-Category: Mettalling Road Project Type: Upgradation or Improvement
Name of Executant: Rajen Toppo
Administrative Approval Details
Approval No.: OD/345/3295/115999/421122/00052769/AS
Technical Sanction Details
Technical Sanction No.: OD/345/3295/115999/421122/00052769/TS
Fund Sanction No.: 30642
Fund Sanction Amount (in Rs.): 363336
ACTIVITY STATEMENT
Sl.No. Activity taken Unit Quantity Unit Price (in Rs.) Total (in Rs.)
1 Road Work (AR1308) : moorum and sand admixture laying in sub-base in layers not exceeding 100mm watering and compacting to the required density in O.M.C with PRR - Supplying & spreading moorum and sand admixture in a ratio (70:30) laying in sub-base in layers not exceeding 100mm watering and compacting to the required density in O.M.C with PRR including cost, conveyance, royalty, taxes cost of all labour & material, hire charges of T & P materials required for work as per specification and complete as per direction of Engineer-in-Charge. Cum 110.55 1029.8181980512 113846.40179456
2 Road Work (AR1305) : Filler materials laterite moorum and consolidation with H.R.R. - Supplying & spreading metal to proper camber and consolidation with filler materials laterite moorum and consolidation with H.R.R. including watering and turf edging including cost, conveyance, royalty, and taxes, etc. required for work as per specification and direction of Engineer-in-Charge. Cum 105.6 2273.3306411307 240063.7157034
Total Amount (in Rs.): 353910.11749796
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled
462
Qty/Unit (B) Total Qty (A*B)
1 Road Work (AR1308) : moorum and sand admixture laying in sub-base in layers not exceeding 100mm watering and compacting to the required density in O.M.C with PRR - Supplying & spreading moorum and sand admixture in a ratio (70:30) laying in sub-base in layers not exceeding 100mm watering and compacting to the required density in O.M.C with PRR including cost, conveyance, royalty, taxes cost of all labour & material, hire charges of T & P materials required for work as per specification and complete as per direction of Engineer-in-Charge. 110.55 Cubic Meter 1.1333922261484 125.29651060071
2 Road Work (AR1305) : Filler materials laterite moorum and consolidation with H.R.R. - Supplying & spreading metal to proper camber and consolidation with filler materials laterite moorum and consolidation with H.R.R. including watering and turf edging including cost, conveyance, royalty, and taxes, etc. required for work as per specification and direction of Engineer-in-Charge. 105.6 Cubic Meter 1.7667844522968 186.57243816254
Total Qty 311.86894876325
Rate Per Man Day 462
Total Amount 144083.45432862
Total Labour Amount (in Rs.): 144083.45432862
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM025 BRM029 BRM041
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Road Work (AR1308) :.moorum and sand admixture laying in sub-base in layers not exceeding 100mm watering and compacting to the required density in O.M.C with PRR - Supplying & spreading moorum and sand admixture in a ratio (70:30) laying in sub-base in layers not exceeding 100mm watering and compacting to the required density in O.M.C with PRR including cost, conveyance, royalty, taxes cost of all labour & material, hire charges of T & P materials required for work as per specification and complete as per direction of Engineer-in-Charge. 110.55 Cum 0.89578798586572 99.029361837456 0.384 42.4512 - -
2 Road Work (AR1305) :.Filler materials laterite moorum and consolidation with H.R.R. - Supplying & spreading metal to proper camber and consolidation with filler materials laterite moorum and consolidation with H.R.R. including watering and turf edging including cost, conveyance, royalty, and taxes, etc. required for work as per specification and direction of Engineer-in-Charge. 105.6 Cum 0.3 31.68 - - 1 105.6
Total Qty 130.70936183746 42.4512 105.6
Rate Per Unit 336.01 347.95 1172.19
Total Amount 43919.652671004 14770.89504 123783.264
Total Material Amount (in Rs.): 182473.811711
ROYALTY STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM025 BRM029 BRM041
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Road Work (AR1308) :.moorum and sand admixture laying in sub-base in layers not exceeding 100mm watering and compacting to the required density in O.M.C with PRR - Supplying & spreading moorum and sand admixture in a ratio (70:30) laying in sub-base in layers not exceeding 100mm watering and compacting to the required density in O.M.C with PRR including cost, conveyance, royalty, taxes cost of all labour & material, hire charges of T & P materials required for work as per specification and complete as per direction of Engineer-in-Charge. 110.55 Cum 0.89578798586572 99.029361837456 0.384 42.4512 - -
2 Road Work (AR1305) :.Filler materials laterite moorum and consolidation with H.R.R. - Supplying & spreading metal to proper camber and consolidation with filler materials laterite moorum and consolidation with H.R.R. including watering and turf edging including cost, conveyance, royalty, and taxes, etc. required for work as per specification and direction of Engineer-in-Charge. 105.6 Cum 0.3 31.68 - - 1 105.6
Total Qty 130.70936183746 42.4512 105.6
Rate Per Unit 40.25 40.25 149.5
Total Amount 5261.0518139576 1708.6608 15787.2
Total Royalty Amount (in Rs.): 22756.912613958
ADDITION COMPONENT
S/N Item Name Amount (in Rs.)
1 Provision for Contingency @ 1% Rs. 3539.1011749796
2 Display Citizen Board @ Rs. 2347 Rs. 2347
3 Any Other Lumpsum @ 1% Rs. 3539.1011749796
Total Addition Component Amount (in Rs.): 9425.2023499592
DEDUCTION COMPONENT
Sl.No. Item Name Amount (in Rs.)
No data to display.
Total Deduction Component Amount (in Rs.): 0
Total Net Amount (in Rs.): 363335.31984792