| State: Odisha |
District: Rayagada |
Block: Ramanaguda |
Gram Panchayat: Ukkamba |
Work Code: OD/370/3556/121248/426792/00054052 (REPAIR AND MAINTANENCE OF PRY SCHOOL PUJARIGUDA UKKAMBA)
Project Category: Building
| Financial Year: 2024-25 |
Execution Level: ps |
| Executing Agency: Panchayat Samiti, Ramanaguda |
Proposal Date: - |
| Date of Commencement: 16-10-2025 |
Date of Completion: - |
| Scheme Name: 5th SFC Grant in Aid |
Scheme Component Name: Maintenance of Primary School Building |
| Project Sub-Category: Elementary School |
Project Type: Repair and Maintenance |
| Name of Executant: TRINATH MISHRA |
|
Administrative Approval Details
Approval No.: OD/370/3556/121248/426792/00054052/AS
Technical Sanction Details
Technical Sanction No.: OD/370/3556/121248/426792/00054052/TS
Fund Sanction No.: 28923
Fund Sanction Amount (in Rs.): 150000
ACTIVITY STATEMENT
| Sl.No. |
Activity taken |
Unit |
Quantity |
Unit Price (in Rs.) |
Total (in Rs.) |
| 1 |
R.C.C. Work (AR0402) : Reinforced cement concrete (1:11/2:3) work with 12mm size black hard crusher broken granite chips including hoisting and laying in position compacting(To be used for minor repair work only) - 'Reinforced cement concrete (1:1.5:3) work with 12mm size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. (To be used for minor repair work only)
|
Cum |
2.1651 |
7577.25397054 |
16405.512571616 |
| 2 |
Masonry Brick Work (AR0603ci) : Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in superstructure - Brickwork with Flyash Bricks of size (23cm x 11cm x 8cm) in cement mortar (1:6) in superstructure having crushing strength not less than 75.00 Kg/cm2 with dimensional tolerance ±8 percent immersing the bricks in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge.
|
Cum |
13.18725 |
4940.515340672 |
65151.810926277 |
| 3 |
R.C.C. Work (AR0409) : Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position - Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position including cost of binding wire 18 to 20 gauge with cost of steel rod and as per drawing, design, and direction of Engineer-in-charge.
|
Qntl |
1.8 |
8933.9152161 |
16081.04738898 |
| 4 |
R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc
|
Sqm |
10.11 |
216.23489289764 |
2186.1347671951 |
| 5 |
R.C.C. Work (AR0410e) : Rigid and smooth centering and shuttering for R.C.C. works including false works and dismantling them after casting - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. Lintels Data for 7.8 sqm
|
Sqm |
8.13 |
499.15267251462 |
4058.1112275439 |
| 6 |
R.C.C. Work (AR0410a) : Centring & Shuttering for R.C.C. floor and roof slabs, landings,balconies, projecting sun shades and chajjas - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. floor and roof slabs, landings, balconies, projecting sun shades and chajjas up to 4.3m height
|
Sqm |
1.08 |
662.689943368 |
715.70513883744 |
| 7 |
Roofing (AR1132) : Supplying, feeting & fixing of G.C.I. Sheet (0.30mm thick) in roof drilling hole in wind ties - Supplying, fitting & fixing of G.C.I. Sheet (0.30mm thick) in roof drilling hole in wind ties including fixing of ridges valleys wind ties etc. including cost of fitting, Labour and material etc. complete as per direction of Engineer-in-Charge
|
Sqm |
57.105 |
521.37106791032 |
29772.894833019 |
| 8 |
Plastering (AR1014) : 16mm thick cement Plaster in CM (1:6) over brick work in inside. - 16mm thick cement Plaster in CM (1:6) over brick work in inside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc comp.and as per direction of Engineer-in-charge.
|
Sqm |
53.64 |
239.823471618 |
12864.13101759 |
Total Amount (in Rs.): 147235.34787106
LABOUR STATEMENT
| Sl.No. |
Activity Name |
Quantity (A) |
Unit |
Un-Skilled
|
Skilled
|
Highly-Skilled
|
Semi-Skilled
|
| 462 |
562 |
612 |
512 |
| Qty/Unit (B) |
Total Qty (A*B) |
Qty/Unit (B) |
Total Qty (A*B) |
Qty/Unit (B) |
Total Qty (A*B) |
Qty/Unit (B) |
Total Qty (A*B) |
| 1 |
R.C.C. Work (AR0402) : Reinforced cement concrete (1:11/2:3) work with 12mm size black hard crusher broken granite chips including hoisting and laying in position compacting(To be used for minor repair work only) - 'Reinforced cement concrete (1:1.5:3) work with 12mm size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. (To be used for minor repair work only)
|
2.1651 |
Cubic Meter |
4.6 |
9.95946 |
- |
- |
0.68 |
1.472268 |
- |
- |
| 2 |
Masonry Brick Work (AR0603ci) : Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in superstructure - Brickwork with Flyash Bricks of size (23cm x 11cm x 8cm) in cement mortar (1:6) in superstructure having crushing strength not less than 75.00 Kg/cm2 with dimensional tolerance ±8 percent immersing the bricks in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge.
|
13.18725 |
Cubic Meter |
2.96 |
39.03426 |
- |
- |
1.05 |
13.8466125 |
0.35 |
4.6155375 |
| 3 |
R.C.C. Work (AR0409) : Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position - Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position including cost of binding wire 18 to 20 gauge with cost of steel rod and as per drawing, design, and direction of Engineer-in-charge.
|
1.8 |
Quintal |
0.8 |
1.44 |
0.044 |
0.0792 |
- |
- |
0.3 |
0.54 |
| 4 |
R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc
|
10.11 |
Square Meter |
- |
- |
0.05 |
0.5055 |
0.05 |
0.5055 |
- |
- |
| 5 |
R.C.C. Work (AR0410e) : Rigid and smooth centering and shuttering for R.C.C. works including false works and dismantling them after casting - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. Lintels Data for 7.8 sqm
|
8.13 |
Square Meter |
- |
- |
0.16025641025641 |
1.3028846153846 |
0.16025641025641 |
1.3028846153846 |
- |
- |
| 6 |
R.C.C. Work (AR0410a) : Centring & Shuttering for R.C.C. floor and roof slabs, landings,balconies, projecting sun shades and chajjas - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. floor and roof slabs, landings, balconies, projecting sun shades and chajjas up to 4.3m height
|
1.08 |
Square Meter |
- |
- |
0.30555555555556 |
0.33 |
0.30555555555556 |
0.33 |
- |
- |
| 7 |
Roofing (AR1132) : Supplying, feeting & fixing of G.C.I. Sheet (0.30mm thick) in roof drilling hole in wind ties - Supplying, fitting & fixing of G.C.I. Sheet (0.30mm thick) in roof drilling hole in wind ties including fixing of ridges valleys wind ties etc. including cost of fitting, Labour and material etc. complete as per direction of Engineer-in-Charge
|
57.105 |
Square Meter |
0.21505376344086 |
12.28064516129 |
- |
- |
- |
- |
0.16129032258065 |
9.2104838709677 |
| 8 |
Plastering (AR1014) : 16mm thick cement Plaster in CM (1:6) over brick work in inside. - 16mm thick cement Plaster in CM (1:6) over brick work in inside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc comp.and as per direction of Engineer-in-charge.
|
53.64 |
Square Meter |
0.24 |
12.8736 |
- |
- |
0.16 |
8.5824 |
- |
- |
| Total Qty |
75.58796516129 |
26.039665115385 |
14.366021370968 |
2.2175846153846 |
| Rate Per Man Day |
462 |
562 |
612 |
512 |
| Total Amount |
34921.639904516 |
14634.291794846 |
8792.0050790323 |
1135.4033230769 |
Total Labour Amount (in Rs.): 59483.340101471
MATERIAL STATEMENT
| Sl.No. |
Activity Name |
Quantity (A) |
Unit |
BRM340 |
BRM028 |
BRM056 |
BRMMR0025 |
BRM006 |
BRM162 |
BRM341 |
BRM104 |
BRM092 |
BRM094 |
BRM084 |
BRM149 |
| Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
| 1 |
R.C.C. Work (AR0402) :.Reinforced cement concrete (1:11/2:3) work with 12mm size black hard crusher broken granite chips including hoisting and laying in position compacting(To be used for minor repair work only) - 'Reinforced cement concrete (1:1.5:3) work with 12mm size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. (To be used for minor repair work only) |
2.1651 |
Cum |
4.29 |
9.288279 |
0.45 |
0.974295 |
0.9 |
1.94859 |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
| 2 |
Masonry Brick Work (AR0603ci) :.Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in superstructure - Brickwork with Flyash Bricks of size (23cm x 11cm x 8cm) in cement mortar (1:6) in superstructure having crushing strength not less than 75.00 Kg/cm2 with dimensional tolerance ±8 percent immersing the bricks in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge. |
13.18725 |
Cum |
0.672 |
8.861832 |
0.28 |
3.69243 |
- |
- |
1 |
13.18725 |
400 |
5274.9 |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
| 3 |
R.C.C. Work (AR0409) :.Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position - Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position including cost of binding wire 18 to 20 gauge with cost of steel rod and as per drawing, design, and direction of Engineer-in-charge. |
1.8 |
Qntl |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
0.8 |
1.44 |
1.05 |
1.89 |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
| 4 |
R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc |
10.11 |
Sqm |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
0.00267 |
0.0269937 |
0.126 |
1.27386 |
- |
- |
- |
- |
- |
- |
| 5 |
R.C.C. Work (AR0410e) :.Rigid and smooth centering and shuttering for R.C.C. works including false works and dismantling them after casting - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. Lintels Data for 7.8 sqm |
8.13 |
Sqm |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
0.0052948717948718 |
0.043047307692308 |
- |
- |
0.26923076923077 |
2.1888461538462 |
- |
- |
- |
- |
| 6 |
R.C.C. Work (AR0410a) :.Centring & Shuttering for R.C.C. floor and roof slabs, landings,balconies, projecting sun shades and chajjas - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. floor and roof slabs, landings, balconies, projecting sun shades and chajjas up to 4.3m height |
1.08 |
Sqm |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
0.0050222222222222 |
0.005424 |
- |
- |
- |
- |
0.62222222222222 |
0.672 |
- |
- |
| 7 |
Roofing (AR1132) :.Supplying, feeting & fixing of G.C.I. Sheet (0.30mm thick) in roof drilling hole in wind ties - Supplying, fitting & fixing of G.C.I. Sheet (0.30mm thick) in roof drilling hole in wind ties including fixing of ridges valleys wind ties etc. including cost of fitting, Labour and material etc. complete as per direction of Engineer-in-Charge |
57.105 |
Sqm |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
1 |
57.105 |
| 8 |
Plastering (AR1014) :.16mm thick cement Plaster in CM (1:6) over brick work in inside. - 16mm thick cement Plaster in CM (1:6) over brick work in inside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc comp.and as per direction of Engineer-in-charge. |
53.64 |
Sqm |
0.043 |
2.30652 |
0.018 |
0.96552 |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
| Total Qty |
20.456631 |
5.632245 |
1.94859 |
13.18725 |
5274.9 |
1.44 |
1.89 |
0.075465007692308 |
1.27386 |
2.1888461538462 |
0.672 |
57.105 |
| Rate Per Unit |
537.807 |
352.89 |
1933.03 |
33 |
5.24616 |
90.1 |
6620.127 |
58573.086 |
229.106 |
240.106 |
250.166 |
318.144462 |
| Total Amount |
11001.719348217 |
1987.56293805 |
3766.6829277 |
435.17925 |
27672.969384 |
129.744 |
12512.04003 |
4420.2183855522 |
291.84896916 |
525.55509461538 |
168.111552 |
18167.63950251 |
Total Material Amount (in Rs.): 81079.271381805
ROYALTY STATEMENT
| Sl.No. |
Activity Name |
Quantity (A) |
Unit |
BRM340 |
BRM028 |
BRM056 |
BRM006 |
BRM341 |
BRM104 |
BRM092 |
BRM094 |
BRM084 |
BRM149 |
| Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
Qty/unit (B) |
Total Qty (A*B) |
| 1 |
R.C.C. Work (AR0402) :.Reinforced cement concrete (1:11/2:3) work with 12mm size black hard crusher broken granite chips including hoisting and laying in position compacting(To be used for minor repair work only) - 'Reinforced cement concrete (1:1.5:3) work with 12mm size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. (To be used for minor repair work only) |
2.1651 |
Cum |
4.29 |
9.288279 |
0.45 |
0.974295 |
0.9 |
1.94859 |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
| 2 |
Masonry Brick Work (AR0603ci) :.Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in superstructure - Brickwork with Flyash Bricks of size (23cm x 11cm x 8cm) in cement mortar (1:6) in superstructure having crushing strength not less than 75.00 Kg/cm2 with dimensional tolerance ±8 percent immersing the bricks in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge. |
13.18725 |
Cum |
0.672 |
8.861832 |
0.28 |
3.69243 |
- |
- |
400 |
5274.9 |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
| 3 |
R.C.C. Work (AR0409) :.Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position - Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position including cost of binding wire 18 to 20 gauge with cost of steel rod and as per drawing, design, and direction of Engineer-in-charge. |
1.8 |
Qntl |
- |
- |
- |
- |
- |
- |
- |
- |
1.05 |
1.89 |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
| 4 |
R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc |
10.11 |
Sqm |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
0.00267 |
0.0269937 |
0.000614 |
0.00620754 |
- |
- |
- |
- |
- |
- |
| 5 |
R.C.C. Work (AR0410e) :.Rigid and smooth centering and shuttering for R.C.C. works including false works and dismantling them after casting - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. Lintels Data for 7.8 sqm |
8.13 |
Sqm |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
0.0052948717948718 |
0.043047307692308 |
- |
- |
0.0035384615384615 |
0.028767692307692 |
- |
- |
- |
- |
| 6 |
R.C.C. Work (AR0410a) :.Centring & Shuttering for R.C.C. floor and roof slabs, landings,balconies, projecting sun shades and chajjas - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. floor and roof slabs, landings, balconies, projecting sun shades and chajjas up to 4.3m height |
1.08 |
Sqm |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
0.0050222222222222 |
0.005424 |
- |
- |
- |
- |
0.0076666666666667 |
0.00828 |
- |
- |
| 7 |
Roofing (AR1132) :.Supplying, feeting & fixing of G.C.I. Sheet (0.30mm thick) in roof drilling hole in wind ties - Supplying, fitting & fixing of G.C.I. Sheet (0.30mm thick) in roof drilling hole in wind ties including fixing of ridges valleys wind ties etc. including cost of fitting, Labour and material etc. complete as per direction of Engineer-in-Charge |
57.105 |
Sqm |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
1 |
57.105 |
| 8 |
Plastering (AR1014) :.16mm thick cement Plaster in CM (1:6) over brick work in inside. - 16mm thick cement Plaster in CM (1:6) over brick work in inside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc comp.and as per direction of Engineer-in-charge. |
53.64 |
Sqm |
0.043 |
2.30652 |
0.018 |
0.96552 |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
| Total Qty |
20.456631 |
5.632245 |
1.94859 |
5274.9 |
1.89 |
0.075465007692308 |
0.00620754 |
0.028767692307692 |
0.00828 |
57.105 |
| Rate Per Unit |
0 |
55.25 |
164.5 |
0.04025 |
0 |
0 |
0 |
0 |
0 |
0 |
| Total Amount |
0 |
311.18153625 |
320.543055 |
212.314725 |
0 |
0 |
0 |
0 |
0 |
0 |
Total Royalty Amount (in Rs.): 844.03931625
ADDITION COMPONENT
| S/N |
Item Name |
Amount (in Rs.) |
| 1 |
Provision for Contingency @
Rs. 1264
|
Rs. 1264 |
| 2 |
Display Citizen Board @
Rs. 1500
|
Rs. 1500 |
Total Addition Component Amount (in Rs.): 2764
DEDUCTION COMPONENT
| Sl.No. |
Item Name |
Amount (in Rs.) |
| No data to display. |
Total Deduction Component Amount (in Rs.): 0
Total Net Amount (in Rs.): 149999.34787106