State: Odisha District: Rayagada Block: Kasipur Gram Panchayat: Bankamba
Work Code: OD/370/3552/121174/426105/00060524 (Maintenance and improvement of Roads at Dakli)
Project Category: Road
Financial Year: 2022-23 Execution Level: ps
Executing Agency: Panchayat Samiti, Kasipur Proposal Date: 08-06-2021
Date of Commencement: 31-10-2025 Date of Completion: -
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: Maintenance and improvement of Road infrastructure
Project Sub-Category: CC Road Project Type: New Work
Name of Executant: KRISHNA PRIYA MANDAL
Administrative Approval Details
Approval No.: OD/370/3552/121174/426105/00060524/AS
Technical Sanction Details
Technical Sanction No.: OD/370/3552/121174/426105/00060524/TS
Fund Sanction No.: 9114
Fund Sanction Amount (in Rs.): 159826
ACTIVITY STATEMENT
Sl.No. Activity taken Unit Quantity Unit Price (in Rs.) Total (in Rs.)
1 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. Cum 16.98905 836.434732 14210.231483685
2 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. Cum 14.68805 5619.90563404 82545.454948061
3 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. Cum 6.998875 7170.19750248 50183.31604517
4 Earth Work (AR0122Ai) : Earth work in all kinds of soil within 50m, initial lead and 1.5m, initial lift - Earth work in all kinds of soil within 50m, initial lead and 1.5m, initial lift including rought dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per direction of the Engineer-in-charge. Cum 22.837425 220.96043508 5046.1673641069
5 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc Sqm 7.67 216.23489289764 1658.5216285249
Total Amount (in Rs.): 153643.69146955
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled
462 562 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 16.98905 Cubic Meter 0.1236 2.09984658 - - - -
2 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 14.68805 Cubic Meter 3.9 57.283395 - - 0.18 2.643849
3 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 6.998875 Cubic Meter 4.6 32.194825 - - 0.68 4.759235
4 Earth Work (AR0122Ai) : Earth work in all kinds of soil within 50m, initial lead and 1.5m, initial lift - Earth work in all kinds of soil within 50m, initial lead and 1.5m, initial lift including rought dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per direction of the Engineer-in-charge. 22.837425 Cubic Meter 0.473534 10.81429720995 - - - -
5 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 7.67 Square Meter - - 0.05 0.3835 0.05 0.3835
Total Qty 102.39236378995 7.786584 0.3835
Rate Per Man Day 462 562 512
Total Amount 47305.272070957 4376.060208 196.352
Total Labour Amount (in Rs.): 51877.684278957
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM340 BRM028 BRM044 BRM056 BRM104 BRM092
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 16.98905 Cum 1 16.98905 - - - - - - - - - - - -
2 Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 14.68805 Cum - - 2.29 33.6356345 0.48 7.050264 0.96 14.100528 - - - - - -
3 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 6.998875 Cum - - 3.23 22.60636625 0.45 3.14949375 - - 0.9 6.2989875 - - - -
4 Earth Work (AR0122Ai) :.Earth work in all kinds of soil within 50m, initial lead and 1.5m, initial lift - Earth work in all kinds of soil within 50m, initial lead and 1.5m, initial lift including rought dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per direction of the Engineer-in-charge. 22.837425 Cum - - - - - - - - - - - - - -
5 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 7.67 Sqm - - - - - - - - - - 0.00267 0.0204789 0.126 0.96642
Total Qty 16.98905 56.24200075 10.19975775 14.100528 6.2989875 0.0204789 0.96642
Rate Per Unit 673.45 555.642 678.39 1421.31 1867.93 58573.086 229.106
Total Amount 11441.2757225 31250.417780731 6919.4136600225 20041.22145168 11766.067720875 1199.5123708854 221.41262052
Total Material Amount (in Rs.): 82839.321327214
ROYALTY STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM340 BRM028 BRM044 BRM056 BRM104 BRM092
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 16.98905 Cum 1 16.98905 - - - - - - - - - - - -
2 Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 14.68805 Cum - - 2.29 33.6356345 0.48 7.050264 0.96 14.100528 - - - - - -
3 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 6.998875 Cum - - 3.23 22.60636625 0.45 3.14949375 - - 0.9 6.2989875 - - - -
4 Earth Work (AR0122Ai) :.Earth work in all kinds of soil within 50m, initial lead and 1.5m, initial lift - Earth work in all kinds of soil within 50m, initial lead and 1.5m, initial lift including rought dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per direction of the Engineer-in-charge. 22.837425 Cum - - - - - - - - - - - - - -
5 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 7.67 Sqm - - - - - - - - - - 0.00267 0.0204789 0.000614 0.00470938
Total Qty 16.98905 56.24200075 10.19975775 14.100528 6.2989875 0.0204789 0.00470938
Rate Per Unit 97.6 0 97.6 336.46 336.46 0 0
Total Amount 1658.13128 0 995.4963564 4744.26365088 2119.35733425 0 0
Total Royalty Amount (in Rs.): 9517.24862153
ADDITION COMPONENT
S/N Item Name Amount (in Rs.)
1 Provision for Contingency @ Rs. 1598 Rs. 1598
2 Display Citizen Board @ Rs. 4584 Rs. 4584
Total Addition Component Amount (in Rs.): 6182
DEDUCTION COMPONENT
Sl.No. Item Name Amount (in Rs.)
No data to display.
Total Deduction Component Amount (in Rs.): 0
Total Net Amount (in Rs.): 159825.69146955