State: Odisha District: Sonepur Block: Binka Gram Panchayat: Sankara
Work Code: OD/372/3567/121435/419086/00062593 (Const. of Toilet in AWC Bagbahali)
Project Category: Building
Financial Year: 2020-21 Execution Level: ps
Executing Agency: Panchayat Samiti, Binka Proposal Date: 14-02-2022
Date of Commencement: - Date of Completion: -
Scheme Name: Asset Management Women and Child Development Department Scheme Component Name: Self/Personal Deposit
Project Sub-Category: AWC Project Type: New Work
Name of Executant:
Administrative Approval Details
Approval No.:
Technical Sanction Details
Technical Sanction No.:
Fund Sanction No.:
Fund Sanction Amount (in Rs.): 12000
ACTIVITY STATEMENT
Sl.No. Activity taken Unit Quantity Unit Price (in Rs.) Total (in Rs.)
1 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. Cum 0.285 5534.18204766 1577.2418835831
2 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. Cum 0.286 6981.75775642 1996.7827183361
3 Painting (AR0901d) : Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces (Inner surface) - Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces including cost conveyance, taxes of all materials, labor and T&P required for the work complete as per direction of the Engineer-in-charge. Sqm 34.26 71.84257680551 2461.3266813568
4 Painting (AR0920) : Finishing wall two coats with plastic emulsion paint of approved shades on new work (Inside) - Finishing wall two coats with plastic emulsion paint of approved shades on new work to give an even shade including all costs of labor, Paint and Brushes required for the work, etc. complete and as per direction of the Engineer-in-charge.(Inside) Sqm 11.22 94.7676397125 1063.2929175742
5 Painting (AR0918cb) : Finishing wall two coats with weather coat with one coat waterbound Primer - Finishing wall two coats with weather coat with one coat waterbound Primer including all costs of labour, Paint, Primer, Brushes and putty required for the work etc. complete and as per direction of Engineer-in-charge.(Outside) Sqm 21.84 160.74115594024 3510.5868457348
Total Amount (in Rs.): 10609.231046585
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Skilled Un-Skilled Highly-Skilled
562 462 612
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 0.285 Cubic Meter 3.9 1.1115 0.18 0.0513 - -
2 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 0.286 Cubic Meter 4.6 1.3156 0.68 0.19448 - -
3 Painting (AR0901d) : Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces (Inner surface) - Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces including cost conveyance, taxes of all materials, labor and T&P required for the work complete as per direction of the Engineer-in-charge. 34.26 Square Meter 0.053763440860215 1.841935483871 - - 0.053763440860215 1.841935483871
4 Painting (AR0920) : Finishing wall two coats with plastic emulsion paint of approved shades on new work (Inside) - Finishing wall two coats with plastic emulsion paint of approved shades on new work to give an even shade including all costs of labor, Paint and Brushes required for the work, etc. complete and as per direction of the Engineer-in-charge.(Inside) 11.22 Square Meter 0.064 0.71808 - - 0.054 0.60588
5 Painting (AR0918cb) : Finishing wall two coats with weather coat with one coat waterbound Primer - Finishing wall two coats with weather coat with one coat waterbound Primer including all costs of labour, Paint, Primer, Brushes and putty required for the work etc. complete and as per direction of Engineer-in-charge.(Outside) 21.84 Square Meter 0.11776344086022 2.5719535483871 - - 0.10776344086022 2.3535535483871
Total Qty 0.24578 7.5590690322581 4.8013690322581
Rate Per Man Day 562 462 612
Total Amount 138.12836 3492.2898929032 2938.4378477419
Total Labour Amount (in Rs.): 6568.8561006452
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM340 BRM028 BRM044 BRM056 BRM253 BRM140 BRM255
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 0.285 Cum 2.29 0.65265 0.48 0.1368 0.96 0.2736 - - - - - - - -
2 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 0.286 Cum 3.23 0.92378 0.45 0.1287 - - 0.9 0.2574 - - - - - -
3 Painting(AR0901d) :.Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces (Inner surface) - Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces including cost conveyance, taxes of all materials, labor and T&P required for the work complete as per direction of the Engineer-in-charge. 34.26 Sqm - - - - - - - - 0.084 2.87784 - - - -
4 Painting(AR0920) :.Finishing wall two coats with plastic emulsion paint of approved shades on new work (Inside) - Finishing wall two coats with plastic emulsion paint of approved shades on new work to give an even shade including all costs of labor, Paint and Brushes required for the work, etc. complete and as per direction of the Engineer-in-charge.(Inside) 11.22 Sqm - - - - - - - - - - 0.125 1.4025 - -
5 Painting(AR0918cb) :.Finishing wall two coats with weather coat with one coat waterbound Primer - Finishing wall two coats with weather coat with one coat waterbound Primer including all costs of labour, Paint, Primer, Brushes and putty required for the work etc. complete and as per direction of Engineer-in-charge.(Outside) 21.84 Sqm - - - - - - - - 0.090322580645161 1.9726451612903 - - 0.125 2.73
Total Qty 1.57643 0.2655 0.2736 0.2574 4.8504851612903 1.4025 2.73
Rate Per Unit 558.057 417.99 1596.76 1981.51 159.39677 249.70677 195.15677
Total Amount 879.73779651 110.976345 436.873536 510.040674 773.15166764261 350.213744925 532.7779821
Total Material Amount (in Rs.): 3593.7717461776
ROYALTY STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM340 BRM028 BRM044 BRM056 BRM253 BRM140 BRM255
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 0.285 Cum 2.29 0.65265 0.48 0.1368 0.96 0.2736 - - - - - - - -
2 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 0.286 Cum 3.23 0.92378 0.45 0.1287 - - 0.9 0.2574 - - - - - -
3 Painting(AR0901d) :.Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces (Inner surface) - Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces including cost conveyance, taxes of all materials, labor and T&P required for the work complete as per direction of the Engineer-in-charge. 34.26 Sqm - - - - - - - - 0.084 2.87784 - - - -
4 Painting(AR0920) :.Finishing wall two coats with plastic emulsion paint of approved shades on new work (Inside) - Finishing wall two coats with plastic emulsion paint of approved shades on new work to give an even shade including all costs of labor, Paint and Brushes required for the work, etc. complete and as per direction of the Engineer-in-charge.(Inside) 11.22 Sqm - - - - - - - - - - 0.125 1.4025 - -
5 Painting(AR0918cb) :.Finishing wall two coats with weather coat with one coat waterbound Primer - Finishing wall two coats with weather coat with one coat waterbound Primer including all costs of labour, Paint, Primer, Brushes and putty required for the work etc. complete and as per direction of Engineer-in-charge.(Outside) 21.84 Sqm - - - - - - - - 0.090322580645161 1.9726451612903 - - 0.125 2.73
Total Qty 1.57643 0.2655 0.2736 0.2574 4.8504851612903 1.4025 2.73
Rate Per Unit 0 170.25 279.5 279.5 0 0 0
Total Amount 0 45.201375 76.4712 71.9433 0 0 0
Total Royalty Amount (in Rs.): 193.615875
ADDITION COMPONENT
S/N Item Name Amount (in Rs.)
1 Provision for PH Work @ Rs. 1150 Rs. 1150
2 Provision for Contingency @ Rs. 100 Rs. 100
3 Display Citizen Board @ Rs. 140.7 Rs. 140.7
Total Addition Component Amount (in Rs.): 1390.7
DEDUCTION COMPONENT
Sl.No. Item Name Amount (in Rs.)
No data to display.
Total Deduction Component Amount (in Rs.): 0
Total Net Amount (in Rs.): 11999.931046585