| State: Odisha | District: Jajpur | Block: Rasulpur | Gram Panchayat: Jabara |
| Financial Year: 2022-23 | Execution Level: ps |
| Executing Agency: Panchayat Samiti, Rasulpur | Proposal Date: - |
| Date of Commencement: 24-11-2025 | Date of Completion: - |
| Scheme Name: 5th SFC Grant in Aid | Scheme Component Name: Provision of Facilities at GP Head Quarter |
| Project Sub-Category: GP Facility Centre | Project Type: New Work |
| Name of Executant: SUCHISMITA BISWAL |
| Sl.No. | Activity taken | Unit | Quantity | Unit Price (in Rs.) | Total (in Rs.) |
|---|---|---|---|---|---|
| 1 | Earth Work (AR0122Ai) : Earth work in all kinds of soil within 50m, initial lead and 1.5m, initial lift - Earth work in all kinds of soil within 50m, initial lead and 1.5m, initial lift including rought dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per direction of the Engineer-in-charge. | Cum | 17.7687 | 220.96043508 | 3926.179682806 |
| 2 | Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. | Cum | 9.27465 | 751.847232 | 6973.1199302688 |
| 3 | Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. | Cum | 6.1831 | 5952.73917766 | 36806.38160939 |
| 4 | Masonry Brick Work (AR0603b) : Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in foundation and plinth - Brickwork with Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in foundation and plinth having crushing strength not less than 75.00 Kg/cm2 with dimensional tolerance ±8 percent immersing the bricks in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge. | Cum | 0.9775 | 4977.508915288 | 4865.514964694 |
| 5 | Masonry Brick Work (AR0603bi) : Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in superstructure - Brickwork with Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in superstructure having crushing strength not less than 75.00 Kg/cm2 with dimensional tolerance ±8 percent immersing the bricks in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge. | Cum | 25.0496 | 5010.838915288 | 125519.5104924 |
| 6 | Masonry Brick Work (AR0602bi) : Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:4) in superstructure - Brickwork with Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:4) in superstructure having crushing strength not less than 75.00 Kg/cm2 immerging the with dimensional tolerance ±8 percent immersing in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge. | Cum | 1.6246 | 5296.985501 | 8605.4826449246 |
| 7 | R.C.C. Work (AR0404Aa) : Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge (RCC foundation, footing bases of column, mass concreate, pre-cast slabs etc.) | Cum | 2.7225 | 6493.6721172047 | 17679.02233909 |
| 8 | R.C.C. Work (AR0404Ab) : Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge (RCC Plinth band) | Cum | 1.63125 | 7250.4942423464 | 11827.368732828 |
| 9 | R.C.C. Work (AR0404Ad) : Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge (RCC Lintels) | Cum | 1.766625 | 13157.956345735 | 23245.174629284 |
| 10 | R.C.C. Work (AR0404Ac) : Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge. (RCC Beams, Column, Girder & Bressmer etc) | Cum | 3.834875 | 14549.425504525 | 55795.228131665 |
| 11 | R.C.C. Work (AR0404Af) : Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge (RCC Sun sheds & Chajja) | Sqm | 4.98 | 1114.4088858323 | 5549.7562514449 |
| 12 | R.C.C. Work (AR0404Ag) : Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge (RCC Roof slab, landing, balcony, sun shade) | Cum | 7.599384 | 12795.556521595 | 97238.347501305 |
| 13 | R.C.C. Work (AR0409) : Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position - Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position including cost of binding wire 18 to 20 gauge with cost of steel rod and as per drawing, design, and direction of Engineer-in-charge. | Qntl | 20.61 | 8429.867838 | 173739.57614118 |
| 14 | Plastering (AR1004) : 12mm thick cement plster (1:6) over Brick work in inside - 12mm thick cement plster (1:6) over Brick work in inside including racking out joints finishing smooth with proper plumb and line curing for proper period with cost conveyance, royality, taxes of all materials, labour and T & P required for the work etc. comp.and as per direction of Engineer-in-charge. | Sqm | 98.3632 | 170.0503077332 | 16726.692429622 |
| 15 | Plastering (AR1014) : 16mm thick cement Plaster in CM (1:6) over brick work in inside. - 16mm thick cement Plaster in CM (1:6) over brick work in inside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc comp.and as per direction of Engineer-in-charge. | Sqm | 150.6932 | 244.341858522 | 36820.656554627 |
| 16 | Painting (AR0901di) : Priming one coat with outer surface primer of approved quality water-bound primer over plastering surfaces(outer surface ) - Priming one coat with outer surface primer of approved quality water-bound primer over plastering surfaces including cost conveyance, taxes of all materials, labor and T&P required for the work complete as per direction of the Engineer-in-charge. | Sqm | 248.695 | 72.536702463226 | 18039.515219092 |
| 17 | Painting (AR0918cb) : Finishing wall two coats with weather coat with one coat waterbound Primer - Finishing wall two coats with weather coat with one coat waterbound Primer including all costs of labour, Paint, Primer, Brushes and putty required for the work etc. complete and as per direction of Engineer-in-charge.(Outside) | Sqm | 295.78 | 160.17640605073 | 47376.977381685 |
| 18 | Flooring (AR0816a) : Fixing Marble Tiles in floor, treads or steps and landing of minimum 16 mm thick, dunguri Variety Up to 0.10 Sqm Above 0.10 Sqm. to 0.40 Sqm on a 25mm thick bed of cement mortar 1:1 - Fixing Marble Tiles in floor, treads or steps and landing of minimum 16 mm thick, dunguri Variety Up to 0.10 Sqm Above 0.10 Sqm. to 0.40 Sqm on a 25mm thick bed of cement mortar 1:1 (1cement: 1sand) jointed with neat cement slurry mixed with pigment to match the shades of the marble tiles including rubbing and polishing, cost of precast tiles complete as per direction of Enginer-in-charge. | Sqm | 32.4304 | 1437.6978128908 | 46625.115151174 |
| 19 | Flooring (AR0817af) : Fixing Marble Tiles of minimum 16 mm thick, dunguri Variety Up to 0.10 Sqm in dados skirting and risers of steps on 12mm thick cement plaster (1:3) - Fixing Marble Tiles of minimum 16 mm thick, dunguri Variety Up to 0.10 Sqm in dados, skirting and risers of steps on 12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with pigments to match the shade of the Marble tiles including rubbing and polishing complete including cost of precast tiles. | Sqm | 4.9785 | 1452.730928136 | 7232.4209257251 |
| 20 | Flooring (AR0817b) : Fixing ceramic tiles (20cmx30cm / 20cmx20cm special plain/printed series ceramic wall tiles of premium grade having thickness 6.5mm to 6.7mm confirming to IS 13753) - Fixing ceramic tiles (20cmx30cm / 20cmx20cm special plain/printed series ceramic wall tiles of premium grade having thickness 6.5mm to 6.7mm confirming to IS 13753) in wall cladding on 12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with pigments to match the shade of the ceramic tiles including rubbing and polishing, cost of precast tiles complete as per direction of Engineer-in-charge. | Sqm | 46.7376 | 874.546328136 | 40874.196465889 |
| 21 | Flooring (AR0817aq) : Fixing ceramic Tiles (30cmx30cm / 40cmx40cm special plain/printed series ceramic floor tiles of premium grade having thickness 7mm to 8mm confirming to IS 13755) in dados skirting and risers of steps on 12mm thick cement plaster (1:3) - Fixing ceramic Tiles (30cmx30cm / 40cmx40cm special plain/printed series ceramic floor tiles of premium grade having thickness 7mm to 8mm confirming to IS 13755) in dados skirting and risers of steps on 12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with pigments to match the shade of the ceramic tiles including rubbing and polishing, cost of precast tiles complete as per direction of Engineer-in-charge(For repair and maintenance) . | Sqm | 11.1216 | 2070.861028136 | 23031.288010517 |
| 22 | Painting (AR0903b) : Painting two coats of enamel paint with a coat of red oxide primer over iron surface - Painting two coats of enamel paint with a coat of red oxide primer over iron surface including all costs of labour, Paint, Primer, brushes and putty required for the work etc. complete and as per direction of Engineer-in-charge. | Sqm | 17.65245 | 229.57454532053 | 4052.5531825434 |
| Sl.No. | Activity Name | Quantity (A) | Unit | Un-Skilled | Skilled | Highly-Skilled | Semi-Skilled | ||||
|---|---|---|---|---|---|---|---|---|---|---|---|
| 462 | 562 | 612 | 512 | ||||||||
| Qty/Unit (B) | Total Qty (A*B) | Qty/Unit (B) | Total Qty (A*B) | Qty/Unit (B) | Total Qty (A*B) | Qty/Unit (B) | Total Qty (A*B) | ||||
| 1 | Earth Work (AR0122Ai) : Earth work in all kinds of soil within 50m, initial lead and 1.5m, initial lift - Earth work in all kinds of soil within 50m, initial lead and 1.5m, initial lift including rought dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per direction of the Engineer-in-charge. | 17.7687 | Cubic Meter | 0.473534 | 8.4140835858 | - | - | - | - | - | - |
| 2 | Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. | 9.27465 | Cubic Meter | 0.1236 | 1.14634674 | - | - | - | - | - | - |
| 3 | Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. | 6.1831 | Cubic Meter | 3.9 | 24.11409 | - | - | 0.18 | 1.112958 | - | - |
| 4 | Masonry Brick Work (AR0603b) : Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in foundation and plinth - Brickwork with Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in foundation and plinth having crushing strength not less than 75.00 Kg/cm2 with dimensional tolerance ±8 percent immersing the bricks in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge. | 0.9775 | Cubic Meter | 2.96 | 2.8934 | - | - | 1.05 | 1.026375 | 0.35 | 0.342125 |
| 5 | Masonry Brick Work (AR0603bi) : Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in superstructure - Brickwork with Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in superstructure having crushing strength not less than 75.00 Kg/cm2 with dimensional tolerance ±8 percent immersing the bricks in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge. | 25.0496 | Cubic Meter | 2.96 | 74.146816 | - | - | 1.05 | 26.30208 | 0.35 | 8.76736 |
| 6 | Masonry Brick Work (AR0602bi) : Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:4) in superstructure - Brickwork with Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:4) in superstructure having crushing strength not less than 75.00 Kg/cm2 immerging the with dimensional tolerance ±8 percent immersing in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge. | 1.6246 | Cubic Meter | 3.1 | 5.03626 | - | - | 1.05 | 1.70583 | 0.35 | 0.56861 |
| 7 | R.C.C. Work (AR0404Aa) : Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge (RCC foundation, footing bases of column, mass concreate, pre-cast slabs etc.) | 2.7225 | Cubic Meter | 1.3333 | 3.62990925 | 0.1323 | 0.36018675 | 0.175 | 0.4764375 | - | - |
| 8 | R.C.C. Work (AR0404Ab) : Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge (RCC Plinth band) | 1.63125 | Cubic Meter | 1.3333 | 2.174945625 | 0.3073 | 0.501283125 | 0.35 | 0.5709375 | - | - |
| 9 | R.C.C. Work (AR0404Ad) : Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge (RCC Lintels) | 1.766625 | Cubic Meter | 1.3333 | 2.3554411125 | 2.30105 | 4.06509245625 | 2.34375 | 4.14052734375 | - | - |
| 10 | R.C.C. Work (AR0404Ac) : Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge. (RCC Beams, Column, Girder & Bressmer etc) | 3.834875 | Cubic Meter | 1.3333 | 5.1130388375 | 5.29605 | 20.30968974375 | 5.33875 | 20.47343890625 | - | - |
| 11 | R.C.C. Work (AR0404Af) : Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge (RCC Sun sheds & Chajja) | 4.98 | Square Meter | 0.08333125 | 0.414989625 | 0.33963125 | 1.691363625 | 0.3423 | 1.704654 | - | - |
| 12 | R.C.C. Work (AR0404Ag) : Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge (RCC Roof slab, landing, balcony, sun shade) | 7.599384 | Cubic Meter | 1.3333 | 10.1322586872 | 3.11255 | 23.6534626692 | 3.15525 | 23.977956366 | - | - |
| 13 | R.C.C. Work (AR0409) : Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position - Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position including cost of binding wire 18 to 20 gauge with cost of steel rod and as per drawing, design, and direction of Engineer-in-charge. | 20.61 | Quintal | 0.8 | 16.488 | 0.044 | 0.90684 | - | - | 0.3 | 6.183 |
| 14 | Plastering (AR1004) : 12mm thick cement plster (1:6) over Brick work in inside - 12mm thick cement plster (1:6) over Brick work in inside including racking out joints finishing smooth with proper plumb and line curing for proper period with cost conveyance, royality, taxes of all materials, labour and T & P required for the work etc. comp.and as per direction of Engineer-in-charge. | 98.3632 | Square Meter | 0.12 | 11.803584 | - | - | 0.14 | 13.770848 | - | - |
| 15 | Plastering (AR1014) : 16mm thick cement Plaster in CM (1:6) over brick work in inside. - 16mm thick cement Plaster in CM (1:6) over brick work in inside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc comp.and as per direction of Engineer-in-charge. | 150.6932 | Square Meter | 0.24 | 36.166368 | - | - | 0.16 | 24.110912 | - | - |
| 16 | Painting (AR0901di) : Priming one coat with outer surface primer of approved quality water-bound primer over plastering surfaces(outer surface ) - Priming one coat with outer surface primer of approved quality water-bound primer over plastering surfaces including cost conveyance, taxes of all materials, labor and T&P required for the work complete as per direction of the Engineer-in-charge. | 248.695 | Square Meter | 0.053763440860215 | 13.370698924731 | - | - | - | - | 0.053763440860215 | 13.370698924731 |
| 17 | Painting (AR0918cb) : Finishing wall two coats with weather coat with one coat waterbound Primer - Finishing wall two coats with weather coat with one coat waterbound Primer including all costs of labour, Paint, Primer, Brushes and putty required for the work etc. complete and as per direction of Engineer-in-charge.(Outside) | 295.78 | Square Meter | 0.11776344086022 | 34.832070537634 | - | - | - | - | 0.10776344086022 | 31.874270537634 |
| 18 | Flooring (AR0816a) : Fixing Marble Tiles in floor, treads or steps and landing of minimum 16 mm thick, dunguri Variety Up to 0.10 Sqm Above 0.10 Sqm. to 0.40 Sqm on a 25mm thick bed of cement mortar 1:1 - Fixing Marble Tiles in floor, treads or steps and landing of minimum 16 mm thick, dunguri Variety Up to 0.10 Sqm Above 0.10 Sqm. to 0.40 Sqm on a 25mm thick bed of cement mortar 1:1 (1cement: 1sand) jointed with neat cement slurry mixed with pigment to match the shades of the marble tiles including rubbing and polishing, cost of precast tiles complete as per direction of Enginer-in-charge. | 32.4304 | Square Meter | 0.216 | 7.0049664 | 0.55 | 17.83672 | - | - | 0.216 | 7.0049664 |
| 19 | Flooring (AR0817af) : Fixing Marble Tiles of minimum 16 mm thick, dunguri Variety Up to 0.10 Sqm in dados skirting and risers of steps on 12mm thick cement plaster (1:3) - Fixing Marble Tiles of minimum 16 mm thick, dunguri Variety Up to 0.10 Sqm in dados, skirting and risers of steps on 12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with pigments to match the shade of the Marble tiles including rubbing and polishing complete including cost of precast tiles. | 4.9785 | Square Meter | 0.325 | 1.6180125 | 0.76 | 3.78366 | - | - | 0.325 | 1.6180125 |
| 20 | Flooring (AR0817b) : Fixing ceramic tiles (20cmx30cm / 20cmx20cm special plain/printed series ceramic wall tiles of premium grade having thickness 6.5mm to 6.7mm confirming to IS 13753) - Fixing ceramic tiles (20cmx30cm / 20cmx20cm special plain/printed series ceramic wall tiles of premium grade having thickness 6.5mm to 6.7mm confirming to IS 13753) in wall cladding on 12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with pigments to match the shade of the ceramic tiles including rubbing and polishing, cost of precast tiles complete as per direction of Engineer-in-charge. | 46.7376 | Square Meter | 0.325 | 15.18972 | - | - | - | - | 0.325 | 15.18972 |
| 21 | Flooring (AR0817aq) : Fixing ceramic Tiles (30cmx30cm / 40cmx40cm special plain/printed series ceramic floor tiles of premium grade having thickness 7mm to 8mm confirming to IS 13755) in dados skirting and risers of steps on 12mm thick cement plaster (1:3) - Fixing ceramic Tiles (30cmx30cm / 40cmx40cm special plain/printed series ceramic floor tiles of premium grade having thickness 7mm to 8mm confirming to IS 13755) in dados skirting and risers of steps on 12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with pigments to match the shade of the ceramic tiles including rubbing and polishing, cost of precast tiles complete as per direction of Engineer-in-charge(For repair and maintenance) . | 11.1216 | Square Meter | 0.325 | 3.61452 | 0.76 | 8.452416 | - | - | 0.325 | 3.61452 |
| 22 | Painting (AR0903b) : Painting two coats of enamel paint with a coat of red oxide primer over iron surface - Painting two coats of enamel paint with a coat of red oxide primer over iron surface including all costs of labour, Paint, Primer, brushes and putty required for the work etc. complete and as per direction of Engineer-in-charge. | 17.65245 | Square Meter | 0.17204301075269 | 3.0369806451613 | - | - | - | - | 0.18817204301075 | 3.3216975806452 |
| Total Qty | 282.69650047053 | 119.372954616 | 91.854980943011 | 81.5607143692 | |||||||
| Rate Per Man Day | 462 | 562 | 612 | 512 | |||||||
| Total Amount | 130605.78321738 | 67087.600494192 | 56215.248337123 | 41759.08575703 | |||||||
| Sl.No. | Activity Name | Quantity (A) | Unit | BRM029 | BRM340 | BRM028 | BRM044 | BRM005 | BRMMR0025 | BRM060 | BRM052 | BRM104 | BRM092 | BRM094 | BRM084 | BRM162 | BRM341 | BRM253 | BRM255 | BRM118 | BRMMR0027 | BRM117 | CON026 | BRM129 | BRM123 | BRM137 | BRM141 | ||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Qty/unit (B) | Total Qty (A*B) | Qty/unit (B) | Total Qty (A*B) | Qty/unit (B) | Total Qty (A*B) | Qty/unit (B) | Total Qty (A*B) | Qty/unit (B) | Total Qty (A*B) | Qty/unit (B) | Total Qty (A*B) | Qty/unit (B) | Total Qty (A*B) | Qty/unit (B) | Total Qty (A*B) | Qty/unit (B) | Total Qty (A*B) | Qty/unit (B) | Total Qty (A*B) | Qty/unit (B) | Total Qty (A*B) | Qty/unit (B) | Total Qty (A*B) | Qty/unit (B) | Total Qty (A*B) | Qty/unit (B) | Total Qty (A*B) | Qty/unit (B) | Total Qty (A*B) | Qty/unit (B) | Total Qty (A*B) | Qty/unit (B) | Total Qty (A*B) | Qty/unit (B) | Total Qty (A*B) | Qty/unit (B) | Total Qty (A*B) | Qty/unit (B) | Total Qty (A*B) | Qty/unit (B) | Total Qty (A*B) | Qty/unit (B) | Total Qty (A*B) | Qty/unit (B) | Total Qty (A*B) | Qty/unit (B) | Total Qty (A*B) | ||||
| 1 | Earth Work (AR0122Ai) :.Earth work in all kinds of soil within 50m, initial lead and 1.5m, initial lift - Earth work in all kinds of soil within 50m, initial lead and 1.5m, initial lift including rought dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per direction of the Engineer-in-charge. | 17.7687 | Cum | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
| 2 | Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. | 9.27465 | Cum | 1 | 9.27465 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
| 3 | Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. | 6.1831 | Cum | - | - | 2.29 | 14.159299 | 0.48 | 2.967888 | 0.96 | 5.935776 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
| 4 | Masonry Brick Work (AR0603b) :.Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in foundation and plinth - Brickwork with Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in foundation and plinth having crushing strength not less than 75.00 Kg/cm2 with dimensional tolerance ±8 percent immersing the bricks in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge. | 0.9775 | Cum | - | - | 0.672 | 0.65688 | 0.28 | 0.2737 | - | - | 350 | 342.125 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
| 5 | Masonry Brick Work (AR0603bi) :.Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in superstructure - Brickwork with Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in superstructure having crushing strength not less than 75.00 Kg/cm2 with dimensional tolerance ±8 percent immersing the bricks in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge. | 25.0496 | Cum | - | - | 0.672 | 16.8333312 | 0.28 | 7.013888 | - | - | 350 | 8767.36 | 1 | 25.0496 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
| 6 | Masonry Brick Work (AR0602bi) :.Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:4) in superstructure - Brickwork with Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:4) in superstructure having crushing strength not less than 75.00 Kg/cm2 immerging the with dimensional tolerance ±8 percent immersing in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge. | 1.6246 | Cum | - | - | 1 | 1.6246 | 0.28 | 0.454888 | - | - | 350 | 568.61 | 1 | 1.6246 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
| 7 | R.C.C. Work (AR0404Aa) :.Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge (RCC foundation, footing bases of column, mass concreate, pre-cast slabs etc.) | 2.7225 | Cum | - | - | 3.4733 | 9.45605925 | 0.45 | 1.225125 | - | - | - | - | - | - | 0.36 | 0.9801 | 0.54 | 1.47015 | 0.004005 | 0.0109036125 | 0.189 | 0.5145525 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
| 8 | R.C.C. Work (AR0404Ab) :.Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge (RCC Plinth band) | 1.63125 | Cum | - | - | 3.4733 | 5.665820625 | 0.45 | 0.7340625 | - | - | - | - | - | - | 0.36 | 0.58725 | 0.54 | 0.880875 | 0.01335 | 0.0217771875 | 0.63 | 1.0276875 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
| 9 | R.C.C. Work (AR0404Ad) :.Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge (RCC Lintels) | 1.766625 | Cum | - | - | 3.4733 | 6.1360186125 | 0.45 | 0.79498125 | - | - | - | - | - | - | 0.36 | 0.635985 | 0.54 | 0.9539775 | 0.0741335 | 0.1309660944375 | - | - | 3.7695 | 6.6592929375 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
| 10 | R.C.C. Work (AR0404Ac) :.Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge. (RCC Beams, Column, Girder & Bressmer etc) | 3.834875 | Cum | - | - | 3.4733 | 13.3196713375 | 0.45 | 1.72569375 | - | - | - | - | - | - | 0.36 | 1.380555 | 0.54 | 2.0708325 | 0.041529 | 0.159258523875 | - | - | - | - | 4.4196 | 16.94861355 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
| 11 | R.C.C. Work (AR0404Af) :.Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge (RCC Sun sheds & Chajja) | 4.98 | Sqm | - | - | 0.21708125 | 1.081064625 | 0.028125 | 0.1400625 | - | - | - | - | - | - | 0.0225 | 0.11205 | 0.03375 | 0.168075 | 0.00552344 | 0.0275067312 | - | - | - | - | 0.68432 | 3.4079136 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
| 12 | R.C.C. Work (AR0404Ag) :.Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge (RCC Roof slab, landing, balcony, sun shade) | 7.599384 | Cum | - | - | 3.4733 | 26.3949404472 | 0.45 | 3.4197228 | - | - | - | - | - | - | 0.36 | 2.73577824 | 0.54 | 4.10366736 | 0.0502172 | 0.3816197862048 | - | - | - | - | 6.2216 | 47.2803274944 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
| 13 | R.C.C. Work (AR0409) :.Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position - Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position including cost of binding wire 18 to 20 gauge with cost of steel rod and as per drawing, design, and direction of Engineer-in-charge. | 20.61 | Qntl | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | 0.8 | 16.488 | 1.05 | 21.6405 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
| 14 | Plastering (AR1004) :.12mm thick cement plster (1:6) over Brick work in inside - 12mm thick cement plster (1:6) over Brick work in inside including racking out joints finishing smooth with proper plumb and line curing for proper period with cost conveyance, royality, taxes of all materials, labour and T & P required for the work etc. comp.and as per direction of Engineer-in-charge. | 98.3632 | Sqm | - | - | 0.0358 | 3.52140256 | 0.015 | 1.475448 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
| 15 | Plastering (AR1014) :.16mm thick cement Plaster in CM (1:6) over brick work in inside. - 16mm thick cement Plaster in CM (1:6) over brick work in inside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc comp.and as per direction of Engineer-in-charge. | 150.6932 | Sqm | - | - | 0.043 | 6.4798076 | 0.018 | 2.7124776 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
| 16 | Painting(AR0901di) :.Priming one coat with outer surface primer of approved quality water-bound primer over plastering surfaces(outer surface ) - Priming one coat with outer surface primer of approved quality water-bound primer over plastering surfaces including cost conveyance, taxes of all materials, labor and T&P required for the work complete as per direction of the Engineer-in-charge. | 248.695 | Sqm | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | 0.090322580645161 | 22.462774193548 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
| 17 | Painting(AR0918cb) :.Finishing wall two coats with weather coat with one coat waterbound Primer - Finishing wall two coats with weather coat with one coat waterbound Primer including all costs of labour, Paint, Primer, Brushes and putty required for the work etc. complete and as per direction of Engineer-in-charge.(Outside) | 295.78 | Sqm | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | 0.090322580645161 | 26.715612903226 | 0.125 | 36.9725 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
| 18 | Flooring (AR0816a) :.Fixing Marble Tiles in floor, treads or steps and landing of minimum 16 mm thick, dunguri Variety Up to 0.10 Sqm Above 0.10 Sqm. to 0.40 Sqm on a 25mm thick bed of cement mortar 1:1 - Fixing Marble Tiles in floor, treads or steps and landing of minimum 16 mm thick, dunguri Variety Up to 0.10 Sqm Above 0.10 Sqm. to 0.40 Sqm on a 25mm thick bed of cement mortar 1:1 (1cement: 1sand) jointed with neat cement slurry mixed with pigment to match the shades of the marble tiles including rubbing and polishing, cost of precast tiles complete as per direction of Enginer-in-charge. | 32.4304 | Sqm | - | - | 0.2737 | 8.87620048 | 0.013 | 0.4215952 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | 1 | 32.4304 | 1 | 32.4304 | - | - | - | - | - | - | - | - | - | - | - | - |
| 19 | Flooring (AR0817af) :.Fixing Marble Tiles of minimum 16 mm thick, dunguri Variety Up to 0.10 Sqm in dados skirting and risers of steps on 12mm thick cement plaster (1:3) - Fixing Marble Tiles of minimum 16 mm thick, dunguri Variety Up to 0.10 Sqm in dados, skirting and risers of steps on 12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with pigments to match the shade of the Marble tiles including rubbing and polishing complete including cost of precast tiles. | 4.9785 | Sqm | - | - | 0.1375 | 0.68454375 | 0.015 | 0.0746775 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | 1 | 4.9785 | 1 | 4.9785 | 0.1375 | 0.68454375 | - | - | - | - | - | - | - | - |
| 20 | Flooring (AR0817b) :.Fixing ceramic tiles (20cmx30cm / 20cmx20cm special plain/printed series ceramic wall tiles of premium grade having thickness 6.5mm to 6.7mm confirming to IS 13753) - Fixing ceramic tiles (20cmx30cm / 20cmx20cm special plain/printed series ceramic wall tiles of premium grade having thickness 6.5mm to 6.7mm confirming to IS 13753) in wall cladding on 12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with pigments to match the shade of the ceramic tiles including rubbing and polishing, cost of precast tiles complete as per direction of Engineer-in-charge. | 46.7376 | Sqm | - | - | 0.1375 | 6.42642 | 0.015 | 0.701064 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | 1 | 46.7376 | - | - | - | - | - | - |
| 21 | Flooring (AR0817aq) :.Fixing ceramic Tiles (30cmx30cm / 40cmx40cm special plain/printed series ceramic floor tiles of premium grade having thickness 7mm to 8mm confirming to IS 13755) in dados skirting and risers of steps on 12mm thick cement plaster (1:3) - Fixing ceramic Tiles (30cmx30cm / 40cmx40cm special plain/printed series ceramic floor tiles of premium grade having thickness 7mm to 8mm confirming to IS 13755) in dados skirting and risers of steps on 12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with pigments to match the shade of the ceramic tiles including rubbing and polishing, cost of precast tiles complete as per direction of Engineer-in-charge(For repair and maintenance) . | 11.1216 | Sqm | - | - | 0.1375 | 1.52922 | 0.015 | 0.166824 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | 1 | 11.1216 | - | - | 0.1375 | 1.52922 | - | - | 1 | 11.1216 | - | - | - | - |
| 22 | Painting(AR0903b) :.Painting two coats of enamel paint with a coat of red oxide primer over iron surface - Painting two coats of enamel paint with a coat of red oxide primer over iron surface including all costs of labour, Paint, Primer, brushes and putty required for the work etc. complete and as per direction of Engineer-in-charge. | 17.65245 | Sqm | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | 0.054 | 0.9532323 | 0.125 | 2.20655625 |
| Total Qty | 9.27465 | 122.8452794872 | 24.3020981 | 5.935776 | 9678.095 | 26.6742 | 6.43171824 | 9.64757736 | 0.7320319357173 | 1.54224 | 6.6592929375 | 67.6368546444 | 16.488 | 21.6405 | 49.178387096774 | 36.9725 | 32.4304 | 48.5305 | 4.9785 | 2.21376375 | 46.7376 | 11.1216 | 0.9532323 | 2.20655625 | |||||||||||||||||||||||||||
| Rate Per Unit | 413.05 | 568.667 | 417.99 | 1776.47 | 6.04185 | 33 | 2250.97 | 2218.16 | 58573.086 | 229.106 | 240.106 | 250.166 | 90.1 | 6217.337 | 155.84787 | 193.24787 | 680.5011111 | 8.5 | 560.2011111 | 0 | 414.8011111 | 1185.2011111 | 140.74787 | 200.44787 | |||||||||||||||||||||||||||
| Total Amount | 3830.8941825 | 69858.056550148 | 10158.033984819 | 10544.72799072 | 58473.59827575 | 880.2486 | 14477.604806693 | 21399.870196858 | 42877.369525516 | 353.33643744 | 1598.9361900514 | 16920.441378971 | 1485.5688 | 134546.2813485 | 7664.3468790677 | 7144.856873575 | 22068.923233417 | 412.50925 | 2788.9612316114 | 0 | 19386.808410147 | 13181.33267721 | 134.1654158402 | 442.29950034769 | |||||||||||||||||||||||||||
| Sl.No. | Activity Name | Quantity (A) | Unit | BRM029 | BRM340 | BRM028 | BRM044 | BRM005 | BRM060 | BRM052 | BRM104 | BRM092 | BRM094 | BRM084 | BRM341 | BRM253 | BRM255 | BRM118 | BRM117 | BRM129 | BRM123 | BRM137 | BRM141 | ||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Qty/unit (B) | Total Qty (A*B) | Qty/unit (B) | Total Qty (A*B) | Qty/unit (B) | Total Qty (A*B) | Qty/unit (B) | Total Qty (A*B) | Qty/unit (B) | Total Qty (A*B) | Qty/unit (B) | Total Qty (A*B) | Qty/unit (B) | Total Qty (A*B) | Qty/unit (B) | Total Qty (A*B) | Qty/unit (B) | Total Qty (A*B) | Qty/unit (B) | Total Qty (A*B) | Qty/unit (B) | Total Qty (A*B) | Qty/unit (B) | Total Qty (A*B) | Qty/unit (B) | Total Qty (A*B) | Qty/unit (B) | Total Qty (A*B) | Qty/unit (B) | Total Qty (A*B) | Qty/unit (B) | Total Qty (A*B) | Qty/unit (B) | Total Qty (A*B) | Qty/unit (B) | Total Qty (A*B) | Qty/unit (B) | Total Qty (A*B) | Qty/unit (B) | Total Qty (A*B) | ||||
| 1 | Earth Work (AR0122Ai) :.Earth work in all kinds of soil within 50m, initial lead and 1.5m, initial lift - Earth work in all kinds of soil within 50m, initial lead and 1.5m, initial lift including rought dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per direction of the Engineer-in-charge. | 17.7687 | Cum | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
| 2 | Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. | 9.27465 | Cum | 1 | 9.27465 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
| 3 | Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. | 6.1831 | Cum | - | - | 2.29 | 14.159299 | 0.48 | 2.967888 | 0.96 | 5.935776 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
| 4 | Masonry Brick Work (AR0603b) :.Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in foundation and plinth - Brickwork with Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in foundation and plinth having crushing strength not less than 75.00 Kg/cm2 with dimensional tolerance ±8 percent immersing the bricks in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge. | 0.9775 | Cum | - | - | 0.672 | 0.65688 | 0.28 | 0.2737 | - | - | 350 | 342.125 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
| 5 | Masonry Brick Work (AR0603bi) :.Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in superstructure - Brickwork with Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in superstructure having crushing strength not less than 75.00 Kg/cm2 with dimensional tolerance ±8 percent immersing the bricks in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge. | 25.0496 | Cum | - | - | 0.672 | 16.8333312 | 0.28 | 7.013888 | - | - | 350 | 8767.36 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
| 6 | Masonry Brick Work (AR0602bi) :.Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:4) in superstructure - Brickwork with Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:4) in superstructure having crushing strength not less than 75.00 Kg/cm2 immerging the with dimensional tolerance ±8 percent immersing in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge. | 1.6246 | Cum | - | - | 1 | 1.6246 | 0.28 | 0.454888 | - | - | 350 | 568.61 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
| 7 | R.C.C. Work (AR0404Aa) :.Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge (RCC foundation, footing bases of column, mass concreate, pre-cast slabs etc.) | 2.7225 | Cum | - | - | 3.4733 | 9.45605925 | 0.45 | 1.225125 | - | - | - | - | 0.36 | 0.9801 | 0.54 | 1.47015 | 0.004005 | 0.0109036125 | 0.000921 | 0.0025074225 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
| 8 | R.C.C. Work (AR0404Ab) :.Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge (RCC Plinth band) | 1.63125 | Cum | - | - | 3.4733 | 5.665820625 | 0.45 | 0.7340625 | - | - | - | - | 0.36 | 0.58725 | 0.54 | 0.880875 | 0.01335 | 0.0217771875 | 0.00307 | 0.0050079375 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
| 9 | R.C.C. Work (AR0404Ad) :.Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge (RCC Lintels) | 1.766625 | Cum | - | - | 3.4733 | 6.1360186125 | 0.45 | 0.79498125 | - | - | - | - | 0.36 | 0.635985 | 0.54 | 0.9539775 | 0.0741335 | 0.1309660944375 | - | - | 0.049542 | 0.08752213575 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
| 10 | R.C.C. Work (AR0404Ac) :.Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge. (RCC Beams, Column, Girder & Bressmer etc) | 3.834875 | Cum | - | - | 3.4733 | 13.3196713375 | 0.45 | 1.72569375 | - | - | - | - | 0.36 | 1.380555 | 0.54 | 2.0708325 | 0.041529 | 0.159258523875 | - | - | - | - | 0.045339 | 0.173869397625 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
| 11 | R.C.C. Work (AR0404Af) :.Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge (RCC Sun sheds & Chajja) | 4.98 | Sqm | - | - | 0.21708125 | 1.081064625 | 0.028125 | 0.1400625 | - | - | - | - | 0.0225 | 0.11205 | 0.03375 | 0.168075 | 0.00552344 | 0.0275067312 | - | - | - | - | 0.0084318 | 0.041990364 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
| 12 | R.C.C. Work (AR0404Ag) :.Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge (RCC Roof slab, landing, balcony, sun shade) | 7.599384 | Cum | - | - | 3.4733 | 26.3949404472 | 0.45 | 3.4197228 | - | - | - | - | 0.36 | 2.73577824 | 0.54 | 4.10366736 | 0.0502172 | 0.3816197862048 | - | - | - | - | 0.076659 | 0.582561178056 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
| 13 | R.C.C. Work (AR0409) :.Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position - Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position including cost of binding wire 18 to 20 gauge with cost of steel rod and as per drawing, design, and direction of Engineer-in-charge. | 20.61 | Qntl | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | 1.05 | 21.6405 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
| 14 | Plastering (AR1004) :.12mm thick cement plster (1:6) over Brick work in inside - 12mm thick cement plster (1:6) over Brick work in inside including racking out joints finishing smooth with proper plumb and line curing for proper period with cost conveyance, royality, taxes of all materials, labour and T & P required for the work etc. comp.and as per direction of Engineer-in-charge. | 98.3632 | Sqm | - | - | 0.0358 | 3.52140256 | 0.015 | 1.475448 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
| 15 | Plastering (AR1014) :.16mm thick cement Plaster in CM (1:6) over brick work in inside. - 16mm thick cement Plaster in CM (1:6) over brick work in inside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc comp.and as per direction of Engineer-in-charge. | 150.6932 | Sqm | - | - | 0.043 | 6.4798076 | 0.018 | 2.7124776 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
| 16 | Painting(AR0901di) :.Priming one coat with outer surface primer of approved quality water-bound primer over plastering surfaces(outer surface ) - Priming one coat with outer surface primer of approved quality water-bound primer over plastering surfaces including cost conveyance, taxes of all materials, labor and T&P required for the work complete as per direction of the Engineer-in-charge. | 248.695 | Sqm | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | 0.090322580645161 | 22.462774193548 | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
| 17 | Painting(AR0918cb) :.Finishing wall two coats with weather coat with one coat waterbound Primer - Finishing wall two coats with weather coat with one coat waterbound Primer including all costs of labour, Paint, Primer, Brushes and putty required for the work etc. complete and as per direction of Engineer-in-charge.(Outside) | 295.78 | Sqm | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | 0.090322580645161 | 26.715612903226 | 0.125 | 36.9725 | - | - | - | - | - | - | - | - | - | - | - | - |
| 18 | Flooring (AR0816a) :.Fixing Marble Tiles in floor, treads or steps and landing of minimum 16 mm thick, dunguri Variety Up to 0.10 Sqm Above 0.10 Sqm. to 0.40 Sqm on a 25mm thick bed of cement mortar 1:1 - Fixing Marble Tiles in floor, treads or steps and landing of minimum 16 mm thick, dunguri Variety Up to 0.10 Sqm Above 0.10 Sqm. to 0.40 Sqm on a 25mm thick bed of cement mortar 1:1 (1cement: 1sand) jointed with neat cement slurry mixed with pigment to match the shades of the marble tiles including rubbing and polishing, cost of precast tiles complete as per direction of Enginer-in-charge. | 32.4304 | Sqm | - | - | 0.2737 | 8.87620048 | 0.013 | 0.4215952 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | 1 | 32.4304 | - | - | - | - | - | - | - | - | - | - |
| 19 | Flooring (AR0817af) :.Fixing Marble Tiles of minimum 16 mm thick, dunguri Variety Up to 0.10 Sqm in dados skirting and risers of steps on 12mm thick cement plaster (1:3) - Fixing Marble Tiles of minimum 16 mm thick, dunguri Variety Up to 0.10 Sqm in dados, skirting and risers of steps on 12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with pigments to match the shade of the Marble tiles including rubbing and polishing complete including cost of precast tiles. | 4.9785 | Sqm | - | - | 0.1375 | 0.68454375 | 0.015 | 0.0746775 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | 1 | 4.9785 | - | - | - | - | - | - | - | - |
| 20 | Flooring (AR0817b) :.Fixing ceramic tiles (20cmx30cm / 20cmx20cm special plain/printed series ceramic wall tiles of premium grade having thickness 6.5mm to 6.7mm confirming to IS 13753) - Fixing ceramic tiles (20cmx30cm / 20cmx20cm special plain/printed series ceramic wall tiles of premium grade having thickness 6.5mm to 6.7mm confirming to IS 13753) in wall cladding on 12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with pigments to match the shade of the ceramic tiles including rubbing and polishing, cost of precast tiles complete as per direction of Engineer-in-charge. | 46.7376 | Sqm | - | - | 0.1375 | 6.42642 | 0.015 | 0.701064 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | 1 | 46.7376 | - | - | - | - | - | - |
| 21 | Flooring (AR0817aq) :.Fixing ceramic Tiles (30cmx30cm / 40cmx40cm special plain/printed series ceramic floor tiles of premium grade having thickness 7mm to 8mm confirming to IS 13755) in dados skirting and risers of steps on 12mm thick cement plaster (1:3) - Fixing ceramic Tiles (30cmx30cm / 40cmx40cm special plain/printed series ceramic floor tiles of premium grade having thickness 7mm to 8mm confirming to IS 13755) in dados skirting and risers of steps on 12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with pigments to match the shade of the ceramic tiles including rubbing and polishing, cost of precast tiles complete as per direction of Engineer-in-charge(For repair and maintenance) . | 11.1216 | Sqm | - | - | 0.1375 | 1.52922 | 0.015 | 0.166824 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | 1 | 11.1216 | - | - | - | - |
| 22 | Painting(AR0903b) :.Painting two coats of enamel paint with a coat of red oxide primer over iron surface - Painting two coats of enamel paint with a coat of red oxide primer over iron surface including all costs of labour, Paint, Primer, brushes and putty required for the work etc. complete and as per direction of Engineer-in-charge. | 17.65245 | Sqm | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | 0.054 | 0.9532323 | 0.125 | 2.20655625 |
| Total Qty | 9.27465 | 122.8452794872 | 24.3020981 | 5.935776 | 9678.095 | 6.43171824 | 9.64757736 | 0.7320319357173 | 0.00751536 | 0.08752213575 | 0.798420939681 | 21.6405 | 49.178387096774 | 36.9725 | 32.4304 | 4.9785 | 46.7376 | 11.1216 | 0.9532323 | 2.20655625 | |||||||||||||||||||||||
| Rate Per Unit | 274.25 | 0 | 274.25 | 444.5 | 0 | 444.5 | 444.5 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 29.44 | 29.44 | 0 | 16.45 | 0 | 0 | |||||||||||||||||||||||
| Total Amount | 2543.5727625 | 0 | 6664.850403925 | 2638.452432 | 0 | 2858.89875768 | 4288.34813652 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 954.750976 | 146.56704 | 0 | 182.95032 | 0 | 0 | |||||||||||||||||||||||
| S/N | Item Name | Amount (in Rs.) |
|---|---|---|
| 1 | Provision for PH Work @ Rs. 50000 | Rs. 50000 |
| 2 | Provision for Contingency @ 1% | Rs. 8125.5007837215 |
| 3 | Display Citizen Board @ Rs. 500 | Rs. 500 |
| 4 | Any Other Lumpsum @ Rs. 78824.4 | Rs. 78824.4 |
| Sl.No. | Item Name | Amount (in Rs.) | |||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| No data to display. | |||||||||||||||||||