State: Odisha District: Ganjam Block: Bellaguntha Gram Panchayat: Benipalli
Work Code: OD/354/3366/117619/410678/00064174 (CONSTRUCTION OF PAVER C.C.ROAD FROM CHANDRASEKHAR TO UP SCHOOL)
Project Category: Road
Financial Year: 2022-23 Execution Level: ps
Executing Agency: Panchayat Samiti, Bellaguntha Proposal Date: -
Date of Commencement: 17-11-2025 Date of Completion: 09-01-2026
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: All Weather Connectivity
Project Sub-Category: Pavor Block Project Type: New Work
Name of Executant: Phulamani Majhi
Administrative Approval Details
Approval No.: OD/354/3366/117619/410678/00064174/AS
Technical Sanction Details
Technical Sanction No.: OD/354/3366/117619/410678/00064174/TS
Fund Sanction No.: 9122
Fund Sanction Amount (in Rs.): 250000
ACTIVITY STATEMENT
Sl.No. Activity taken Unit Quantity Unit Price (in Rs.) Total (in Rs.)
1 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. Cum 27.510337536 683.086432 18791.938310582
2 Concrete (AR0307a) : Cement concrete (1:2:4)with 12mm size hard granite(Hand broken)chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(hand broken) chips including hoisting and laying in position compacting to proper thickness and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. Cum 3.6245504 6648.01258882 24096.056688013
3 miscellaneous (ARM287) : Supplying and fixing of 80mm thick cement concrete interlocking paver block of M-40 grade of approved make, design, colour and size made by Block making machine with proper compaction laid in required pattern etc. complete in all respect conforming to IRC - Supplying and fixing of 80mm thick cement concrete interlocking paver block of M-40 grade of approved make, design, colour and size made by Block making machine with proper compaction laid in required pattern etc. complete in all respect conforming to IRC SP-63:2018. (New miscellaneous items) and as directed by Engineer-in-Charge. Sqm 273.506432 626.9766 171482.13281349
Total Amount (in Rs.): 214370.12781209
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled
462 562
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 27.510337536 Cubic Meter 0.1236 3.4002777194496 - -
2 Concrete (AR0307a) : Cement concrete (1:2:4)with 12mm size hard granite(Hand broken)chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(hand broken) chips including hoisting and laying in position compacting to proper thickness and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 3.6245504 Cubic Meter 4.6 16.67293184 0.68 2.464694272
Total Qty 20.07320955945 2.464694272
Rate Per Man Day 462 562
Total Amount 9273.8228164657 1385.158180864
Total Labour Amount (in Rs.): 10658.98099733
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM057 BRM340 BRM028 BRMM287
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 27.510337536 Cum 1 27.510337536 - - - - - - - -
2 Concrete (AR0307a) :.Cement concrete (1:2:4)with 12mm size hard granite(Hand broken)chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(hand broken) chips including hoisting and laying in position compacting to proper thickness and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 3.6245504 Cum - - 0.9 3.26209536 3.23 11.707297792 0.45 1.63104768 - -
3 miscellaneous(ARM287) :.Supplying and fixing of 80mm thick cement concrete interlocking paver block of M-40 grade of approved make, design, colour and size made by Block making machine with proper compaction laid in required pattern etc. complete in all respect conforming to IRC - Supplying and fixing of 80mm thick cement concrete interlocking paver block of M-40 grade of approved make, design, colour and size made by Block making machine with proper compaction laid in required pattern etc. complete in all respect conforming to IRC SP-63:2018. (New miscellaneous items) and as directed by Engineer-in-Charge. 273.506432 Sqm 0.03 8.20519296 - - - - - - 1 273.506432
Total Qty 35.715530496 3.26209536 11.707297792 1.63104768 273.506432
Rate Per Unit 403.97 1411.11 598.962 407.34 608.4
Total Amount 14428.002854469 4603.1753834496 7012.2265000919 664.3909619712 166401.3132288
Total Material Amount (in Rs.): 193109.10892878
ROYALTY STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM057 BRM340 BRM028
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 27.510337536 Cum 1 27.510337536 - - - - - -
2 Concrete (AR0307a) :.Cement concrete (1:2:4)with 12mm size hard granite(Hand broken)chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(hand broken) chips including hoisting and laying in position compacting to proper thickness and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 3.6245504 Cum - - 0.9 3.26209536 3.23 11.707297792 0.45 1.63104768
3 miscellaneous(ARM287) :.Supplying and fixing of 80mm thick cement concrete interlocking paver block of M-40 grade of approved make, design, colour and size made by Block making machine with proper compaction laid in required pattern etc. complete in all respect conforming to IRC - Supplying and fixing of 80mm thick cement concrete interlocking paver block of M-40 grade of approved make, design, colour and size made by Block making machine with proper compaction laid in required pattern etc. complete in all respect conforming to IRC SP-63:2018. (New miscellaneous items) and as directed by Engineer-in-Charge. 273.506432 Sqm 0.03 8.20519296 - - - - - -
Total Qty 35.715530496 3.26209536 11.707297792 1.63104768
Rate Per Unit 215.25 288.5 0 215.25
Total Amount 7687.767939264 941.11451136 0 351.08301312
Total Royalty Amount (in Rs.): 8979.965463744
ADDITION COMPONENT
S/N Item Name Amount (in Rs.)
1 Provision for Contingency @ Rs. 2500 Rs. 2500
2 Display Citizen Board @ Rs. 3177 Rs. 3177
3 Any Other Lumpsum @ Rs. 29952 Rs. 29952
Total Addition Component Amount (in Rs.): 35629
DEDUCTION COMPONENT
Sl.No. Item Name Amount (in Rs.)
No data to display.
Total Deduction Component Amount (in Rs.): 0
Total Net Amount (in Rs.): 249999.12781209