State: Odisha District: Mayurbhanj Block: Kusumi Gram Panchayat: Talapati
Work Code: OD/365/3501/120270/388304/00072180 (Const. of CC road from Dova Giri Sahi to Tentoposi)
Project Category: Road
Financial Year: 2023-24 Execution Level: ps
Executing Agency: Panchayat Samiti, Kusumi Proposal Date: -
Date of Commencement: - Date of Completion: -
Scheme Name: SFC Devolution of Fund Scheme Component Name: 5TH SFC DEVOLUTION GRANT TO ZILLA PARISHAD
Project Sub-Category: CC Road Project Type: New Work
Name of Executant:
Administrative Approval Details
Approval No.:
Technical Sanction Details
Technical Sanction No.:
Fund Sanction No.:
Fund Sanction Amount (in Rs.): 180000
ACTIVITY STATEMENT
Sl.No. Activity taken Unit Quantity Unit Price (in Rs.) Total (in Rs.)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge Cum 3.19546026624 240.77592 769.38988542738
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. Cum 11.54023150368 956.665132 11040.137094779
3 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. Cum 13.96103473568 6114.2111743 85360.714585685
4 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. Cum 8.7498912 7665.4648011 67071.983007055
5 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc Sqm 38.08465582 216.23489289764 8235.2314722812
Total Amount (in Rs.): 172477.45604523
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled
462 562 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 3.19546026624 Cubic Meter 0.516 1.6488574973798 - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 11.54023150368 Cubic Meter 0.1236 1.4263726138548 - - - -
3 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 13.96103473568 Cubic Meter 3.9 54.448035469152 - - 0.18 2.5129862524224
4 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 8.7498912 Cubic Meter 4.6 40.24949952 - - 0.68 5.949926016
5 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 38.08465582 Square Meter - - 0.05 1.904232791 0.05 1.904232791
Total Qty 97.772765100387 10.367145059422 1.904232791
Rate Per Man Day 462 562 512
Total Amount 45171.017476379 5826.3355233954 974.967188992
Total Labour Amount (in Rs.): 51972.320188766
MATERIAL STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM340 BRM028 BRM044 BRM056 BRM104 BRM092
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) :.Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 3.19546026624 Cum - - - - - - - - - - - - - -
2 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 11.54023150368 Cum 1 11.54023150368 - - - - - - - - - - - -
3 Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 13.96103473568 Cum - - 2.29 31.970769544707 0.48 6.7012966731264 0.96 13.402593346253 - - - - - -
4 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 8.7498912 Cum - - 3.23 28.262148576 0.45 3.93745104 - - 0.9 7.87490208 - - - -
5 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 38.08465582 Sqm - - - - - - - - - - 0.00267 0.1016860310394 0.126 4.79866663332
Total Qty 11.54023150368 60.232918120707 10.638747713126 13.402593346253 7.87490208 0.1016860310394 4.79866663332
Rate Per Unit 596.84 656.567 603.26 1531.66 1933.03 58573.086 229.106
Total Amount 6887.6717706564 39546.946351758 6417.9309454206 20528.216124722 15222.421967702 5956.0646410694 1099.4033176934
Total Material Amount (in Rs.): 95658.655119022
ROYALTY STATEMENT
Sl.No. Activity Name Quantity (A) Unit BRM029 BRM340 BRM028 BRM044 BRM056 BRM104 BRM092
Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B) Qty/unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) :.Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 3.19546026624 Cum - - - - - - - - - - - - - -
2 Earth Work (AR0115) :.Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 11.54023150368 Cum 1 11.54023150368 - - - - - - - - - - - -
3 Concrete (AR0303) :.Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 13.96103473568 Cum - - 2.29 31.970769544707 0.48 6.7012966731264 0.96 13.402593346253 - - - - - -
4 Concrete (AR0307) :.Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 8.7498912 Cum - - 3.23 28.262148576 0.45 3.93745104 - - 0.9 7.87490208 - - - -
5 R.C.C. Work (AR0410c) :.R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 38.08465582 Sqm - - - - - - - - - - 0.00267 0.1016860310394 0.000614 0.02338397867348
Total Qty 11.54023150368 60.232918120707 10.638747713126 13.402593346253 7.87490208 0.1016860310394 0.02338397867348
Rate Per Unit 293.25 0 293.25 516.5 516.5 0 0
Total Amount 3384.1728884542 0 3119.8127668743 6922.4394633396 4067.38692432 0 0
Total Royalty Amount (in Rs.): 17493.812042988
ADDITION COMPONENT
S/N Item Name Amount (in Rs.)
1 Provision for Contingency @ Rs. 1800 Rs. 1800
2 Display Citizen Board @ Rs. 5000 Rs. 5000
3 Any Other Lumpsum @ Rs. 722.54 Rs. 722.54
Total Addition Component Amount (in Rs.): 7522.54
DEDUCTION COMPONENT
Sl.No. Item Name Amount (in Rs.)
No data to display.
Total Deduction Component Amount (in Rs.): 0
Total Net Amount (in Rs.): 179999.99604523