State: Odisha District: Mayurbhanj Block: Jamda Gram Panchayat: Jamda
Work Code: OD/365/3495/120165/387615/00013013 (Repair And Renovation Of Kalyan Mandap At Jamda With Provision Of Drinking Water And Electrification Works)
Project Category: Building
Financial Year: 2023-24 Execution Level: ps
Executing Agency: Panchayat Samiti, Jamda Proposal Date: -
Date of Commencement: 18-09-2025 Date of Completion: -
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: Maintenance of Capital Assets
Project Sub-Category: Kalyan Mandap Project Type: Repair and Maintenance
Name of Executant:
Administrative Approval Details
Approval No.: OD/365/3495/120165/387615/00013013/AS
Technical Sanction Details
Technical Sanction No.: OD/365/3495/120165/387615/00013013/TS
Fund Sanction No.: 12762
Fund Sanction Amount (in Rs.): 1000000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled Highly-Skilled
462 562 512 612
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 27.9275006336 Cubic Meter 0.516 14.410590326938 - - - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 22.2605727168 Cubic Meter 0.1236 2.7514067877965 - - - - - -
3 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 27.61454336 Cubic Meter 3.9 107.696719104 - - 0.18 4.9706178048 - -
4 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 20.8474332 Square Meter - - 0.05 1.04237166 0.05 1.04237166 - -
5 Painting (AR0901a) : Priming one coat in inner surface with primer of approved quality over woodwork - Priming one coat in inner surface with primer of approved quality over woodwork including cost conveyance, taxes of all materials, labor and T&P required for the work complete as per direction of the Engineer-in-charge. 178.37376 Square Meter 0.053763440860215 9.5899870967742 - - - - 0.053763440860215 9.5899870967742
6 Painting (AR0919) : Finishing wall One Coat with plastic emulsion paint of approved shades on old work (Inside) - Finishing wall One Coat with plastic emulsion paint of approved shades on old work to give an even shade including all costs of labor, Paint and Brushes required for the work, etc. complete and as per direction of the Engineer-in-charge.(Inside) 178.37376 Square Meter 0.043 7.67007168 - - - - 0.036 6.42145536
7 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 13.839836 Cubic Meter 4.6 63.6632456 - - 0.68 9.41108848 - -
8 Masonry Brick Work (AR0603b) : Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in foundation and plinth - Brickwork with Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in foundation and plinth having crushing strength not less than 75.00 Kg/cm2 with dimensional tolerance ±8 percent immersing the bricks in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge. 14.1584 Cubic Meter 2.96 41.908864 - - 1.05 14.86632 0.35 4.95544
9 Masonry Brick Work (AR0603bi) : Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in superstructure - Brickwork with Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in superstructure having crushing strength not less than 75.00 Kg/cm2 with dimensional tolerance ±8 percent immersing the bricks in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge. 24.6639328 Cubic Meter 2.96 73.005241088 - - 1.05 25.89712944 0.35 8.63237648
10 Painting (AR0918cb) : Finishing wall two coats with weather coat with one coat waterbound Primer - Finishing wall two coats with weather coat with one coat waterbound Primer including all costs of labour, Paint, Primer, Brushes and putty required for the work etc. complete and as per direction of Engineer-in-charge.(Outside) 427.725412 Square Meter 0.11776344086022 50.370416260473 - - - - 0.10776344086022 46.093162140473
11 Plastering (AR1014) : 16mm thick cement Plaster in CM (1:6) over brick work in inside. - 16mm thick cement Plaster in CM (1:6) over brick work in inside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc comp.and as per direction of Engineer-in-charge. 204.3866 Square Meter 0.24 49.052784 - - 0.16 32.701856 - -
Total Qty 420.11932594398 88.8893833848 1.04237166 75.692421077247
Rate Per Man Day 462 562 512 612
Total Amount 194095.12858612 49955.833462258 533.69428992 46323.761699275
Total Labour Amount (in Rs.): 290908.41803757