State: Odisha District: Khordha Block: Bhubaneswar Gram Panchayat: Daruthenga
Work Code: OD/362/3460/119603/407462/00013189 (Preservation & Development of Siva Mandir Pokhari, Daruthenga)
Project Category: Water Body
Financial Year: 2022-23 Execution Level: ps
Executing Agency: Panchayat Samiti, Bhubaneswar Proposal Date: -
Date of Commencement: 20-05-2025 Date of Completion: 23-05-2025
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: Preservation and Development of Water Bodies
Project Sub-Category: Embankment Project Type: Renovation or Rejuvenation
Name of Executant: Suchismita Mohanty
Administrative Approval Details
Approval No.: OD/362/3460/119603/407462/00013189/AS
Technical Sanction Details
Technical Sanction No.: OD/362/3460/119603/407462/00013189/TS
Fund Sanction No.:
Fund Sanction Amount (in Rs.): 663375
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Semi-Skilled Skilled Highly-Skilled
452 502 552 602
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 26.319 Cubic Meter 0.1236 3.2530284 - - - - - -
2 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 115.19972 Square Meter - - 0.05 5.759986 0.05 5.759986 - -
3 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 17.37054 Cubic Meter 3.9 67.745106 - - 0.18 3.1266972 - -
4 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 157.914 Cubic Meter 0.516 81.483624 - - - - - -
5 R.C.C. Work (AR0404Aa) : Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge (RCC foundation, footing bases of column, mass concreate, pre-cast slabs etc.) 49.65518 Cubic Meter 1.3333 66.205251494 0.1323 6.569380314 0.175 8.6896565 - -
6 R.C.C. Work (AR0409) : Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position - Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position including cost of binding wire 18 to 20 gauge with cost of steel rod and as per drawing, design, and direction of Engineer-in-charge. 16.92 Quintal 0.8 13.536 0.044 0.74448 - - 0.3 5.076
Total Qty 232.223009894 13.073846314 17.5763397 5.076
Rate Per Man Day 452 502 552 602
Total Amount 104964.80047209 6563.070849628 9702.1395144 3055.752
Total Labour Amount (in Rs.): 124285.76283612