State: Odisha District: Nabarangpur Block: Nabarangpur Gram Panchayat: Basini
Work Code: OD/366/3517/120490/427816/00013547 (Const.of CC Road at Hirliaguda)
Project Category: Road
Financial Year: 2023-24 Execution Level: ps
Executing Agency: Panchayat Samiti, Nabarangpur Proposal Date: 25-06-2023
Date of Commencement: 03-12-2024 Date of Completion: -
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: All Weather Connectivity
Project Sub-Category: CC Road Project Type: New Work
Name of Executant: SK MURSHID
Administrative Approval Details
Approval No.: OD/366/3517/120490/427816/00013547/AS
Technical Sanction Details
Technical Sanction No.: OD/366/3517/120490/427816/00013547/TS
Fund Sanction No.: 13737
Fund Sanction Amount (in Rs.): 143788
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled
452 552 502
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 18.629999160767 Cubic Meter 0.516 9.6130795669556 - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 12.420000076294 Cubic Meter 0.1236 1.5351120094299 - - - -
3 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 12.420000076294 Cubic Meter 3.9 48.438000297546 - - 0.18 2.2356000137329
4 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 10.35000038147 Square Meter - - 0.05 0.51750001907349 0.05 0.51750001907349
5 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 8.6940002441406 Cubic Meter 4.6 39.992401123047 - - 0.68 5.9119201660156
Total Qty 99.578592996979 8.665020198822 0.51750001907349
Rate Per Man Day 452 552 502
Total Amount 45009.524034634 4783.0911497498 259.78500957489
Total Labour Amount (in Rs.): 50052.400193959