State: Odisha District: Bargarh Block: Bargarh Gram Panchayat: Gudesira
Work Code: OD/347/3312/116380/380624/00014298 (Imp of CC road at Harijanpada, Nua Gudesira)
Project Category: Road
Financial Year: 2024-25 Execution Level: ps
Executing Agency: Panchayat Samiti, Bargarh Proposal Date: -
Date of Commencement: 04-04-2025 Date of Completion: 07-06-2025
Scheme Name: SFC Devolution of Fund Scheme Component Name: 5TH SFC DEVOLUTION GRANT TO PANCHAYAT SAMITI
Project Sub-Category: CC Road Project Type: Upgradation or Improvement
Name of Executant: SUSHMITA TIRKEY
Administrative Approval Details
Approval No.: OD/347/3312/116380/380624/00014298/AS
Technical Sanction Details
Technical Sanction No.: OD/347/3312/116380/380624/00014298/TS
Fund Sanction No.: 15384
Fund Sanction Amount (in Rs.): 300000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled
452 552 502
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0122Bi) : Earthwork in ordinary soil within 5 Km. mechanical carriages and spreading in filling area/road berm within initial lead and lift - Earthwork in ordinary soil within 5 Km. mechanical carriages and spreading in filling area/road berm within initial lead and lift including dressing and leveling the bed, etc. as per direction of Engineer-in-Charge. 6.4538 Cubic Meter 0.32 2.065216 - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 21.96 Cubic Meter 0.1236 2.714256 - - - -
3 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 22.8018 Cubic Meter 3.9 88.92702 - - 0.18 4.104324
4 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 21.96 Cubic Meter 4.6 101.016 - - 0.68 14.9328
5 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 56.12 Square Meter - - 0.05 2.806 0.05 2.806
6 Earth Work (AR0122Bi) : Earthwork in ordinary soil within 5 Km. mechanical carriages and spreading in filling area/road berm within initial lead and lift - Earthwork in ordinary soil within 5 Km. mechanical carriages and spreading in filling area/road berm within initial lead and lift including dressing and leveling the bed, etc. as per direction of Engineer-in-Charge. 0 Cubic Meter 0.32 0 - - - -
Total Qty 194.722492 21.843124 2.806
Rate Per Man Day 452 552 502
Total Amount 88014.566384 12057.404448 1408.612
Total Labour Amount (in Rs.): 101480.582832