State: Odisha District: Cuttack Block: Baranga Gram Panchayat: Dadhapatna
Work Code: OD/350/3336/116936/907103/00016935 (Maint. & Imp. of Road with CC/ Gr-II Metalling from Station Bazar Level Crossing to Kanak Durga Temple)
Project Category: Road
Financial Year: 2024-25 Execution Level: ps
Executing Agency: Panchayat Samiti, Baranga Proposal Date: -
Date of Commencement: 05-06-2025 Date of Completion: -
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: Maintenance and improvement of Road infrastructure
Project Sub-Category: Mettalling Road Project Type: Repair and Maintenance
Name of Executant: Santosh Kumar Patra
Administrative Approval Details
Approval No.: OD/350/3336/116936/907103/00016935/AS
Technical Sanction Details
Technical Sanction No.: OD/350/3336/116936/907103/00016935/TS
Fund Sanction No.:
Fund Sanction Amount (in Rs.): 186532
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled
462 562 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 23.099712768 Cubic Meter 4.6 106.2586787328 - - 0.68 15.70780468224
2 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 12.63109188 Square Meter - - 0.05 0.631554594 0.05 0.631554594
3 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 1.3592064 Cubic Meter 3.9 5.30090496 - - 0.18 0.244657152
Total Qty 111.5595836928 16.58401642824 0.631554594
Rate Per Man Day 462 562 512
Total Amount 51540.527666074 9320.2172326709 323.355952128
Total Labour Amount (in Rs.): 61184.100850872