State: Odisha District: Cuttack Block: Niali Gram Panchayat: Niali
Work Code: OD/350/3341/117065/400347/00017316 (Improvement of road from PwD main road to Kuanri Sahi)
Project Category: Road
Financial Year: 2024-25 Execution Level: ps
Executing Agency: Panchayat Samiti, Niali Proposal Date: -
Date of Commencement: 08-05-2025 Date of Completion: 30-07-2025
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: All Weather Connectivity
Project Sub-Category: CC Road Project Type: Upgradation or Improvement
Name of Executant: PRITI CHANDRIKA SAMAL
Administrative Approval Details
Approval No.: OD/350/3341/117065/400347/00017316/AS
Technical Sanction Details
Technical Sanction No.: OD/350/3341/117065/400347/00017316/TS
Fund Sanction No.:
Fund Sanction Amount (in Rs.): 450000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Skilled Un-Skilled Semi-Skilled
562 462 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 0.243 Cubic Meter 3.9 0.9477 - - 0.18 0.04374
2 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 55.115 Cubic Meter 4.6 253.529 - - 0.68 37.4782
3 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 45.3 Square Meter - - 0.05 2.265 0.05 2.265
Total Qty 39.78694 254.4767 2.265
Rate Per Man Day 562 462 512
Total Amount 22360.26028 117568.2354 1159.68
Total Labour Amount (in Rs.): 141088.17568