State: Odisha District: Ganjam Block: Purushottampur Gram Panchayat: Jamuni
Work Code: OD/354/3381/117937/412229/00017471 (CONST OF CC PAVER ROAD FROM JAGANATH MANDIR TO KUMBARA SAHI ROAD VIA KUMBARA SAHI CHAKA OF JAMUNI )
Project Category: Road
Financial Year: 2024-25 Execution Level: ps
Executing Agency: Panchayat Samiti, Purushottampur Proposal Date: 10-12-2024
Date of Commencement: 19-05-2025 Date of Completion: -
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: All Weather Connectivity
Project Sub-Category: Pavor Block Project Type: New Work
Name of Executant: Parameswari Patra
Administrative Approval Details
Approval No.: OD/354/3381/117937/412229/00017471/AS
Technical Sanction Details
Technical Sanction No.: OD/354/3381/117937/412229/00017471/TS
Fund Sanction No.: 29143
Fund Sanction Amount (in Rs.): 900000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled
462 562 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0102a) : Earth work in hard soil or gravelly soil within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 45.114 Cubic Meter 0.43 19.39902 - - - -
3 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 14.214 Cubic Meter 4.6 65.3844 - - 0.68 9.66552
4 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 28.428 Square Meter - - 0.05 1.4214 0.05 1.4214
5 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 120.098 Cubic Meter 0.1236 14.8441128 - - - -
Total Qty 99.6275328 11.08692 1.4214
Rate Per Man Day 462 562 512
Total Amount 46027.9201536 6230.84904 727.7568
Total Labour Amount (in Rs.): 52986.5259936