State: Odisha District: Ganjam Block: Hinjilicut Gram Panchayat: Darubhadra
Work Code: OD/354/3374/117762/412322/00017495 (IMPROVEMENT OF UP SCHOOL AT DARUBHADRA )
Project Category: Building
Financial Year: 2022-23 Execution Level: ps
Executing Agency: Panchayat Samiti, Hinjilicut Proposal Date: 15-09-2021
Date of Commencement: 28-11-2025 Date of Completion: 17-12-2025
Scheme Name: SFC Devolution of Fund Scheme Component Name: 5TH SFC DEVOLUTION GRANT TO PANCHAYAT SAMITI
Project Sub-Category: Elementary School Project Type: New Work
Name of Executant: KALPANA PADHI
Administrative Approval Details
Approval No.: OD/354/3374/117762/412322/00017495/AS
Technical Sanction Details
Technical Sanction No.: OD/354/3374/117762/412322/00017495/TS
Fund Sanction No.: 3488
Fund Sanction Amount (in Rs.): 100000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled
462 562 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 2.915497728 Cubic Meter 0.516 1.504396827648 - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 13.119739776 Cubic Meter 0.1236 1.6215998363136 - - - -
3 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 1.457748864 Cubic Meter 3.9 5.6852205696 - - 0.18 0.26239479552
5 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 0.448538112 Cubic Meter 4.6 2.0632753152 - - 0.68 0.30500591616
6 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 6.37686192 Square Meter - - 0.05 0.318843096 0.05 0.318843096
Total Qty 10.874492548762 0.88624380768 0.318843096
Rate Per Man Day 462 562 512
Total Amount 5024.0155575279 498.06901991616 163.247665152
Total Labour Amount (in Rs.): 5685.332242596