State: Odisha District: Angul Block: Banarpal Gram Panchayat: Badahinsara
Work Code: OD/344/3278/275373/404334/00017821 (Improvement of Road with CC/Gr-II Metalling from Badahinsar AWC-B to Sudhanya Sahu House)
Project Category: Road
Financial Year: 2024-25 Execution Level: ps
Executing Agency: Panchayat Samiti, Banarpal Proposal Date: -
Date of Commencement: 25-07-2025 Date of Completion: 31-10-2025
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: Maintenance and improvement of Road infrastructure
Project Sub-Category: CC Road Project Type: Upgradation or Improvement
Name of Executant: Samara Ballava Biswal
Administrative Approval Details
Approval No.: OD/344/3278/275373/404334/00017821/AS
Technical Sanction Details
Technical Sanction No.: OD/344/3278/275373/404334/00017821/TS
Fund Sanction No.: 31142
Fund Sanction Amount (in Rs.): 186532
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled
462 562 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 2.1662352 Cubic Meter 0.516 1.1177773632 - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 10.0989885024 Cubic Meter 0.1236 1.2482349788966 - - - -
3 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 13.7079363456 Cubic Meter 3.9 53.46095174784 - - 0.18 2.467428542208
4 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 11.5417011456 Cubic Meter 4.6 53.09182526976 - - 0.68 7.848356779008
5 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 12.622173192 Square Meter - - 0.05 0.6311086596 0.05 0.6311086596
Total Qty 108.9187893597 10.946893980816 0.6311086596
Rate Per Man Day 462 562 512
Total Amount 50320.48068418 6152.1544172186 323.1276337152
Total Labour Amount (in Rs.): 56795.762735114