State: Odisha District: Kalahandi Block: Kalampur Gram Panchayat: Bijamara
Work Code: OD/358/3414/118722/424156/00022750 (Const. of CC Road at Bijmara Pandikipada)
Project Category: Road
Financial Year: 2024-25 Execution Level: ps
Executing Agency: Panchayat Samiti, Kalampur Proposal Date: 31-12-2024
Date of Commencement: 04-02-2026 Date of Completion: -
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: Maintenance and improvement of Road infrastructure
Project Sub-Category: CC Road Project Type: New Work
Name of Executant: SUMANTA DANDAPATH
Administrative Approval Details
Approval No.: OD/358/3414/118722/424156/00022750/AS
Technical Sanction Details
Technical Sanction No.: OD/358/3414/118722/424156/00022750/TS
Fund Sanction No.: 31141
Fund Sanction Amount (in Rs.): 250000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled
462 562 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0102a) : Earth work in hard soil or gravelly soil within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 31.242 Cubic Meter 0.43 13.43406 - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 17.399 Cubic Meter 0.1236 2.1505164 - - - -
3 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 20.574 Cubic Meter 3.9 80.2386 - - 0.18 3.70332
4 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 13.9065 Cubic Meter 4.6 63.9699 - - 0.68 9.45642
5 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 27.94 Square Meter - - 0.05 1.397 0.05 1.397
Total Qty 159.7930764 14.55674 1.397
Rate Per Man Day 462 562 512
Total Amount 73824.4012968 8180.88788 715.264
Total Labour Amount (in Rs.): 82720.5531768