State: Odisha District: Kendrapara Block: Garadapur Gram Panchayat: Garadapur
Work Code: OD/360/3436/119081/396806/00029103 (Repair& maintenance of C C road from Budhi jagulai to Veterinary Hospital, Garadpur)
Project Category: Road
Financial Year: 2024-25 Execution Level: ps
Executing Agency: Panchayat Samiti, Garadapur Proposal Date: -
Date of Commencement: 10-11-2025 Date of Completion: 25-11-2025
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: MAINTENANCE OF ROADS AND BRIDGES
Project Sub-Category: CC Road Project Type: Repair and Maintenance
Name of Executant: Priyabrata Das JE
Administrative Approval Details
Approval No.: OD/360/3436/119081/396806/00029103/AS
Technical Sanction Details
Technical Sanction No.: OD/360/3436/119081/396806/00029103/TS
Fund Sanction No.: 29781
Fund Sanction Amount (in Rs.): 200000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled
462 562 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 4.5125 Cubic Meter 0.516 2.32845 - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 13.1765 Cubic Meter 0.1236 1.6286154 - - - -
3 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 17.689 Cubic Meter 3.9 68.9871 - - 0.18 3.18402
4 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 19.855 Square Meter - - 0.05 0.99275 0.05 0.99275
5 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 9.882375 Cubic Meter 4.6 45.458925 - - 0.68 6.720015
Total Qty 118.4030904 10.896785 0.99275
Rate Per Man Day 462 562 512
Total Amount 54702.2277648 6123.99317 508.288
Total Labour Amount (in Rs.): 61334.5089348