State: Odisha District: Ganjam Block: Purushottampur Gram Panchayat: Ranajhali
Work Code: OD/354/3381/117943/412221/00031113 (Improvement Of Road At Das Sahi Tungudas Houseto Das Sahi Well)
Project Category: Road
Financial Year: 2023-24 Execution Level: ps
Executing Agency: Panchayat Samiti, Purushottampur Proposal Date: 01-07-2023
Date of Commencement: 08-09-2025 Date of Completion: 18-09-2025
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: All Weather Connectivity
Project Sub-Category: CC Road Project Type: New Work
Name of Executant: Janaki Patro
Administrative Approval Details
Approval No.: OD/354/3381/117943/412221/00031113/AS
Technical Sanction Details
Technical Sanction No.: OD/354/3381/117943/412221/00031113/TS
Fund Sanction No.: 13737
Fund Sanction Amount (in Rs.): 228000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled
462 562 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 5.893434 Cubic Meter 0.516 3.041011944 - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 2.59311096 Cubic Meter 0.1236 0.320508514656 - - - -
3 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 3.22174392 Cubic Meter 3.9 12.564801288 - - 0.18 0.5799139056
4 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 25.7805825 Square Meter - - 0.05 1.289029125 0.05 1.289029125
5 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 3.928956 Cubic Meter 4.6 18.0731976 - - 0.68 2.67169008
7 Earth Work (AR0115a) : Filling foundation and plinth with crusher dust well watered and rammed - Filling foundation and plinth with crusher dust well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 28.812344 Cubic Meter 0.1236 3.5612057184 - - - -
Total Qty 37.560725065056 4.5406331106 1.289029125
Rate Per Man Day 462 562 512
Total Amount 17353.054980056 2551.8358081572 659.982912
Total Labour Amount (in Rs.): 20564.873700213