State: Odisha District: Malkangiri Block: Khairaput Gram Panchayat: Govindapalli
Work Code: OD/364/3481/119952/430374/00038295 (Provision of Facility Centre at Govindapally)
Project Category: Building
Financial Year: 2024-25 Execution Level: ps
Executing Agency: Panchayat Samiti, Khairaput Proposal Date: -
Date of Commencement: 01-08-2025 Date of Completion: 22-09-2025
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: Provision of Facilities at GP Head Quarter
Project Sub-Category: GP Facility Centre Project Type: New Work
Name of Executant: SAMIR DAS
Administrative Approval Details
Approval No.: OD/364/3481/119952/430374/00038295/AS
Technical Sanction Details
Technical Sanction No.: OD/364/3481/119952/430374/00038295/TS
Fund Sanction No.: 28001
Fund Sanction Amount (in Rs.): 1000000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled Highly-Skilled
462 562 512 612
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 32.022 Cubic Meter 0.516 16.523352 - - - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 28.37488 Cubic Meter 0.1236 3.507135168 - - - - - -
3 Concrete (AR0304a) : Cement concrete (1:4:8) with 4 cm. hard granite(Hand Broken) metal - Cement concrete (1:4:8) with 4 cm. hard granite(Hand Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 27.08231 Cubic Meter 3.9 105.621009 - - 0.18 4.8748158 - -
4 R.C.C. Work (AR0404Aa) : Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge (RCC foundation, footing bases of column, mass concreate, pre-cast slabs etc.) 6.92436 Cubic Meter 1.3333 9.232249188 0.1323 0.916092828 0.175 1.211763 - -
5 R.C.C. Work (AR0404Ab) : Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge (RCC Plinth band) 2.327071 Cubic Meter 1.3333 3.1026837643 0.3073 0.7151089183 0.35 0.81447485 - -
6 R.C.C. Work (AR0404Ac) : Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge. (RCC Beams, Column, Girder & Bressmer etc) 4.890467 Cubic Meter 1.3333 6.5204596511 5.29605 25.90015775535 5.33875 26.10898069625 - -
7 R.C.C. Work (AR0404Ad) : Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge (RCC Lintels) 1.72523 Cubic Meter 1.3333 2.300249159 2.30105 3.9698404915 2.34375 4.0435078125 - -
8 R.C.C. Work (AR0404Ag) : Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge (RCC Roof slab, landing, balcony, sun shade) 8.18928 Cubic Meter 1.3333 10.918767024 3.11255 25.489543464 3.15525 25.83922572 - -
9 Masonry Brick Work (AR0602d) : C.B. Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:4) in foundation and plinth - Brickwork with C.B. Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:4) in foundation and plinth having crushing strength not less than 75.00 Kg/cm2 with dimensional tolerance ±8 percent immersing the bricks in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge. 22.107701 Cubic Meter 2.96 65.43879496 - - 1.05 23.21308605 0.35 7.73769535
10 Plastering (AR1004) : 12mm thick cement plster (1:6) over Brick work in inside - 12mm thick cement plster (1:6) over Brick work in inside including racking out joints finishing smooth with proper plumb and line curing for proper period with cost conveyance, royality, taxes of all materials, labour and T & P required for the work etc. comp.and as per direction of Engineer-in-charge. 102.48 Square Meter 0.12 12.2976 - - 0.14 14.3472 - -
11 Plastering (AR1014) : 16mm thick cement Plaster in CM (1:6) over brick work in inside. - 16mm thick cement Plaster in CM (1:6) over brick work in inside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc comp.and as per direction of Engineer-in-charge. 129.18 Square Meter 0.24 31.0032 - - 0.16 20.6688 - -
12 Plastering (AR1017) : 20mm thick cement Plaster in CM (1:4) over masonry work in inside. - 20mm thick cement Plaster in CM (1:4) over stone work in inside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc comp.and as per direction of Engineer-in-charge. 20.52 Square Meter 0.24 4.9248 - - 0.16 3.2832 - -
13 Other Building Items. (AR1901B) : Vitrified Tile 600mmx600mm Plain Ivory - Supplying, fitting & fixing Vitrified Tile 600mmx600mm Plain Ivory in floors of size 600mm x 600 mm of approved make conforming IS:13755 laid on 20 mm thick cement mortar(1:4)and filling joints with white cement of approved quality including cost of all materials, taxes, labour, T&P , etc. required for the work all complete as per direction of Engineer-in-charge(for new work only) 79.1415 Square Meter 0.216 17.094564 - - - - 0.216 17.094564
14 Painting (AR0922) : Finishing wall two coats with distemper of approved shades on new work (Inside) - Finishing wall two coats with distemper of approved shades on new work to give an even shade including all costs of labor, Paint and Brushes required for the work, etc. complete and as per direction of the Engineer-in-charge.(Inside) 191.7245 Square Meter 0.062 11.886919 - - - - 0.052 9.969674
15 Iron Work (AR1704) : Iron Doors and windows fixing - Supplying, fitting & fixing of Mild steel and put up for frames & shutters of Doors and windows fixing in position with cost, conveyance, taxes of all materials, labours and T & P required for the work etc. as per direction of Engineer-in-charge. 2.091 Quintal 6.3976377952756 13.377460629921 1.9685039370079 4.1161417322835 3.9370078740157 8.2322834645669 3.4448818897638 7.2032480314961
16 Painting (AR0903i) : Painting two coats of enamel paint in outer surface paint (outer surface) - Painting two coats of enamel paint in outer surface paint including all costs of labour, Paint and brushes required for the work etc. complete and as per direction of Engineer-in-charge.(Outside) 18.045 Square Meter 0.11827956989247 2.1343548387097 - - - - 0.13440860215054 2.4254032258065
17 Concrete (AR0317) : 2.5 cm thick grading concrete (1:2:2) on roof slab with 6mm size hard granite chips - 2.5 cm thick grading concrete (1:2:2) on roof slab with 6mm size hard granite chips including hoisting and laying in position compacting and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. (new work) 77.064 Square Meter 0.36 27.74304 - - - - 0.1 7.7064
18 R.C.C. Work (AR0409) : Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position - Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position including cost of binding wire 18 to 20 gauge with cost of steel rod and as per drawing, design, and direction of Engineer-in-charge. 24.046 Quintal 0.8 19.2368 0.044 1.058024 - - 0.3 7.2138
19 Painting (AR0918ca) : Finishing wall two coats with weather coat with one coat oilbound Primer - Finishing wall surface two coats with weather coat with one coat oilbound Primer including all costs of labour, Paint, Primer, Brushes and putty required for the work etc. complete and as per direction of Engineer-in-charge.(Outside) 123 Square Meter 0.11776344086022 14.484903225806 - - - - 0.10776344086022 13.254903225806
Total Qty 377.34834160884 132.63733739332 62.164909189433 72.605687833109
Rate Per Man Day 462 562 512 612
Total Amount 174334.93382328 74542.183615044 31828.43350499 44434.680953863
Total Labour Amount (in Rs.): 325140.23189718