State: Odisha District: Sundargarh Block: Bargaon Gram Panchayat: Bhoipali
Work Code: OD/373/3574/121539/384132/00039385 (CONSTRUCTION OF SHED AT RAIDIHI WEEKLY MARKET)
Project Category: Other Infrastructure
Financial Year: 2025-26 Execution Level: ps
Executing Agency: Panchayat Samiti, Bargaon Proposal Date: -
Date of Commencement: 29-11-2025 Date of Completion: 14-01-2026
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: Maintenance of Capital Assets
Project Sub-Category: Rural Haat Project Type: New Work
Name of Executant: DANBHUSAN XAXA AE
Administrative Approval Details
Approval No.: OD/373/3574/121539/384132/00039385/AS
Technical Sanction Details
Technical Sanction No.: OD/373/3574/121539/384132/00039385/TS
Fund Sanction No.: 26956
Fund Sanction Amount (in Rs.): 370000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Skilled Un-Skilled Highly-Skilled Semi-Skilled
562 462 612 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 3.875 Cubic Meter 3.9 15.1125 - - 0.18 0.6975 - -
2 Plastering (AR1004) : 12mm thick cement plster (1:6) over Brick work in inside - 12mm thick cement plster (1:6) over Brick work in inside including racking out joints finishing smooth with proper plumb and line curing for proper period with cost conveyance, royality, taxes of all materials, labour and T & P required for the work etc. comp.and as per direction of Engineer-in-charge. 39.2 Square Meter 0.12 4.704 - - 0.14 5.488 - -
3 Dismantling (AR1613) : Removing old lime or cement plaster - Removing old lime or cement plaster from walls including raking out joints 12 mm deep and removing the debris within 50m lead and as per direction of Engineer-in-Charge. 28 Square Meter 0.10752688172043 3.010752688172 - - - - - -
4 Masonry Brick Work (AR0603c) : Flyash Bricks of size (23cm x 11cm x 8cm) in cement mortar (1:6) in foundation and plinth - Brickwork with Flyash Bricks of size (23cm x 11cm x 8cm) in cement mortar (1:6) in foundation and plinth having crushing strength not less than 75.00 Kg/cm2 with dimensional tolerance ±8 percent immersing the bricks in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge. 3.588 Cubic Meter 2.96 10.62048 - - 1.05 3.7674 0.35 1.2558
5 Painting (AR0918hk) : Finishing wall with two coats weather coat paint of approved shade including one coat of water bound primer in the outer surface of old work(Outside)(For repair and maintenance). - Finishing wall with two coats weather coat paint of approved shade including one coat of water bound primer in the outer surface of old work to give an even shade including all costs of labour, Paint, Brushes, and putty required for the work, etc. complete and as per direction of Engineer-in-charge(Outside)(For repair and maintenance). 39.2 Square Meter 0.12011870967742 4.7086534193548 - - - - 0.10991870967742 4.3088134193548
6 Roofing (AR1132i) : Supplying, feeting & fixing of G.C.I. Sheet (0.40mm thick) in roof drilling hole in wind ties - Supplying, fitting & fixing of G.C.I. Sheet (0.40mm thick) in roof drilling hole in wind ties including fixing of ridges valleys wind ties etc. including cost of fitting, Labour and material etc. complete as per direction of Engineer-in-Charge 143.1 Square Meter 0.21505376344086 30.774193548387 - - - - 0.16129032258065 23.08064516129
7 Iron Work (AR1704) : Iron Doors and windows fixing - Supplying, fitting & fixing of Mild steel and put up for frames & shutters of Doors and windows fixing in position with cost, conveyance, taxes of all materials, labours and T & P required for the work etc. as per direction of Engineer-in-charge. 8.25 Quintal 6.3976377952756 52.780511811024 1.9685039370079 16.240157480315 3.9370078740157 32.48031496063 3.4448818897638 28.420275590551
8 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 16.6875 Cubic Meter 0.1236 2.062575 - - - - - -
9 Flooring (AR0816) : Fixing ceramic Tiles (30cmx30cm / 40cmx40cm special plain/printed series ceramic floor tiles of premium grade having thickness 7mm to 8mm confirming to IS 13755) in floor - Fixing ceramic Tiles (30cmx30cm / 40cmx40cm special plain/printed series ceramic floor tiles of premium grade having thickness 7mm to 8mm confirming to IS 13755) in floor , treads or steps and landing on a 25mm thick bed of cement mortar 1:1 (1cement: 1sand) jointed with neat cement slurry mixed with pigment to match the shades of the ceramic tiles including rubbing and polishing, cost of precast tiles complete as per direction of Enginer-in-charge. 76.25 Square Meter 0.216 16.47 0.55 41.9375 - - 0.216 16.47
Total Qty 42.43321496063 140.24366646694 73.535534171196 58.177657480315
Rate Per Man Day 562 462 612 512
Total Amount 23847.466807874 64792.573907725 45003.746912772 29786.960629921
Total Labour Amount (in Rs.): 163430.74825829