State: Odisha District: Kandhamal Block: K.Nuagan Gram Panchayat: Chanchedi
Work Code: OD/359/3426/118925/416200/00040191 (CONST OF DRAIN AT TAPOBANA TO TADANGIA)
Project Category: Water Body
Financial Year: 2022-23 Execution Level: ps
Executing Agency: Panchayat Samiti, K.Nuagan Proposal Date: 01-04-2023
Date of Commencement: 13-09-2025 Date of Completion: -
Scheme Name: SFC Devolution of Fund Scheme Component Name: 5TH SFC DEVOLUTION GRANT TO ZILLA PARISHAD
Project Sub-Category: Drainage Work Project Type: New Work
Name of Executant: SAROJ KUMAR PRADHAN
Administrative Approval Details
Approval No.: OD/359/3426/118925/416200/00040191/AS
Technical Sanction Details
Technical Sanction No.: OD/359/3426/118925/416200/00040191/TS
Fund Sanction No.: 45
Fund Sanction Amount (in Rs.): 300000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled
462 562 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 66.33 Cubic Meter 0.516 34.22628 - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 11.055 Cubic Meter 0.1236 1.366398 - - - -
3 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 31.155 Cubic Meter 3.9 121.5045 - - 0.18 5.6079
4 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 4.69 Cubic Meter 4.6 21.574 - - 0.68 3.1892
5 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 160.8 Square Meter - - 0.05 8.04 0.05 8.04
Total Qty 178.671178 16.8371 8.04
Rate Per Man Day 462 562 512
Total Amount 82546.084236 9462.4502 4116.48
Total Labour Amount (in Rs.): 96125.014436