State: Odisha District: Sonepur Block: Biramaharajpur Gram Panchayat: Luthurpank
Work Code: OD/372/3568/121447/419459/00040570 (Construction of CC Road at Kulsahi village)
Project Category: Road
Financial Year: 2024-25 Execution Level: ps
Executing Agency: Panchayat Samiti, Biramaharajpur Proposal Date: 10-12-2024
Date of Commencement: - Date of Completion: -
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: All Weather Connectivity
Project Sub-Category: CC Road Project Type: New Work
Name of Executant:
Administrative Approval Details
Approval No.:
Technical Sanction Details
Technical Sanction No.:
Fund Sanction No.: 29143
Fund Sanction Amount (in Rs.): 143788
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Semi-Skilled Skilled Un-Skilled
512 562 462
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 24.75 Square Meter - - 0.05 1.2375 0.05 1.2375
2 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 9.03375 Cubic Meter 4.6 41.55525 - - 0.68 6.14295
3 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 11.34375 Cubic Meter 3.9 44.240625 - - 0.18 2.041875
4 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 8.58 Cubic Meter 0.1236 1.060488 - - - -
5 Earth Work (AR0102a1) : Earthwork in hard soil or gravelly soil within 50m to 75m lead and 1.5m, initial lift - Earthwork in hard soil or gravelly soil within 50m to 75m lead and 1.5m, initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per direction of the Engineer-in-charge. 1.98 Cubic Meter 0.46 0.9108 - - - -
Total Qty 1.2375 9.422325 87.767163
Rate Per Man Day 512 562 462
Total Amount 633.6 5295.34665 40548.429306
Total Labour Amount (in Rs.): 46477.375956