State: Odisha District: Koraput Block: Pottangi Gram Panchayat: Deopattangi
Work Code: OD/363/3478/119901/430050/00043031 (Repair and maintenance of UP School Salapguda)
Project Category: Building
Financial Year: 2024-25 Execution Level: ps
Executing Agency: Panchayat Samiti, Pottangi Proposal Date: 16-07-2024
Date of Commencement: 20-01-2026 Date of Completion: -
Scheme Name: SFC Devolution of Fund Scheme Component Name: 5TH SFC DEVOLUTION GRANT TO PANCHAYAT SAMITI
Project Sub-Category: Elementary School Project Type: Repair and Maintenance
Name of Executant: PRASANNA GARADA
Administrative Approval Details
Approval No.: OD/363/3478/119901/430050/00043031/AS
Technical Sanction Details
Technical Sanction No.: OD/363/3478/119901/430050/00043031/TS
Fund Sanction No.: 15384
Fund Sanction Amount (in Rs.): 100000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Highly-Skilled Skilled
462 612 562
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Dismantling (AR1620) : Dismantling and removing 2.5 cm thick grading concrete from roof - Dismantling and removing 2.5 cm thick grading concrete from roof slab cleaning the surface lowering and removing the debris within 50m lead and as per direction of Engineer-in-Charge. 84 Square Meter 0.24193548387097 20.322580645161 - - - -
2 Concrete (AR0317) : First floor - 2.5 cm thick grading concrete (1:2:2) on roof slab with 6mm size hard granite chips including hoisting and laying in position compacting and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. (new work) 84 Square Meter 0.414 34.776 - - 0.115 9.66
3 Dismantling (AR1613) : Fifth Floor - Removing old lime or cement plaster from walls including raking out joints 12 mm deep and removing the debris within 50m lead and as per direction of Engineer-in-Charge. 28.8 Square Meter 0.1372345766129 3.9523558064516 - - - -
4 Other Building Items. (AR1902) : First Floor - Finishing surface of walls with cement based wall putty (water based) of approved make and finished smooth and even surface to receive painting including cost of scaffolding staging charges with cost of all materials taxes,labour,T&P,etc.complete. and as per the direction of Engineer in Charge. 68.07 Square Meter 0.05871 3.9963897 0.0515 3.505605 - -
5 Painting (AR0901d) : Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces (Inner surface) - Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces including cost conveyance, taxes of all materials, labor and T&P required for the work complete as per direction of the Engineer-in-charge. 167.4675 Square Meter 0.053763440860215 9.0036290322581 - - 0.053763440860215 9.0036290322581
6 Painting (AR0920) : First Floor - Finishing wall two coats with plastic emulsion paint of approved shades on new work to give an even shade including all costs of labor, Paint and Brushes required for the work, etc. complete and as per direction of the Engineer-in-charge.(Inside) 168 Square Meter 0.06592 11.07456 - - 0.05562 9.34416
7 Painting (AR0918cb) : Finishing wall two coats with weather coat with one coat waterbound Primer - Finishing wall two coats with weather coat with one coat waterbound Primer including all costs of labour, Paint, Primer, Brushes and putty required for the work etc. complete and as per direction of Engineer-in-charge.(Outside) 115.56 Square Meter 0.11776344086022 13.608743225806 - - 0.10776344086022 12.453143225806
Total Qty 96.734258409677 40.460932258065 3.505605
Rate Per Man Day 462 612 562
Total Amount 44691.227385271 24762.090541935 1970.15001
Total Labour Amount (in Rs.): 71423.467937206