State: Odisha District: Kendujhar Block: Jhumpura Gram Panchayat: Balibandha
Work Code: OD/361/3450/119416/385542/00043413 (RENOVATION OF HATA TOTA POKHARI BALIBANDHA )
Project Category: Water Body
Financial Year: 2025-26 Execution Level: ps
Executing Agency: Panchayat Samiti, Jhumpura Proposal Date: -
Date of Commencement: 22-12-2025 Date of Completion: -
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: Maintenance of Capital Assets
Project Sub-Category: Tank Project Type: Renovation or Rejuvenation
Name of Executant: Mihir Kumar Tudu
Administrative Approval Details
Approval No.: OD/361/3450/119416/385542/00043413/AS
Technical Sanction Details
Technical Sanction No.: OD/361/3450/119416/385542/00043413/TS
Fund Sanction No.: 26956
Fund Sanction Amount (in Rs.): 500000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Highly-Skilled Semi-Skilled
462 562 612 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 65.0295312 Cubic Meter 0.516 33.5552380992 - - - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 21.55191648 Cubic Meter 0.1236 2.663816876928 - - - - - -
3 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 23.94114648 Cubic Meter 3.9 93.370471272 - - 0.18 4.3094063664 - -
4 Concrete (AR0307a) : Cement concrete (1:2:4)with 12mm size hard granite(Hand broken)chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(hand broken) chips including hoisting and laying in position compacting to proper thickness and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 13.21261888 Cubic Meter 4.6 60.778046848 - - 0.68 8.9845808384 - -
6 Masonry Stone Work (AR0713) : Rough stone dry packing in approns and revetments with hard granite stones (15cm to 30cm) with hard granite stones - Rough stone dry packing in approns and revetments with hard granite stones (15cm to 30cm) with hard granite stones of size not less than 0.0025 cum stacked including cost, conveyance, royalty, taxes of all materials, labour required for the work etc. complete and as per direction of Engineer-in charge. (15cm-30cm) 59.46528 Cubic Meter 1.04 61.8438912 0.35 20.812848 - - 0.17 10.1090976
7 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 154.21898 Square Meter - - 0.05 7.710949 0.05 7.710949 - -
Total Qty 252.21146429613 21.0049362048 10.1090976 28.523797
Rate Per Man Day 462 562 612 512
Total Amount 116521.69650481 11804.774147098 6186.7677312 14604.184064
Total Labour Amount (in Rs.): 149117.42244711