State: Odisha District: Kendrapara Block: Garadapur Gram Panchayat: Bangalpur
Work Code: OD/360/3436/119091/396706/00045026 (Const. Of Road With Pavour Block From Ghoda Danad Nira Nayak House To Barik Sahi Road, Village Nuasasan)
Project Category: Road
Financial Year: 2023-24 Execution Level: ps
Executing Agency: Panchayat Samiti, Garadapur Proposal Date: -
Date of Commencement: 23-10-2025 Date of Completion: 06-01-2026
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: Maintenance and improvement of Road infrastructure
Project Sub-Category: CC Road Project Type: Repair and Maintenance
Name of Executant: PRADIP SAMANTRAY JE
Administrative Approval Details
Approval No.: OD/360/3436/119091/396706/00045026/AS
Technical Sanction Details
Technical Sanction No.: OD/360/3436/119091/396706/00045026/TS
Fund Sanction No.: 31142
Fund Sanction Amount (in Rs.): 133422
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled
462 562 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 4.23225 Cubic Meter 0.516 2.183841 - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 9.56175 Cubic Meter 0.1236 1.1818323 - - - -
3 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 5.643 Cubic Meter 4.6 25.9578 - - 0.68 3.83724
5 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 50.16 Square Meter - - 0.05 2.508 0.05 2.508
Total Qty 29.3234733 6.34524 2.508
Rate Per Man Day 462 562 512
Total Amount 13547.4446646 3566.02488 1284.096
Total Labour Amount (in Rs.): 18397.5655446