State: Odisha District: Koraput Block: Jeypore Gram Panchayat: Anta
Work Code: OD/363/3470/119778/429073/00046195 (REPAIR AND RENOVATION OF AWC AT DAMAPUT)
Project Category: Building
Financial Year: 2021-22 Execution Level: ps
Executing Agency: Panchayat Samiti, Jeypore Proposal Date: 05-10-2021
Date of Commencement: 05-08-2025 Date of Completion: 28-08-2025
Scheme Name: SFC Devolution of Fund Scheme Component Name: 5TH SFC DEVOLUTION GRANT TO PANCHAYAT SAMITI
Project Sub-Category: AWC Project Type: Repair and Maintenance
Name of Executant: TARUN KUMAR NAIK
Administrative Approval Details
Approval No.: OD/363/3470/119778/429073/00046195/AS
Technical Sanction Details
Technical Sanction No.: OD/363/3470/119778/429073/00046195/TS
Fund Sanction No.: 17170
Fund Sanction Amount (in Rs.): 150000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Highly-Skilled
462 562 612
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 23.2675 Cubic Meter 0.516 12.00603 - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 13.5935 Cubic Meter 0.1236 1.6801566 - - - -
3 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 7.9915 Cubic Meter 3.9 31.16685 0.18 1.43847 - -
4 Plastering (AR1004) : 12mm thick cement plster (1:6) over Brick work in inside - 12mm thick cement plster (1:6) over Brick work in inside including racking out joints finishing smooth with proper plumb and line curing for proper period with cost conveyance, royality, taxes of all materials, labour and T & P required for the work etc. comp.and as per direction of Engineer-in-charge. 66.7954 Square Meter 0.12 8.015448 0.14 9.351356 - -
5 Painting (AR0901a) : Priming one coat in inner surface with primer of approved quality over woodwork - Priming one coat in inner surface with primer of approved quality over woodwork including cost conveyance, taxes of all materials, labor and T&P required for the work complete as per direction of the Engineer-in-charge. 66.7954 Square Meter 0.053763440860215 3.5911505376344 - - 0.053763440860215 3.5911505376344
6 Painting (AR0922) : Finishing wall two coats with distemper of approved shades on new work (Inside) - Finishing wall two coats with distemper of approved shades on new work to give an even shade including all costs of labor, Paint and Brushes required for the work, etc. complete and as per direction of the Engineer-in-charge.(Inside) 66.7954 Square Meter 0.062 4.1413148 - - 0.052 3.4733608
7 Masonry Brick Work (AR0603bi) : Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in superstructure - Brickwork with Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in superstructure having crushing strength not less than 75.00 Kg/cm2 with dimensional tolerance ±8 percent immersing the bricks in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge. 11.94389 Cubic Meter 2.96 35.3539144 1.05 12.5410845 0.35 4.1803615
Total Qty 95.954864337634 23.3309105 11.244872837634
Rate Per Man Day 462 562 612
Total Amount 44331.147323987 13111.971701 6881.8621766323
Total Labour Amount (in Rs.): 64324.981201619