State: Odisha District: Angul Block: Banarpal Gram Panchayat: Kurudol
Work Code: OD/344/3278/115622/404107/00048374 (COMPLETION OF KALYAN MANDAP)
Project Category: Building
Financial Year: 2025-26 Execution Level: ps
Executing Agency: Panchayat Samiti, Banarpal Proposal Date: -
Date of Commencement: 09-01-2026 Date of Completion: -
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: Maintenance of Capital Assets
Project Sub-Category: Kalyan Mandap Project Type: Completion
Name of Executant: Mahesh Kumar samal
Administrative Approval Details
Approval No.: OD/344/3278/115622/404107/00048374/AS
Technical Sanction Details
Technical Sanction No.: OD/344/3278/115622/404107/00048374/TS
Fund Sanction No.: 33742
Fund Sanction Amount (in Rs.): 1000000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Skilled Un-Skilled Semi-Skilled Highly-Skilled
562 462 512 612
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 24.318 Cubic Meter 3.9 94.8402 - - 0.18 4.37724 - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 121.59 Cubic Meter 0.1236 15.028524 - - - - - -
3 R.C.C. Work (AR0404Ac) : Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge. (RCC Beams, Column, Girder & Bressmer etc) 10.2795 Cubic Meter 1.3333 13.70565735 5.29605 54.440745975 5.33875 54.879680625 - -
4 R.C.C. Work (AR0404Ab) : Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge (RCC Plinth band) 10.5744 Cubic Meter 1.3333 14.09884752 0.3073 3.24951312 0.35 3.70104 - -
5 Masonry Brick Work (AR0603ci) : Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in superstructure - Brickwork with Flyash Bricks of size (23cm x 11cm x 8cm) in cement mortar (1:6) in superstructure having crushing strength not less than 75.00 Kg/cm2 with dimensional tolerance ±8 percent immersing the bricks in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge. 47.978625 Cubic Meter 2.96 142.01673 - - 1.05 50.37755625 0.35 16.79251875
6 R.C.C. Work (AR0404Ad) : Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge (RCC Lintels) 3.78075 Cubic Meter 1.3333 5.040873975 2.30105 8.6996947875 2.34375 8.8611328125 - -
7 R.C.C. Work (AR0409) : Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position - Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position including cost of binding wire 18 to 20 gauge with cost of steel rod and as per drawing, design, and direction of Engineer-in-charge. 31.8 Quintal 0.8 25.44 0.044 1.3992 - - 0.3 9.54
Total Qty 122.1966496875 310.170832845 67.7891538825 26.33251875
Rate Per Man Day 562 462 512 612
Total Amount 68674.517124375 143298.92477439 34708.04678784 16115.501475
Total Labour Amount (in Rs.): 262796.99016161