State: Odisha District: Sonepur Block: Tarbha Gram Panchayat: Pua
Work Code: OD/372/3571/121500/419646/00051661 (Development of Rural Haat at Pua)
Project Category: Other Infrastructure
Financial Year: 2022-23 Execution Level: ps
Executing Agency: Panchayat Samiti, Tarbha Proposal Date: -
Date of Commencement: 22-01-2026 Date of Completion: -
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: Development of Rural Haat
Project Sub-Category: Rural Haat Project Type: New Work
Name of Executant: KSHIRODINI NAIK
Administrative Approval Details
Approval No.: OD/372/3571/121500/419646/00051661/AS
Technical Sanction Details
Technical Sanction No.: OD/372/3571/121500/419646/00051661/TS
Fund Sanction No.: 20484
Fund Sanction Amount (in Rs.): 1000000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Highly-Skilled
462 562 612
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 68.7816 Cubic Meter 0.516 35.4913056 - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 110.56542 Cubic Meter 0.1236 13.665885912 - - - -
3 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 27.611235 Cubic Meter 3.9 107.6838165 0.18 4.9700223 - -
4 Masonry Brick Work (AR0603b) : Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in foundation and plinth - Brickwork with Flyash Bricks of size (25cm x 12cm x 8cm) in cement mortar (1:6) in foundation and plinth having crushing strength not less than 75.00 Kg/cm2 with dimensional tolerance ±8 percent immersing the bricks in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge. 60.8076 Cubic Meter 2.96 179.990496 1.05 63.84798 0.35 21.28266
5 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 20.226 Cubic Meter 4.6 93.0396 0.68 13.75368 - -
6 Plastering (AR1004) : 12mm thick cement plster (1:6) over Brick work in inside - 12mm thick cement plster (1:6) over Brick work in inside including racking out joints finishing smooth with proper plumb and line curing for proper period with cost conveyance, royality, taxes of all materials, labour and T & P required for the work etc. comp.and as per direction of Engineer-in-charge. 91.452 Square Meter 0.12 10.97424 0.14 12.80328 - -
7 Roofing (AR1132i) : Supplying, feeting & fixing of G.C.I. Sheet (0.40mm thick) in roof drilling hole in wind ties - Supplying, fitting & fixing of G.C.I. Sheet (0.40mm thick) in roof drilling hole in wind ties including fixing of ridges valleys wind ties etc. including cost of fitting, Labour and material etc. complete as per direction of Engineer-in-Charge 209.41 Square Meter 0.21505376344086 45.034408602151 - - 0.16129032258065 33.775806451613
Total Qty 485.87975261415 95.3749623 55.058466451613
Rate Per Man Day 462 562 612
Total Amount 224476.44570774 53600.7288126 33695.781468387
Total Labour Amount (in Rs.): 311772.95598872