State: Odisha District: Balasore Block: Oupada Gram Panchayat: Shyamasundarpur
Work Code: OD/346/3306/116264/393202/00052045 (Construction of CC road from karunakar Parida house to Pradeep Behera house)
Project Category: Road
Financial Year: 2022-23 Execution Level: ps
Executing Agency: Panchayat Samiti, Oupada Proposal Date: 03-12-2022
Date of Commencement: 15-09-2025 Date of Completion: 16-09-2025
Scheme Name: SFC Devolution of Fund Scheme Component Name: 5TH SFC DEVOLUTION GRANT TO ZILLA PARISHAD
Project Sub-Category: CC Road Project Type: New Work
Name of Executant: Jyotirashmi Nayak
Administrative Approval Details
Approval No.: OD/346/3306/116264/393202/00052045/AS
Technical Sanction Details
Technical Sanction No.: OD/346/3306/116264/393202/00052045/TS
Fund Sanction No.: 4897
Fund Sanction Amount (in Rs.): 100000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled
462 562 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 0.9301644 Cubic Meter 0.516 0.4799648304 - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 5.118621 Cubic Meter 0.1236 0.6326615556 - - - -
3 Concrete (AR0303a) : Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal - Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 7.129619 Cubic Meter 3.9 27.8055141 - - 0.18 1.28333142
4 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 5.6034 Cubic Meter 4.6 25.77564 - - 0.68 3.810312
5 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 14.71536 Square Meter - - 0.05 0.735768 0.05 0.735768
Total Qty 54.693780486 5.82941142 0.735768
Rate Per Man Day 462 562 512
Total Amount 25268.526584532 3276.12921804 376.713216
Total Labour Amount (in Rs.): 28921.369018572