State: Odisha District: Ganjam Block: Patrapur Gram Panchayat: Tandipur
Work Code: OD/354/3379/117894/413152/00052877 (CONST OF CC ROAD AND PAVER BLOCK ROAD AT PWD ROAD AT PANASA KHOLA)
Project Category: Road
Financial Year: 2025-26 Execution Level: ps
Executing Agency: Panchayat Samiti, Patrapur Proposal Date: -
Date of Commencement: 14-11-2025 Date of Completion: -
Scheme Name: Chief Minister Special Assistant Scheme Component Name: Special Problem Fund (SPF) 16 th Phase
Project Sub-Category: Pavor Block Project Type: New Work
Name of Executant: SUNIL KUMAR JANI
Administrative Approval Details
Approval No.: OD/354/3379/117894/413152/00052877/AS
Technical Sanction Details
Technical Sanction No.: OD/354/3379/117894/413152/00052877/TS
Fund Sanction No.:
Fund Sanction Amount (in Rs.): 1000000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled
462 562 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 36.8253 Cubic Meter 0.516 19.0018548 - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 108.3431 Cubic Meter 0.1236 13.39120716 - - - -
3 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 28.23273 Cubic Meter 3.9 110.107647 - - 0.18 5.0818914
4 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 245.502 Square Meter - - 0.05 12.2751 0.05 12.2751
6 Earth Work (AR0110) : Fine dressing of earth work in ordinary or hard soil in road formation - Fine dressing of earth work in ordinary or hard soil in road formaton according to the direction of the department including cutting or filling earth upto 0.15m depth of surface. 861.4 Square Meter 0.01 8.614 - - - -
Total Qty 151.11470896 17.3569914 12.2751
Rate Per Man Day 462 562 512
Total Amount 69814.99553952 9754.6291668 6284.8512
Total Labour Amount (in Rs.): 85854.47590632