State: Odisha District: Kalahandi Block: Dharamagarh Gram Panchayat: Bramhanchhendia
Work Code: OD/358/3410/118629/423938/00060124 (CREATION OF BANKING INFRASTRUCTURE AT BRAHMANCHHENDIA GP)
Project Category: Building
Financial Year: 2022-23 Execution Level: ps
Executing Agency: Panchayat Samiti, Dharamagarh Proposal Date: 05-09-2023
Date of Commencement: 25-01-2026 Date of Completion: -
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: Infrastructure for Banking Facilities at GP Hqrs
Project Sub-Category: Banking Facility Building Project Type: New Work
Name of Executant: JYOTIPRAKASH PRADHAN
Administrative Approval Details
Approval No.: OD/358/3410/118629/423938/00060124/AS
Technical Sanction Details
Technical Sanction No.: OD/358/3410/118629/423938/00060124/TS
Fund Sanction No.: 4595
Fund Sanction Amount (in Rs.): 1000000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Highly-Skilled Semi-Skilled
462 562 612 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Masonry Brick Work (AR0603ci) : First floor - Brickwork with Flyash Bricks of size (23cm x 11cm x 8cm) in cement mortar (1:6) in superstructure having crushing strength not less than 75.00 Kg/cm2 with dimensional tolerance ±8 percent immersing the bricks in water not less than six hours with cost conveyance, royalty, taxes of all materials, labor, and T&P required for the work, etc. complete and as per direction of Engineer-in-charge. 24.8118 Cubic Meter 3.404 84.4593672 - - 1.2075 29.9602485 0.4025 9.9867495
2 R.C.C. Work (AR0404Ac) : First Floor - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge. (RCC Beams, Column, Girder & Bressmer etc) 8.7417 Cubic Meter 1.533295 13.4036049015 6.352395 55.5307313715 6.4015 55.95999255 - -
3 R.C.C. Work (AR0404Ad) : First Floor - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge (RCC Lintels) 1.3975 Cubic Meter 1.533295 2.1427797625 2.758395 3.8548570125 2.8075 3.92348125 - -
4 R.C.C. Work (AR0404Ag) : First Floor - Reinforced cement concrete work of M-20 grade with 20mm & down grade size black hard crusher broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. (including centring and shuttering) complete and as per direction of Engineer-in charge (RCC Roof slab, landing, balcony, sun shade) 14.8707375 Cubic Meter 1.533295 22.801227455062 3.732195 55.500492143812 3.7813 56.23071970875 - -
5 Plastering (AR1004) : First Floor - 12mm thick cement plster (1:6) over Brick work in inside including racking out joints finishing smooth with proper plumb and line curing for proper period with cost conveyance, royality, taxes of all materials, labour and T & P required for the work etc. comp.and as per direction of Engineer-in-charge. 135.679 Square Meter 0.1236 16.7699244 - - 0.1442 19.5649118 - -
6 Plastering (AR1014) : First Floor - 16mm thick cement Plaster in CM (1:6) over brick work in inside including racking out joints finishing smooth with proper plumb and line, curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T & P required for the work etc comp.and as per direction of Engineer-in-charge. 62.655 Square Meter 0.2472 15.488316 - - 0.1648 10.325544 - -
7 Other Building Items. (AR1902) : First Floor - Finishing surface of walls with cement based wall putty (water based) of approved make and finished smooth and even surface to receive painting including cost of scaffolding staging charges with cost of all materials taxes,labour,T&P,etc.complete. and as per the direction of Engineer in Charge. 222.435 Square Meter 0.05871 13.05915885 - - 0.0515 11.4554025 - -
8 Painting (AR0918c) : First Floor - Finishing wall with two coat water proofing cement paint including one coat cement wash on the outer surface of approved shade on new work to give an even shade including all costs of labour, Paint, Brushes, and putty required for the work, etc. complete and as per direction of Engineer-in-charge. (Outside) 12.604986137 Square Meter 0.044890322580645 0.56584189381449 - - 0.0084677419354839 0.10673576970847 0.0231 0.2911751797647
9 Painting (AR0901d) : First Floor - Priming one coat with inner surface primer of approved quality water-bound primer over plastering surfaces including cost conveyance, taxes of all materials, labor and T&P required for the work complete as per direction of the Engineer-in-charge. 12.331479705 Square Meter 0.055376344086022 0.68287226323387 - - - - 0.055376344086022 0.68287226323387
10 Painting (AR0920) : First Floor - Finishing wall two coats with plastic emulsion paint of approved shades on new work to give an even shade including all costs of labor, Paint and Brushes required for the work, etc. complete and as per direction of the Engineer-in-charge.(Inside) 12.331479705 Square Meter 0.06592 0.8128911421536 - - - - 0.05562 0.6858769011921
11 Painting (AR0918Ai) : First Floor - Finishing wall one coat with weather coat including all costs of labour, Paint, Primer and Brushes required for the work etc. complete and as per direction of Engineer-in-charge. 5.957590681 Square Meter 0.04515 0.26898521924715 - - - - 0.0378 0.2251969277418
12 Iron Work (AR1704) : Iron Doors and windows fixing - Supplying, fitting & fixing of Mild steel and put up for frames & shutters of Doors and windows fixing in position with cost, conveyance, taxes of all materials, labours and T & P required for the work etc. as per direction of Engineer-in-charge. 2.7494 Quintal 6.3976377952756 17.589665354331 1.9685039370079 5.4122047244094 3.9370078740157 10.824409448819 3.4448818897638 9.4713582677165
13 R.C.C. Work (AR0409) : First floor - Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position including cost of binding wire 18 to 20 gauge with cost of steel rod and as per drawing, design, and direction of Engineer-in-charge. 24 Quintal 0.84 20.16 0.0462 1.1088 - - 0.315 7.56
14 Flooring (AR0816) : First floor - Fixing ceramic Tiles (30cmx30cm / 40cmx40cm special plain/printed series ceramic floor tiles of premium grade having thickness 7mm to 8mm confirming to IS 13755) in floor , treads or steps and landing on a 25mm thick bed of cement mortar 1:1 (1cement: 1sand) jointed with neat cement slurry mixed with pigment to match the shades of the ceramic tiles including rubbing and polishing, cost of precast tiles complete as per direction of Enginer-in-charge. 100.1 Square Meter 0.2268 22.70268 0.5775 57.80775 - - 0.2268 22.70268
15 Flooring (AR0817aa) : First floor - Fixing Vitrified tiles of premium grade having thickness 8mm to 10mm confirming to IS 13756 of size 600mmx600mm plain (Ivory) in dados skirting and risers of steps on 12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with pigments to match the shade of the Vitrified tiles including rubbing and polishing complete including cost of precast tiles. 6.57 Square Meter 0.34125 2.2420125 0.798 5.24286 - - 0.34125 2.2420125
Total Qty 233.14932694184 198.35144552728 53.847921539649 184.45769525222
Rate Per Man Day 462 562 612 512
Total Amount 107714.98904713 111473.51238633 32954.927982265 94442.339969138
Total Labour Amount (in Rs.): 346585.76938486