State: Odisha District: Puri Block: Gop Gram Panchayat: Nagapur
Work Code: OD/369/3539/120947/409499/00061770 (Improvement of Baligoradi Mohanty Sahi CC road)
Project Category: Road
Financial Year: 2020-21 Execution Level: ps
Executing Agency: Panchayat Samiti, Gop Proposal Date: 15-07-2021
Date of Commencement: 24-10-2025 Date of Completion: 25-10-2025
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: Maintenance and improvement of Road infrastructure
Project Sub-Category: CC Road Project Type: Upgradation or Improvement
Name of Executant: Manoj Kumar Swain
Administrative Approval Details
Approval No.: OD/369/3539/120947/409499/00061770/AS
Technical Sanction Details
Technical Sanction No.: OD/369/3539/120947/409499/00061770/TS
Fund Sanction No.: 11088
Fund Sanction Amount (in Rs.): 118350
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled
462 562 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 2.584 Cubic Meter 0.516 1.333344 - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 5.3 Cubic Meter 0.1236 0.65508 - - - -
3 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 9.3312 Cubic Meter 3.9 36.39168 - - 0.18 1.679616
4 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 9.69 Square Meter - - 0.05 0.4845 0.05 0.4845
5 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 6.254 Cubic Meter 4.6 28.7684 - - 0.68 4.25272
Total Qty 67.148504 6.416836 0.4845
Rate Per Man Day 462 562 512
Total Amount 31022.608848 3606.261832 248.064
Total Labour Amount (in Rs.): 34876.93468