State: Odisha District: Balasore Block: Basta Gram Panchayat: Natakata
Work Code: OD/346/3301/116130/392386/00065285 (CONSTRUCTION OF CC ROAD FROM MAHALSAHI TO BENUDHAR BHADRA HOUSE)
Project Category: Road
Financial Year: 2021-22 Execution Level: ps
Executing Agency: Panchayat Samiti, Basta Proposal Date: 08-06-2021
Date of Commencement: 25-11-2025 Date of Completion: 15-12-2025
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: Maintenance and improvement of Road infrastructure
Project Sub-Category: CC Road Project Type: Upgradation or Improvement
Name of Executant: BHAGYALAXMI MOHANTA
Administrative Approval Details
Approval No.: OD/346/3301/116130/392386/00065285/AS
Technical Sanction Details
Technical Sanction No.: OD/346/3301/116130/392386/00065285/TS
Fund Sanction No.: 9114
Fund Sanction Amount (in Rs.): 300000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled
462 562 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0101a1) : Earthwork in ordinary soil within 50m to 75m lead and 1.5m, initial lift - Earthwork in ordinary soil within 50m to 75m lead and 1.5m, initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per direction of the Engineer-in-charge. 4.24752 Cubic Meter 0.35 1.486632 - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 15.3760224 Cubic Meter 0.1236 1.90047636864 - - - -
3 Concrete (AR0303a) : Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal - Cement concrete (1:3:6) with 4 cm. hard granite(Hand Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 22.4269056 Cubic Meter 3.9 87.46493184 - - 0.18 4.036843008
4 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 14.7813696 Cubic Meter 4.6 67.99430016 - - 0.68 10.051331328
5 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 36.789588 Square Meter - - 0.05 1.8394794 0.05 1.8394794
Total Qty 158.84634036864 15.927653736 1.8394794
Rate Per Man Day 462 562 512
Total Amount 73387.009250312 8951.341399632 941.8134528
Total Labour Amount (in Rs.): 83280.164102744