State: Odisha District: Ganjam Block: Polosara Gram Panchayat: Balichai
Work Code: OD/354/3380/117898/411379/00068310 (Completion of AWC-I at Nodal School Premises at Balichai)
Project Category: Building
Financial Year: 2021-22 Execution Level: ps
Executing Agency: Panchayat Samiti, Polosara Proposal Date: 18-06-2021
Date of Commencement: 15-12-2025 Date of Completion: 17-12-2025
Scheme Name: SFC Devolution of Fund Scheme Component Name: 5TH SFC DEVOLUTION GRANT TO PANCHAYAT SAMITI
Project Sub-Category: AWC Project Type: Completion
Name of Executant: Sarat Kumar Malla
Administrative Approval Details
Approval No.: OD/354/3380/117898/411379/00068310/AS
Technical Sanction Details
Technical Sanction No.: OD/354/3380/117898/411379/00068310/TS
Fund Sanction No.: 7726
Fund Sanction Amount (in Rs.): 200000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Semi-Skilled Skilled Un-Skilled Highly-Skilled
512 562 462 612
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 R.C.C. Work (AR0410d) : Rigid and smooth centering and shuttering for R.C.C. works including false works and dismantling them after casting - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. beams, column, grider and bressmer, etc. Data for 4.2sqm 26.9044765425 Square Meter - - 0.6547619047619 17.616026307589 0.6547619047619 17.616026307589 - -
2 R.C.C. Work (AR0410a) : Centring & Shuttering for R.C.C. floor and roof slabs, landings,balconies, projecting sun shades and chajjas - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. floor and roof slabs, landings, balconies, projecting sun shades and chajjas up to 4.3m height 43.5158209418 Square Meter - - 0.30555555555556 13.296500843328 0.30555555555556 13.296500843328 - -
3 R.C.C. Work (AR0402a) : Reinforced cement concrete (1:11/2:3) work with 12mm size black hard hand broken granite chips - 'Reinforced cement concrete (1:1.5:3) work with 12mm size black hard hand broken granite chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty,taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. (To be used for minor repair work only) 8.6419935732 Cubic Meter 4.6 39.75317043672 - - 0.68 5.876555629776 - -
4 R.C.C. Work (AR0409) : Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position - Supplying, fitting, and placing uncoated HYSD bar reinforcement including labor charges for cutting, bending, binding, and tying the grills and placing in position including cost of binding wire 18 to 20 gauge with cost of steel rod and as per drawing, design, and direction of Engineer-in-charge. 8.62 Quintal 0.8 6.896 0.044 0.37928 - - 0.3 2.586
5 Plastering (AR1027) : 6mm thick cement Plaster in CM (1:4) over R.C.C. surfaces including chipping (Inside) - 6mm thick cement Plaster in CM (1:4) over R.C.C. surfaces in inside including chipping with proper level and line, curing for the proper period with cost conveyance, royalty, taxes of all materials, labor, and T & P required for the work, etc comp. and as per the direction of the Engineer-in-charge. 24.89428788 Square Meter 0.17 4.2320289396 - - 0.14 3.4852003032 - -
Total Qty 31.291807150917 40.274283083893 50.88119937632 2.586
Rate Per Man Day 512 562 462 612
Total Amount 16021.40526127 22634.147093148 23507.11411186 1582.632
Total Labour Amount (in Rs.): 63745.298466277