State: Odisha District: Balangir Block: Patnagarh Gram Panchayat: Ghuchepali
Work Code: OD/345/3293/115945/420701/00069837 (CONST OF GUARD WALL AT DANDARABAHAL TO FUDUKUPADA ROAD)
Project Category: CD Work
Financial Year: 2023-24 Execution Level: ps
Executing Agency: Panchayat Samiti, Patnagarh Proposal Date: -
Date of Commencement: 11-12-2025 Date of Completion: -
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: MAINTENANCE OF ROADS AND BRIDGES
Project Sub-Category: Drain Masonry or Cement Concrete Project Type: New Work
Name of Executant: Krushmohan Sahu
Administrative Approval Details
Approval No.: OD/345/3293/115945/420701/00069837/AS
Technical Sanction Details
Technical Sanction No.: OD/345/3293/115945/420701/00069837/TS
Fund Sanction No.:
Fund Sanction Amount (in Rs.): 300000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled
462 562 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 32.11875 Cubic Meter 0.516 16.573275 - - - -
2 Earth Work (AR0115) : Filling foundation and plinth with sand well watered and rammed - Filling foundation and plinth with sand well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 6.42375 Cubic Meter 0.1236 0.7939755 - - - -
3 Concrete (AR0303) : Cement concrete (1:3:6) with 4 cm. Crusher Broken hard granite metal - Cement concrete (1:3:6) with 4 cm. hard granite(Crusher Broken) metal including laying in layers not exceeding 300 mm in depth, ramming, compacting to proper thickness, watering and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete and as per direction of Engineer-in charge. 51.961 Cubic Meter 3.9 202.6479 - - 0.18 9.35298
4 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 92.296 Square Meter - - 0.05 4.6148 0.05 4.6148
Total Qty 220.0151505 13.96778 4.6148
Rate Per Man Day 462 562 512
Total Amount 101646.999531 7849.89236 2362.7776
Total Labour Amount (in Rs.): 111859.669491