State: Odisha District: Ganjam Block: Rangeilunda Gram Panchayat: Karapalli
Work Code: OD/354/3382/117960/412624/00073714 (IMPROVEMENT OF ROAD AT RAKSHYA BIHAR AT KARAPALLI)
Project Category: Road
Financial Year: 2022-23 Execution Level: ps
Executing Agency: Panchayat Samiti, Rangeilunda Proposal Date: 05-08-2022
Date of Commencement: 20-01-2026 Date of Completion: 29-01-2026
Scheme Name: 5th SFC Grant in Aid Scheme Component Name: All Weather Connectivity
Project Sub-Category: Pavor Block Project Type: New Work
Name of Executant: CHANDRA SEKHAR SARANGI
Administrative Approval Details
Approval No.: OD/354/3382/117960/412624/00073714/AS
Technical Sanction Details
Technical Sanction No.: OD/354/3382/117960/412624/00073714/TS
Fund Sanction No.: 7873
Fund Sanction Amount (in Rs.): 400000
LABOUR STATEMENT
Sl.No. Activity Name Quantity (A) Unit Un-Skilled Skilled Semi-Skilled
462 562 512
Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B) Qty/Unit (B) Total Qty (A*B)
1 Earth Work (AR0102aa) : Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift - Earth work in hard soil or gravelly soil foundation & plinth within 50m. Initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per the direction of the Engineer-in-charge 6.63462624 Cubic Meter 0.516 3.42346713984 - - - -
2 Earth Work (AR0115a) : Filling foundation and plinth with crusher dust well watered and rammed - Filling foundation and plinth with crusher dust well watered and rammed including cost, conveyance, royalty, taxes of all materials, labours and T & P required for the work etc. complete and as per direction of Engineer-in charge. 34.3411992 Cubic Meter 0.1236 4.24457222112 - - - -
3 Concrete (AR0307) : Cement concrete (1:2:4)with 12mm size hard broken granite chips per 1cum - Cement concrete work with (1:2:4) using 12mm size hard granite(crusher broken) chips including hoisting and laying in position compacting to specified design section and curing for proper period with cost conveyance, royalty, taxes of all materials, labour and T&P required for the work etc. complete as per specificaion and direction of Engineer-in charge. 13.26925248 Cubic Meter 4.6 61.038561408 - - 0.68 9.0230916864
4 R.C.C. Work (AR0410c) : R.C.C. foundation , plinth band and footings bases of columns mass concrete precast slabs etc - Rigid and smooth centring and shuttering for R.C.C. works including false works and dismantling them after casting including cost of materials complete in ground floor R.C.C. foundation, plinth band and footings bases of columns mass concrete precast slabs, etc 65.96113 Square Meter - - 0.05 3.2980565 0.05 3.2980565
Total Qty 68.70660076896 12.3211481864 3.2980565
Rate Per Man Day 462 562 512
Total Amount 31742.44955526 6924.4852807568 1688.604928
Total Labour Amount (in Rs.): 40355.539764016